SKELLY-UNIVERSITY

Operated by RELIANCE ENERGY, INC. (P-5 700995) in the LANCASTER HILL (STRAWN) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 31429District 7CField 51770664Hydrogen sulphide fieldNGPA filingCondensateGasSaveExport
Value, all time
$741 k
Jan 1993 – Nov 2016
Value, last 12 filed months
$2 k
at the published price for each month
Months reported
287
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 16 leases and 16 wells, and the rule below applies to all of them.

Discovered
1961-12-04
as the register files it
Field class
Gas
the register's own label
Between wells
2,500 ft
minimum
From a lease line
660 ft
minimum

A drilling unit in this field needs at least 320 acres.

The register flags this field for hydrogen sulphide. That is a poisonous gas that occurs naturally in some formations. The flag is a property of the field as the Commission records it. It is not a measurement taken at this lease, and it is not a statement that gas is escaping anywhere.

The Commission's schedule remark for this field reads: IS FROM 6933 FT TO 6973 FT.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
NGPA2none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition185 bbl$4,198
GasProduction305,094 Mcf$736,379
Total$740,576

130,892 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.6980, -101.6572. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.69797, -101.65719 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
7,453 ft
1 wells filed one
Completion to plug
53.1 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,453 ft.

Completions filed
Oct 1963
1 of 1 wells
Plug dates filed
Nov 2016
1 of 1 wells

Last completion to plug: a median of 53.1 years across the 1 well that filed both dates, with the middle half between 53.1 years and 53.1 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-1051012317,453 ftOct 1963Nov 2016Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (287)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

287 months

Nov 20160042.492.64$0
Oct 20160946.193.09$28
Sep 201601241.553.10$37
Aug 201601941.442.92$56
Jul 201601741.622.92$50
Jun 201601545.352.69$40
May 2016372242.521.99$1,617
Apr 201602236.561.99$44
Mar 201602333.011.79$41
Feb 201602426.472.06$50
Jan 201602827.352.36$66
Dec 201503932.362.00$78
Nov 201504938.792.17$106
Oct 201506143.552.43$148
Sep 201505342.992.76$146
Aug 201506840.162.87$195
Jul 201509248.152.95$271
Jun 201508856.152.88$254
May 2015010355.212.96$304
Apr 201508849.822.71$238
Mar 2015011942.892.93$349
Feb 201509944.662.98$295
Jan 2015012343.433.10$381
Dec 2014013954.693.59$499
Nov 2014014870.464.25$629
Oct 2014015778.303.90$612
Sep 2014016686.164.05$672
Aug 2014016089.394.04$646
Jul 2014018096.564.18$752
Jun 2014019698.164.74$928
May 2014021494.734.73$1,011
Apr 2014021395.944.81$1,024
Mar 2014023195.895.06$1,168
Feb 2014021197.406.19$1,307
Jan 2014025090.404.86$1,215
Dec 2013026491.824.35$1,150
Nov 2013025288.853.74$942
Oct 2013028797.423.78$1,085
Sep 20130291104.113.72$1,082
Aug 20130286104.253.52$1,007
Jul 20130319102.523.72$1,186
Jun 2013029394.403.93$1,152
May 2013034994.834.15$1,448
Apr 2013028693.964.28$1,225
Mar 2013034993.623.91$1,366
Feb 2013032791.233.42$1,118
Jan 2013036191.603.42$1,235
Dec 2012037386.773.42$1,276
Nov 2012037286.953.62$1,348
Oct 2012040789.383.40$1,384
Sep 2012040094.672.92$1,167
Aug 2012042592.662.91$1,236
Jul 2012041785.133.02$1,260
Jun 2012044779.822.52$1,126
May 2012042791.612.49$1,063
Apr 20120419101.652.00$837
Mar 20120447105.052.22$993
Feb 20120426101.102.57$1,095
Jan 2012044998.092.73$1,228
Dec 2011046696.873.24$1,510
Nov 2011044495.723.31$1,470
Oct 2011048584.983.65$1,770
Sep 2011046483.623.99$1,849
Aug 2011048383.404.15$2,004
Jul 2011049494.144.52$2,232
Jun 2011047492.904.64$2,199
May 2011050098.134.40$2,202
Apr 20110492105.964.33$2,132
Mar 2011050696.364.06$2,053
Feb 2011045885.644.18$1,914
Jan 2011052786.504.59$2,418
Dec 2010051085.734.35$2,217
Nov 2010050380.843.80$1,909
Oct 2010053178.103.51$1,863
Sep 2010049872.633.98$1,982
Aug 2010049673.684.42$2,192
Jul 2010051772.554.74$2,449
Jun 2010049870.364.91$2,445
May 2010053171.124.24$2,249
Apr 2010055381.694.12$2,280
Mar 2010054178.394.39$2,374
Feb 2010051573.585.44$2,803
Jan 2010058174.365.96$3,465
Dec 2009058671.445.48$3,213
Nov 2009057274.593.75$2,146
Oct 2009059672.544.11$2,450
Sep 2009058165.543.06$1,781
Aug 2009051667.423.22$1,661
Jul 2009052061.133.46$1,802
Jun 2009051966.163.90$2,022
May 2009057454.743.93$2,253
Apr 2009052246.773.59$1,873
Mar 2009053642.144.06$2,176
Feb 2009051732.814.63$2,395
Jan 2009062035.865.37$3,330
Dec 2008062837.105.98$3,754
Nov 20080055.496.86$0
Oct 2008064275.246.92$4,444
Sep 20080579101.767.88$4,561
Aug 20080436114.228.48$3,699
Jul 20080588131.0811.39$6,697
Jun 20080388131.3313.03$5,057
May 20080640123.1711.57$7,408
Apr 20080631110.3110.45$6,597
Mar 20080495101.909.66$4,784
Feb 2008050192.538.77$4,394
Jan 2008068290.388.21$5,596
Dec 2007061688.337.30$4,498
Nov 2007051291.677.29$3,733
Oct 2007071382.856.92$4,935
Sep 2007067975.846.24$4,240
Aug 2007070969.066.39$4,529
Jul 2007053570.906.39$3,418
Jun 2007056762.007.55$4,280
May 2007062458.747.85$4,896
Apr 2007055659.617.81$4,340
Mar 2007031656.927.30$2,307
Feb 2007051355.108.22$4,215
Jan 2007055250.306.73$3,713
Dec 2006060756.656.92$4,199
Nov 2006069454.207.62$5,287
Oct 2006055054.906.01$3,308
Sep 2006067460.085.04$3,395
Aug 2006076768.717.34$5,630
Jul 2006080669.376.34$5,112
Jun 2006065166.286.38$4,156
May 2006074266.016.42$4,767
Apr 2006020264.397.36$1,487
Mar 2006032256.707.08$2,281
Feb 2006029057.597.75$2,248
Jan 2006046360.598.93$4,136
Dec 2005061854.9413.42$8,291
Nov 2005056254.6910.59$5,951
Oct 2005067658.3413.80$9,326
Sep 2005059561.4512.08$7,187
Aug 2005058861.519.80$5,761
Jul 2005063155.697.84$4,949
Jun 2005062552.337.38$4,613
May 2005069145.226.65$4,596
Apr 2005057549.207.36$4,232
Mar 2005080250.377.15$5,738
Feb 2005085145.226.31$5,371
Jan 2005088843.166.32$5,614
Dec 2004084239.866.75$5,684
Nov 2004073045.286.33$4,621
Oct 2004062049.706.52$4,039
Sep 2004038843.245.28$2,050
Aug 2004058742.375.55$3,258
Jul 2004072938.286.08$4,435
Jun 2004074836.106.43$4,812
May 2004060037.486.49$3,897
Apr 2004058934.475.86$3,451
Mar 2004066834.365.53$3,694
Feb 2004068132.455.51$3,752
Jan 2004076032.036.30$4,788
Dec 2003076630.266.30$4,827
Nov 2003071128.804.60$3,267
Oct 2003074028.174.76$3,522
Sep 2003075626.314.75$3,591
Aug 2003078229.765.13$4,011
Jul 2003080329.415.17$4,152
Jun 2003078028.565.98$4,667
May 2003084326.595.97$5,035
Apr 2003081626.675.41$4,412
Mar 2003087131.146.10$5,310
Feb 2003071933.487.93$5,699
Jan 2003083730.315.58$4,672
Dec 2002084626.914.85$4,106
Nov 2002081724.664.14$3,380
Oct 2002087826.464.23$3,713
Sep 2002087727.443.64$3,188
Aug 2002097625.963.16$3,088
Jul 2002089624.583.06$2,743
Jun 2002096623.733.34$3,225
May 200201,03124.663.58$3,695
Apr 200201,01423.653.51$3,561
Mar 200201,10322.003.10$3,422
Feb 200201,11618.222.38$2,651
Jan 2002094417.172.38$2,243
Dec 2001093416.932.36$2,208
Nov 2001096618.072.41$2,324
Oct 2001099419.782.53$2,514
Sep 200101,00624.262.25$2,265
Aug 200101,08124.873.05$3,300
Jul 200101,10123.933.20$3,520
Jun 200101,13924.563.82$4,356
May 200101,22525.524.31$5,276
Apr 200101,18324.685.34$6,312
Mar 200101,00924.545.38$5,425
Feb 2001088927.755.77$5,127
Jan 2001098827.478.40$8,298
Dec 200001,05626.889.12$9,633
Nov 200001,00832.215.66$5,703
Oct 200001,04831.235.15$5,392
Sep 200001,05631.875.19$5,477
Aug 200001,11229.644.54$5,049
Jul 200001,10228.534.09$4,507
Jun 200001,07029.304.40$4,705
May 200001,16227.263.68$4,276
Apr 200001,03124.513.12$3,213
Mar 200001,21428.422.86$3,472
Feb 200001,18227.622.73$3,223
Jan 200001,24425.272.48$3,086
Dec 199901,25624.282.42$3,044
Nov 199901,24323.192.43$3,025
Oct 199901,31820.982.80$3,695
Sep 199901,30821.752.62$3,425
Aug 199901,34719.262.88$3,873
Jul 199901,43217.892.37$3,397
Jun 199901,40715.942.36$3,323
May 199901,51315.792.32$3,512
Apr 199901,44615.102.21$3,193
Mar 199901,54112.471.84$2,833
Feb 199901,4509.981.82$2,636
Jan 199901,68910.381.90$3,209
Dec 199801,7399.201.77$3,084
Nov 199801,70510.892.19$3,727
Oct 199801,87412.421.97$3,690
Sep 199801,79212.592.08$3,732
Aug 199801,62611.301.91$3,101
Jul 199801,92611.742.24$4,309
Jun 199801,82911.242.24$4,092
May 199801,88312.622.21$4,155
Apr 199801,63613.042.51$4,099
Mar 199801,68512.802.31$3,891
Feb 199801,43113.952.30$3,290
Jan 199801,65314.702.15$3,562
Dec 199701,64116.322.41$3,957
Nov 199701,63818.193.09$5,059
Oct 199701,79519.253.15$5,654
Sep 199741,71617.742.95$5,142
Aug 199701,79817.862.55$4,593
Jul 199702,06917.582.25$4,649
Jun 199702,04917.242.26$4,625
May 199702,09618.972.31$4,839
Apr 199702,03717.882.08$4,243
Mar 199702,13118.951.94$4,132
Feb 199701,91520.492.21$4,224
Jan 199702,14923.483.54$7,607
Dec 199602,21523.32$0
Nov 199602,16821.97$0
Oct 199602,21723.31$0
Sep 199601,89122.22$0
Aug 199601,88020.26$0
Jul 199601,62319.55$0
Jun 199601,76318.73$0
May 199602,00519.43$0
Apr 199601,83221.51$0
Mar 199601,81019.38$0
Feb 199601,53016.98$0
Jan 199601,71317.07$0
Dec 199501,64617.19$0
Nov 199501,47416.00$0
Oct 199501,65815.43$0
Sep 199501,67416.18$0
Aug 199501,76615.92$0
Jul 199501,91215.24$0
Jun 199501,79816.41$0
May 199501,76917.56$0
Apr 199501,86117.73$0
Mar 199502,06816.44$0
Feb 199501,60816.58$0
Jan 199501,89615.92$0
Dec 199412,30115.03$15
Nov 199402,29615.90$0
Oct 199402,53115.58$0
Sep 199421,73515.29$31
Aug 199401,99616.13$0
Jul 199402,32517.56$0
Jun 199402,75917.09$0
May 199483,18315.88$127
Apr 199403,60214.14$0
Mar 199404,08612.46$0
Feb 199403,81612.50$0
Jan 199403,97212.66$0
Dec 199303,61412.33$0
Nov 199303,38114.49$0
Oct 199303,86015.85$0
Sep 199303,87015.03$0
Aug 199304,31615.66$0
Jul 199304,60315.46$0
Jun 199304,68316.79$0
May 199305,06417.68$0
Apr 199305,04218.05$0
Mar 199305,07418.14$0
Feb 19931334,42617.90$2,381
Jan 199304,58016.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Oct 2016 — as filed, then multipliedworked
Condensate             0 bbl  × $ 46.19 =         $0
Gas                    9 Mcf  × $  3.09 =        $28

────────────────────────────────────────────────────
Month total                                      $28

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/31429 is the state's own key, not one this site invented.