FIELDS 16

Operated by UPP OPERATING, LLC (P-5 875310) in the SAWYER (CANYON) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 58509District 7CField 81267333CondensateGasSaveExport
Value, all time
$134 k
Jan 1993 – May 2026
Value, last 12 filed months
$597
at the published price for each month
Months reported
401
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition7 bbl$555
GasProduction29,011 Mcf$133,536
Total$134,091

314 Mcf of this lease's gas, across 9 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.5126, -100.6035. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.51257, -100.60348 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
6,129 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 6,129 ft.

Completions filed
May 1974
1 of 1 wells

1 well

42-4353069236,129 ftMay 1974

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (401)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

401 months

May 2026015106.413.05$46
Apr 20260898.932.87$23
Mar 202602089.753.15$63
Feb 202601163.503.75$41
Jan 202601359.138.00$104
Dec 202502356.664.41$102
Nov 20250758.593.93$27
Oct 202501659.383.30$53
Sep 20250762.743.08$22
Aug 202501363.933.01$39
Jul 202501166.743.32$36
Jun 202501366.483.13$41
May 202502560.553.23$81
Apr 20250262.363.54$7
Mar 202502567.704.27$107
Feb 20250470.884.34$17
Jan 20250774.324.28$30
Dec 20240468.993.12$12
Nov 20240069.052.20$0
Oct 20240871.372.28$18
Sep 20240069.612.36$0
Aug 20240975.632.06$19
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 202401578.812.20$33
Apr 20240884.451.66$13
Mar 20240680.301.55$9
Feb 202401576.091.78$27
Jan 20240973.023.30$30
Dec 202301071.262.61$26
Nov 20230077.892.81$0
Oct 202301085.443.09$31
Sep 20230089.042.74$0
Aug 202301380.522.67$35
Jul 20230574.852.64$13
Jun 20230668.962.26$14
May 20230970.622.23$20
Apr 20230878.122.24$18
Mar 202301172.852.39$26
Feb 202301075.112.47$25
Jan 20230976.533.39$30
Dec 202201476.415.73$80
Nov 20220585.005.65$28
Oct 202201787.185.86$100
Sep 20220884.888.16$65
Aug 202201394.529.13$119
Jul 2022013101.587.54$98
Jun 202209115.097.98$72
May 2022016109.378.43$135
Apr 2022017104.226.84$116
Mar 2022024108.885.08$122
Feb 202201791.054.86$83
Jan 202201881.844.54$82
Dec 202102271.323.90$86
Nov 202101977.435.24$100
Oct 202101179.795.71$63
Sep 202101569.865.35$80
Aug 202101666.024.22$68
Jul 202101470.783.98$56
Jun 202101769.493.38$57
May 20210963.483.02$27
Apr 20210960.362.76$25
Mar 202102461.302.72$65
Feb 202101557.805.55$83
Jan 202102450.412.81$67
Dec 20200844.642.68$21
Nov 202001238.772.71$32
Oct 20200436.972.48$10
Sep 20200737.091.99$14
Aug 202002439.982.39$57
Jul 202002438.371.83$44
Jun 20200034.901.69$0
May 202003016.921.81$54
Apr 202001614.751.80$29
Mar 20200030.341.86$0
Feb 202002149.881.98$42
Jan 202001157.252.09$23
Dec 201902259.012.30$51
Nov 20190955.302.75$25
Oct 201901753.472.42$41
Sep 201901055.052.66$27
Aug 20190953.112.30$21
Jul 20190056.272.46$0
Jun 201907252.782.49$179
May 201901358.482.74$36
Apr 201904962.632.75$135
Mar 201902156.803.06$64
Feb 201902950.852.79$81
Jan 201901546.033.23$48
Dec 201806346.594.19$264
Nov 201805152.934.24$216
Oct 201802461.443.40$82
Sep 201802559.543.11$78
Aug 201804459.403.07$135
Jul 201802865.142.93$82
Jun 201804460.183.08$135
May 201804765.382.90$136
Apr 201803563.842.90$102
Mar 201801561.222.79$42
Feb 201802261.782.77$61
Jan 201803562.874.01$140
Dec 201701857.272.92$53
Nov 201702355.423.12$72
Oct 20170049.292.98$0
Sep 20170547.523.09$15
Aug 201701045.373.00$30
Jul 20170743.873.09$22
Jun 201704042.493.09$123
May 20170445.373.26$13
Apr 20170547.933.21$16
Mar 20170446.772.98$12
Feb 201701150.452.95$32
Jan 201704049.413.42$137
Dec 201604548.763.72$168
Nov 201602742.492.64$71
Oct 201604446.193.09$136
Sep 201603541.553.10$109
Aug 201605041.442.92$146
Jul 201604041.622.92$117
Jun 201604445.352.69$118
May 201601642.521.99$32
Apr 201604636.561.99$92
Mar 201604933.011.79$88
Feb 201603226.472.06$66
Jan 201604727.352.36$111
Dec 201505032.362.00$100
Nov 201505738.792.17$124
Oct 201502443.552.43$58
Sep 201501542.992.76$41
Aug 201501740.162.87$49
Jul 201501548.152.95$44
Jun 201503456.152.88$98
May 201503855.212.96$112
Apr 201501249.822.71$32
Mar 2015022542.892.93$660
Feb 2015029444.662.98$875
Jan 2015029143.433.10$902
Dec 2014019254.693.59$690
Nov 201402470.464.25$102
Oct 201402478.303.90$94
Sep 201405186.164.05$206
Aug 201405489.394.04$218
Jul 201405496.564.18$226
Jun 201405398.164.74$251
May 201405494.734.73$255
Apr 201405195.944.81$245
Mar 201405295.895.06$263
Feb 201403597.406.19$217
Jan 201404090.404.86$194
Dec 201304091.824.35$174
Nov 201303988.853.74$146
Oct 201304097.423.78$151
Sep 2013041104.113.72$152
Aug 2013042104.253.52$148
Jul 2013041102.523.72$152
Jun 201304094.403.93$157
May 201304194.834.15$170
Apr 201304293.964.28$180
Mar 201304493.623.91$172
Feb 201304091.233.42$137
Jan 201305691.603.42$192
Dec 201206086.773.42$205
Nov 201206286.953.62$225
Oct 201206389.383.40$214
Sep 2012012094.672.92$350
Aug 20120092.662.91$0
Jul 201203485.133.02$103
Jun 201204279.822.52$106
May 201207991.612.49$197
Apr 201200101.652.00$0
Mar 201200105.052.22$0
Feb 201200101.102.57$0
Jan 20120098.092.73$0
Dec 20110096.873.24$0
Nov 20110095.723.31$0
Oct 20110084.983.65$0
Sep 20110083.623.99$0
Aug 20110083.404.15$0
Jul 201104494.144.52$199
Jun 2011010792.904.64$496
May 201107998.134.40$348
Apr 2011068105.964.33$295
Mar 201107796.364.06$312
Feb 201105985.644.18$247
Jan 201108086.504.59$367
Dec 201008685.734.35$374
Nov 201008580.843.80$323
Oct 201006878.103.51$239
Sep 201009272.633.98$366
Aug 201008473.684.42$371
Jul 201007872.554.74$369
Jun 201005970.364.91$290
May 20100071.124.24$0
Apr 20100081.694.12$0
Mar 201003278.394.39$140
Feb 20100073.585.44$0
Jan 20100174.365.96$6
Dec 20090271.445.48$11
Nov 20090074.593.75$0
Oct 20090072.544.11$0
Sep 20090065.543.06$0
Aug 20090967.423.22$29
Jul 200901961.133.46$66
Jun 200901866.163.90$70
May 200904354.743.93$169
Apr 2009011446.773.59$409
Mar 2009013042.144.06$528
Feb 2009013232.814.63$612
Jan 2009010935.865.37$585
Dec 200804537.105.98$269
Nov 200804455.496.86$302
Oct 200805175.246.92$353
Sep 2008041101.767.88$323
Aug 2008047114.228.48$399
Jul 2008051131.0811.39$581
Jun 2008145131.3313.03$718
May 2008054123.1711.57$625
Apr 2008159110.3110.45$727
Mar 2008059101.909.66$570
Feb 200806392.538.77$553
Jan 200806490.388.21$525
Dec 200715888.337.30$512
Nov 200704191.677.29$299
Oct 200704382.856.92$298
Sep 200706775.846.24$418
Aug 2007011969.066.39$760
Jul 2007011570.906.39$735
Jun 2007011462.007.55$861
May 2007010358.747.85$808
Apr 200709859.617.81$765
Mar 2007010256.927.30$745
Feb 200705955.108.22$485
Jan 200706350.306.73$424
Dec 200606656.656.92$457
Nov 200606554.207.62$495
Oct 200607354.906.01$439
Sep 200606360.085.04$317
Aug 200606768.717.34$492
Jul 200606569.376.34$412
Jun 200616266.286.38$462
May 200607366.016.42$469
Apr 200607364.397.36$537
Mar 200607456.707.08$524
Feb 200606057.597.75$465
Jan 200606460.598.93$572
Dec 200506554.9413.42$872
Nov 200507154.6910.59$752
Oct 2005012658.3413.80$1,738
Sep 2005012661.4512.08$1,522
Aug 2005117261.519.80$1,747
Jul 2005020355.697.84$1,592
Jun 2005123352.337.38$1,772
May 2005123545.226.65$1,608
Apr 2005013049.207.36$957
Mar 200506850.377.15$487
Feb 200501445.226.31$88
Jan 2005022343.166.32$1,410
Dec 2004022139.866.75$1,492
Nov 2004021345.286.33$1,348
Oct 2004021149.706.52$1,375
Sep 2004023143.245.28$1,221
Aug 2004022242.375.55$1,232
Jul 2004016538.286.08$1,004
Jun 2004013036.106.43$836
May 2004013437.486.49$870
Apr 2004013034.475.86$762
Mar 2004013234.365.53$730
Feb 2004012732.455.51$700
Jan 2004013532.036.30$850
Dec 2003013430.266.30$844
Nov 2003013128.804.60$602
Oct 2003013328.174.76$633
Sep 2003012726.314.75$603
Aug 2003013329.765.13$682
Jul 2003025829.415.17$1,334
Jun 2003012828.565.98$766
May 2003013526.595.97$806
Apr 2003019026.675.41$1,027
Mar 2003013631.146.10$829
Feb 2003010633.487.93$840
Jan 2003011130.315.58$620
Dec 2002011226.914.85$544
Nov 2002011024.664.14$455
Oct 2002010826.464.23$457
Sep 2002011427.443.64$414
Aug 2002027525.963.16$870
Jul 2002025424.583.06$778
Jun 2002024723.733.34$825
May 2002024424.663.58$875
Apr 2002043423.653.51$1,524
Mar 2002056122.003.10$1,741
Feb 2002048818.222.38$1,159
Jan 2002057717.172.38$1,371
Dec 2001047616.932.36$1,125
Nov 2001037418.072.41$900
Oct 2001027419.782.53$693
Sep 2001025924.262.25$583
Aug 2001026724.873.05$815
Jul 2001028223.933.20$902
Jun 2001038424.563.82$1,468
May 2001034125.524.31$1,469
Apr 2001034024.685.34$1,814
Mar 2001049524.545.38$2,661
Feb 2001045727.755.77$2,636
Jan 2001042727.478.40$3,586
Dec 2000041626.889.12$3,795
Nov 2000044732.215.66$2,529
Oct 2000047031.235.15$2,418
Sep 2000037031.875.19$1,919
Aug 2000063829.644.54$2,897
Jul 2000029628.534.09$1,211
Jun 2000029129.304.40$1,280
May 2000029527.263.68$1,086
Apr 2000029124.513.12$907
Mar 2000033728.422.86$964
Feb 2000033327.622.73$908
Jan 2000026125.272.48$647
Dec 1999029224.282.42$708
Nov 1999032423.192.43$789
Oct 1999020220.982.80$566
Sep 1999011921.752.62$312
Aug 1999015119.262.88$434
Jul 1999019917.892.37$472
Jun 1999021815.942.36$515
May 1999035215.792.32$817
Apr 19990015.102.21$0
Mar 19990012.471.84$0
Feb 1999009.981.82$0
Jan 19990010.381.90$0
Dec 1998009.201.77$0
Nov 19980010.892.19$0
Oct 19980012.421.97$0
Sep 19980012.592.08$0
Aug 19980011.301.91$0
Jul 19980011.742.24$0
Jun 19980011.242.24$0
May 19980012.622.21$0
Apr 19980013.042.51$0
Mar 19980012.802.31$0
Feb 19980013.952.30$0
Jan 19980014.702.15$0
Dec 19970016.322.41$0
Nov 19970018.193.09$0
Oct 19970019.253.15$0
Sep 19970017.742.95$0
Aug 19970017.862.55$0
Jul 19970017.582.25$0
Jun 19970017.242.26$0
May 19970018.972.31$0
Apr 19970017.882.08$0
Mar 19970018.951.94$0
Feb 19970020.492.21$0
Jan 19970023.483.54$0
Dec 19960023.32$0
Nov 19960021.97$0
Oct 19960023.31$0
Sep 19960022.22$0
Aug 19960020.26$0
Jul 19960019.55$0
Jun 19960018.73$0
May 19960019.43$0
Apr 19960021.51$0
Mar 19960019.38$0
Feb 19960016.98$0
Jan 19960017.07$0
Dec 19950017.19$0
Nov 19950016.00$0
Oct 19950015.43$0
Sep 19950016.18$0
Aug 19950015.92$0
Jul 19950015.24$0
Jun 19950016.41$0
May 19950017.56$0
Apr 19950017.73$0
Mar 19950016.44$0
Feb 19950016.58$0
Jan 19950015.92$0
Dec 19940015.03$0
Nov 19940015.90$0
Oct 19940015.58$0
Sep 19940015.29$0
Aug 19940016.13$0
Jul 19940017.56$0
Jun 19940017.09$0
May 19940015.88$0
Apr 19940014.14$0
Mar 19940012.46$0
Feb 19940012.50$0
Jan 19940012.66$0
Dec 19930012.33$0
Nov 19930014.49$0
Oct 19930015.85$0
Sep 199301015.03$0
Aug 199305915.66$0
Jul 19930215.46$0
Jun 199308216.79$0
May 199307317.68$0
Apr 199307018.05$0
Mar 199301018.14$0
Feb 19930217.90$0
Jan 19930616.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                   15 Mcf  × $  3.05 =        $46

────────────────────────────────────────────────────
Month total                                      $46

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/58509 is the state's own key, not one this site invented.