MILLSPAUGH, AUSTIN C. ET UX "B"

Operated by SCOUT ENERGY MANAGEMENT LLC (P-5 760218) in the OZONA (CANYON SAND) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 93139District 7CField 67995200NGPA filingCondensateGasSaveExport
Value, all time
$228 k
Jan 1993 – May 2026
Value, last 12 filed months
$17
at the published price for each month
Months reported
401
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 2,312 leases and 2,323 wells, and the rule below applies to all of them.

Discovered
1962-02-23
as the register files it
Field class
Oil and gas
the register's own label
Between wells
600 ft
minimum
From a lease line
660 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2006-09-12.

The Commission's schedule remark for this field reads: ZONE TO BE SET UP IN OZONA (CANYON SAND, OIL).

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition3 bbl$201
GasProduction62,131 Mcf$227,863
Total$228,064

9,297 Mcf of this lease's gas, across 47 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.5303, -101.5479. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.53028, -101.54786 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
7,344 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,344 ft.

Completions filed
Mar 1981
1 of 1 wells

1 well

42-105331921037,344 ftMar 1981

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (401)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

401 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250566.743.32$17
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 202518762.363.54$371
Mar 202518767.704.27$439
Feb 202517470.884.34$392
Jan 20250074.324.28$0
Dec 202408368.993.12$259
Nov 202408569.052.20$187
Oct 202408971.372.28$203
Sep 202409269.612.36$218
Aug 202409075.632.06$186
Jul 202409779.932.15$208
Jun 2024010278.082.63$269
May 2024011578.812.20$253
Apr 2024011984.451.66$197
Mar 2024012880.301.55$198
Feb 2024012176.091.78$216
Jan 2024012773.023.30$419
Dec 2023012771.262.61$332
Nov 2023011077.892.81$309
Oct 202308085.443.09$247
Sep 202308689.042.74$235
Aug 202309880.522.67$262
Jul 2023010774.852.64$283
Jun 2023011568.962.26$260
May 2023013370.622.23$296
Apr 2023010678.122.24$237
Mar 2023011472.852.39$273
Feb 2023010275.112.47$252
Jan 2023010676.533.39$359
Dec 2022010876.415.73$619
Nov 2022010985.005.65$615
Oct 202209187.185.86$534
Sep 202208584.888.16$694
Aug 202208994.529.13$812
Jul 2022084101.587.54$634
Jun 2022084115.097.98$670
May 2022089109.378.43$751
Apr 20220109104.226.84$745
Mar 2022097108.885.08$492
Feb 202209591.054.86$462
Jan 2022020981.844.54$948
Dec 2021010271.323.90$398
Nov 202108177.435.24$424
Oct 2021011079.795.71$629
Sep 202109769.865.35$519
Aug 202107066.024.22$295
Jul 2021010070.783.98$398
Jun 202108469.493.38$284
May 2021013963.483.02$419
Apr 202109160.362.76$251
Mar 2021011061.302.72$299
Feb 202107557.805.55$416
Jan 202106550.412.81$183
Dec 202008844.642.68$235
Nov 202009638.772.71$260
Oct 2020010236.972.48$253
Sep 202008637.091.99$171
Aug 202009539.982.39$227
Jul 202009738.371.83$177
Jun 202009634.901.69$162
May 2020010216.921.81$185
Apr 2020011314.751.80$204
Mar 2020010530.341.86$195
Feb 2020012049.881.98$238
Jan 2020012657.252.09$264
Dec 2019013759.012.30$316
Nov 2019011855.302.75$325
Oct 2019011653.472.42$281
Sep 2019010455.052.66$276
Aug 2019010453.112.30$240
Jul 2019011856.272.46$290
Jun 2019011652.782.49$289
May 2019011658.482.74$318
Apr 2019011962.632.75$327
Mar 2019012156.803.06$371
Feb 2019011150.852.79$310
Jan 2019010846.033.23$349
Dec 2018012346.594.19$515
Nov 2018011652.934.24$492
Oct 2018010761.443.40$364
Sep 201806559.543.11$202
Aug 201807559.403.07$230
Jul 201807565.142.93$220
Jun 201809860.183.08$302
May 201809265.382.90$267
Apr 2018011163.842.90$322
Mar 2018011761.222.79$326
Feb 2018011061.782.77$304
Jan 2018012462.874.01$497
Dec 2017013257.272.92$386
Nov 2017013255.423.12$412
Oct 2017014249.292.98$424
Sep 2017011347.523.09$349
Aug 2017011845.373.00$355
Jul 2017012443.873.09$383
Jun 2017012242.493.09$377
May 2017013345.373.26$434
Apr 2017013247.933.21$424
Mar 2017014546.772.98$433
Feb 2017012650.452.95$372
Jan 2017014749.413.42$503
Dec 2016015548.763.72$577
Nov 2016014842.492.64$391
Oct 2016014846.193.09$457
Sep 2016012541.553.10$388
Aug 2016013341.442.92$389
Jul 2016014241.622.92$415
Jun 2016014445.352.69$387
May 2016017042.521.99$338
Apr 2016014636.561.99$291
Mar 2016016733.011.79$300
Feb 2016014626.472.06$301
Jan 2016017027.352.36$402
Dec 2015016532.362.00$330
Nov 2015017638.792.17$381
Oct 201507043.552.43$170
Sep 2015011742.992.76$323
Aug 2015010640.162.87$304
Jul 2015010848.152.95$318
Jun 2015012656.152.88$363
May 2015012755.212.96$375
Apr 2015012949.822.71$349
Mar 2015015642.892.93$458
Feb 2015012344.662.98$366
Jan 2015013443.433.10$415
Dec 2014014954.693.59$535
Nov 2014013670.464.25$578
Oct 2014013278.303.90$515
Sep 2014013086.164.05$526
Aug 2014012489.394.04$500
Jul 2014013096.564.18$543
Jun 2014013498.164.74$635
May 2014015394.734.73$723
Apr 2014014595.944.81$697
Mar 2014012495.895.06$627
Feb 2014014697.406.19$904
Jan 2014014790.404.86$715
Dec 2013014991.824.35$649
Nov 2013012588.853.74$467
Oct 201309997.423.78$374
Sep 20130102104.113.72$379
Aug 20130135104.253.52$476
Jul 20130124102.523.72$461
Jun 2013013694.403.93$535
May 2013011794.834.15$485
Apr 2013014993.964.28$638
Mar 2013013093.623.91$509
Feb 2013012791.233.42$434
Jan 2013014391.603.42$489
Dec 2012014286.773.42$486
Nov 2012014086.953.62$507
Oct 2012013889.383.40$469
Sep 2012012794.672.92$371
Aug 2012012092.662.91$349
Jul 2012012485.133.02$375
Jun 2012013279.822.52$333
May 2012014191.612.49$351
Apr 20120126101.652.00$252
Mar 20120151105.052.22$336
Feb 20120160101.102.57$411
Jan 2012014098.092.73$383
Dec 2011013896.873.24$447
Nov 2011013295.723.31$437
Oct 2011014884.983.65$540
Sep 2011010983.623.99$434
Aug 2011010783.404.15$444
Jul 2011012994.144.52$583
Jun 2011013392.904.64$617
May 2011015198.134.40$665
Apr 20110137105.964.33$594
Mar 2011014296.364.06$576
Feb 2011012885.644.18$535
Jan 2011014586.504.59$665
Dec 2010016185.734.35$700
Nov 2010015580.843.80$588
Oct 2010016078.103.51$561
Sep 2010013072.633.98$517
Aug 2010012073.684.42$530
Jul 2010016072.554.74$758
Jun 2010011270.364.91$550
May 2010017471.124.24$737
Apr 2010013081.694.12$536
Mar 2010019078.394.39$834
Feb 2010013973.585.44$756
Jan 2010013274.365.96$787
Dec 2009013171.445.48$718
Nov 2009013874.593.75$518
Oct 2009012672.544.11$518
Sep 2009011965.543.06$365
Aug 2009011167.423.22$357
Jul 2009015461.133.46$534
Jun 200909766.163.90$378
May 200909454.743.93$369
Apr 200909846.773.59$352
Mar 2009010942.144.06$442
Feb 2009010732.814.63$496
Jan 2009014635.865.37$784
Dec 2008015137.105.98$903
Nov 2008015155.496.86$1,036
Oct 2008014775.246.92$1,018
Sep 20080104101.767.88$819
Aug 20080112114.228.48$950
Jul 20080174131.0811.39$1,982
Jun 20080180131.3313.03$2,346
May 20080186123.1711.57$2,153
Apr 20080179110.3110.45$1,871
Mar 20080180101.909.66$1,740
Feb 2008019892.538.77$1,737
Jan 2008021290.388.21$1,740
Dec 2007026288.337.30$1,913
Nov 2007025391.677.29$1,845
Oct 2007038982.856.92$2,693
Sep 2007024875.846.24$1,549
Aug 2007022569.066.39$1,437
Jul 2007022870.906.39$1,456
Jun 2007022462.007.55$1,691
May 2007022158.747.85$1,734
Apr 2007018459.617.81$1,436
Mar 2007020656.927.30$1,504
Feb 2007018555.108.22$1,520
Jan 2007023050.306.73$1,547
Dec 2006018956.656.92$1,308
Nov 2006022654.207.62$1,722
Oct 2006023054.906.01$1,383
Sep 2006028060.085.04$1,410
Aug 2006023568.717.34$1,725
Jul 2006021269.376.34$1,345
Jun 2006019866.286.38$1,264
May 2006023566.016.42$1,510
Apr 2006020264.397.36$1,487
Mar 2006023656.707.08$1,672
Feb 2006019157.597.75$1,480
Jan 2006021760.598.93$1,939
Dec 2005014854.9413.42$1,985
Nov 200503954.6910.59$413
Oct 200507458.3413.80$1,021
Sep 2005015961.4512.08$1,921
Aug 2005019061.519.80$1,861
Jul 2005016855.697.84$1,318
Jun 2005024152.337.38$1,779
May 2005015545.226.65$1,031
Apr 2005019549.207.36$1,435
Mar 2005023050.377.15$1,646
Feb 2005018145.226.31$1,142
Jan 2005020243.166.32$1,277
Dec 2004017739.866.75$1,195
Nov 2004016945.286.33$1,070
Oct 2004022249.706.52$1,446
Sep 2004019143.245.28$1,009
Aug 2004019842.375.55$1,099
Jul 2004020038.286.08$1,217
Jun 2004017436.106.43$1,119
May 2004020137.486.49$1,305
Apr 2004020434.475.86$1,195
Mar 2004012834.365.53$708
Feb 2004016732.455.51$920
Jan 2004024232.036.30$1,525
Dec 2003020230.266.30$1,273
Nov 2003020928.804.60$960
Oct 2003020728.174.76$985
Sep 2003020526.314.75$974
Aug 2003018829.765.13$964
Jul 2003020529.415.17$1,060
Jun 2003018428.565.98$1,101
May 2003018626.595.97$1,111
Apr 2003018426.675.41$995
Mar 2003019531.146.10$1,189
Feb 2003022233.487.93$1,760
Jan 200308230.315.58$458
Dec 2002011926.914.85$578
Nov 2002015824.664.14$654
Oct 2002023926.464.23$1,011
Sep 2002018327.443.64$665
Aug 2002020725.963.16$655
Jul 2002018624.583.06$569
Jun 2002017223.733.34$574
May 2002012224.663.58$437
Apr 2002011723.653.51$411
Mar 2002016122.003.10$500
Feb 2002016418.222.38$390
Jan 2002021217.172.38$504
Dec 2001020716.932.36$489
Nov 2001014918.072.41$358
Oct 2001022819.782.53$577
Sep 2001017724.262.25$398
Aug 2001013324.873.05$406
Jul 2001015623.933.20$499
Jun 2001020924.563.82$799
May 2001022425.524.31$965
Apr 2001021024.685.34$1,120
Mar 2001023424.545.38$1,258
Feb 2001018327.755.77$1,055
Jan 2001018227.478.40$1,529
Dec 200006326.889.12$575
Nov 2000015932.215.66$900
Oct 2000018931.235.15$973
Sep 2000013731.875.19$711
Aug 2000017929.644.54$813
Jul 2000016128.534.09$658
Jun 2000017629.304.40$774
May 2000017327.263.68$637
Apr 2000018424.513.12$573
Mar 2000019328.422.86$552
Feb 2000018527.622.73$504
Jan 2000020725.272.48$513
Dec 1999021524.282.42$521
Nov 1999022323.192.43$543
Oct 1999030820.982.80$864
Sep 1999021321.752.62$558
Aug 1999024519.262.88$705
Jul 1999020617.892.37$489
Jun 1999033615.942.36$794
May 1999024415.792.32$566
Apr 1999022215.102.21$490
Mar 1999025912.471.84$476
Feb 199901889.981.82$342
Jan 1999025310.381.90$481
Dec 199802599.201.77$459
Nov 1998023010.892.19$503
Oct 1998024712.421.97$486
Sep 1998029512.592.08$614
Aug 1998030711.301.91$586
Jul 1998029511.742.24$660
Jun 1998028211.242.24$631
May 1998025512.622.21$563
Apr 1998020813.042.51$521
Mar 1998026412.802.31$610
Feb 1998013413.952.30$308
Jan 1998014914.702.15$321
Dec 1997013916.322.41$335
Nov 1997028018.193.09$865
Oct 1997026919.253.15$847
Sep 1997026617.742.95$786
Aug 1997025817.862.55$659
Jul 1997023517.582.25$528
Jun 1997026617.242.26$600
May 1997042418.972.31$979
Apr 1997039517.882.08$823
Mar 1997019518.951.94$378
Feb 1997022020.492.21$485
Jan 1997020723.483.54$733
Dec 1996026323.32$0
Nov 1996022621.97$0
Oct 1996014623.31$0
Sep 1996016222.22$0
Aug 1996024720.26$0
Jul 1996028519.55$0
Jun 1996028318.73$0
May 1996025419.43$0
Apr 1996028821.51$0
Mar 1996027719.38$0
Feb 1996023816.98$0
Jan 1996018817.07$0
Dec 1995026217.19$0
Nov 1995026216.00$0
Oct 1995036615.43$0
Sep 1995028116.18$0
Aug 1995026615.92$0
Jul 199502815.24$0
Jun 1995028016.41$0
May 19950017.56$0
Apr 199506217.73$0
Mar 199508916.44$0
Feb 199509516.58$0
Jan 1995015015.92$0
Dec 1994017115.03$0
Nov 1994016815.90$0
Oct 1994020615.58$0
Sep 1994016415.29$0
Aug 1994011616.13$0
Jul 1994021717.56$0
Jun 1994013417.09$0
May 1994019115.88$0
Apr 1994011814.14$0
Mar 1994016412.46$0
Feb 1994026312.50$0
Jan 1994015512.66$0
Dec 1993023712.33$0
Nov 1993019414.49$0
Oct 199309715.85$0
Sep 1993013515.03$0
Aug 1993012415.66$0
Jul 1993018815.46$0
Jun 1993024916.79$0
May 1993011417.68$0
Apr 1993022618.05$0
Mar 1993026218.14$0
Feb 1993024917.90$0
Jan 1993015716.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Jul 2025 — as filed, then multipliedworked
Condensate             0 bbl  × $ 66.74 =         $0
Gas                    5 Mcf  × $  3.32 =        $17

────────────────────────────────────────────────────
Month total                                      $17

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/93139 is the state's own key, not one this site invented.