BALDRIDGE

Operated by MERIT ENERGY COMPANY (P-5 561136) in the LEE HARRISON field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Oil lease lease 11882District 8AField 52872001Hydrogen sulphide fieldOilCasinghead gasSaveExport
Value, all time
$373 k
Jan 1993 – Mar 2007
Value, last 12 filed months
$34 k
at the published price for each month
Months reported
171
no gaps in the span
Streams
2
oil, casinghead gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 97 leases and 321 wells, and the rule below applies to all of them.

Discovered
1941-08-20
as the register files it
Field class
Oil
the register's own label
Between wells
660 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2008-12-16.

The register flags this field for hydrogen sulphide. That is a poisonous gas that occurs naturally in some formations. The flag is a property of the field as the Commission records it. It is not a measurement taken at this lease, and it is not a statement that gas is escaping anywhere.

The Commission's schedule remark for this field reads: 5162',AMENDED SPACING,ADOPTED 20 ACRE OPTION WITH 1500'DIAGONAL.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
OilDisposition13,967 bbl$372,742
Casinghead gasProduction92 Mcf$115
Total$372,857

48 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 33.5643, -101.6453. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

33.56428, -101.64528 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
no depth filed
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

1 well

42-303000421

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (171)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

171 months

Mar 20070056.927.30$0
Feb 20070055.108.22$0
Jan 20070050.306.73$0
Dec 20060056.656.92$0
Nov 20060054.207.62$0
Oct 20060054.906.01$0
Sep 20060060.085.04$0
Aug 20060068.717.34$0
Jul 2006174069.376.34$12,070
Jun 2006164066.286.38$10,870
May 20060066.016.42$0
Apr 2006174064.397.36$11,204
Mar 20060056.707.08$0
Feb 2006164057.597.75$9,445
Jan 2006169060.598.93$10,240
Dec 20050054.9413.42$0
Nov 2005165054.6910.59$9,024
Oct 20050058.3413.80$0
Sep 2005167061.4512.08$10,262
Aug 20050061.519.80$0
Jul 2005165055.697.84$9,189
Jun 20050052.337.38$0
May 2005174045.226.65$7,868
Apr 2005156049.207.36$7,675
Mar 20050050.377.15$0
Feb 2005170045.226.31$7,687
Jan 20050043.166.32$0
Dec 2004170039.866.75$6,776
Nov 20040045.286.33$0
Oct 2004166049.706.52$8,250
Sep 20040043.245.28$0
Aug 2004166042.375.55$7,033
Jul 20040038.286.08$0
Jun 2004165036.106.43$5,957
May 20040037.486.49$0
Apr 2004169034.475.86$5,825
Mar 2004170034.365.53$5,841
Feb 20040032.455.51$0
Jan 2004157032.036.30$5,029
Dec 20030030.266.30$0
Nov 2003152028.804.60$4,378
Oct 20030028.174.76$0
Sep 2003169026.314.75$4,446
Aug 20030029.765.13$0
Jul 2003159029.415.17$4,676
Jun 2003170028.565.98$4,855
May 2003157026.595.97$4,175
Apr 20030026.675.41$0
Mar 2003153031.146.10$4,764
Feb 20030033.487.93$0
Jan 2003163030.315.58$4,941
Dec 2002157026.914.85$4,225
Nov 20020024.664.14$0
Oct 20020026.464.23$0
Sep 2002161027.443.64$4,418
Aug 20020025.963.16$0
Jul 2002151024.583.06$3,712
Jun 2002172023.733.34$4,082
May 2002165024.663.58$4,069
Apr 20020023.653.51$0
Mar 2002156022.003.10$3,432
Feb 20020018.222.38$0
Jan 2002145017.172.38$2,490
Dec 20010016.932.36$0
Nov 20010018.072.41$0
Oct 2001147019.782.53$2,908
Sep 2001166024.262.25$4,027
Aug 20010024.873.05$0
Jul 2001158023.933.20$3,781
Jun 2001172024.563.82$4,224
May 2001161025.524.31$4,109
Apr 20010024.685.34$0
Mar 2001153024.545.38$3,755
Feb 2001165027.755.77$4,579
Jan 20010027.478.40$0
Dec 2000157026.889.12$4,220
Nov 20000032.215.66$0
Oct 20000031.235.15$0
Sep 2000197131.875.19$6,284
Aug 20000129.644.54$5
Jul 2000159128.534.09$4,540
Jun 20000129.304.40$4
May 2000157127.263.68$4,284
Apr 2000164124.513.12$4,023
Mar 20000128.422.86$3
Feb 2000160127.622.73$4,422
Jan 20000125.272.48$2
Dec 1999162124.282.42$3,936
Nov 1999158123.192.43$3,666
Oct 19990120.982.80$3
Sep 1999168121.752.62$3,657
Aug 19990119.262.88$3
Jul 19990017.892.37$0
Jun 19990115.942.36$2
May 19990115.792.32$2
Apr 1999163115.102.21$2,464
Mar 19990112.471.84$2
Feb 199915619.981.82$1,559
Jan 19990110.381.90$2
Dec 199815719.201.77$1,446
Nov 1998168110.892.19$1,832
Oct 19980112.421.97$2
Sep 1998159112.592.08$2,004
Aug 19980111.301.91$2
Jul 1998162111.742.24$1,904
Jun 1998165111.242.24$1,857
May 1998164112.622.21$2,072
Apr 19980113.042.51$3
Mar 19980112.802.31$2
Feb 1998153113.952.30$2,137
Jan 19980114.702.15$2
Dec 19970116.322.41$2
Nov 19970118.193.09$3
Oct 1997169119.253.15$3,256
Sep 19970117.742.95$3
Aug 19970117.862.55$3
Jul 1997165117.582.25$2,903
Jun 19970117.242.26$2
May 19970118.972.31$2
Apr 19970117.882.08$2
Mar 1997157118.951.94$2,977
Feb 19970120.492.21$2
Jan 1997165123.483.54$3,878
Dec 19960123.32$0
Nov 1996166121.97$3,647
Oct 19960123.31$0
Sep 19960122.22$0
Aug 1996156120.26$3,161
Jul 19960119.55$0
Jun 1996166118.73$3,109
May 19960119.43$0
Apr 1996165121.51$3,549
Mar 19960119.38$0
Feb 1996159116.98$2,700
Jan 19960117.07$0
Dec 1995164117.19$2,819
Nov 19950116.00$0
Oct 1995161115.43$2,484
Sep 19950116.18$0
Aug 1995163115.92$2,595
Jul 19950115.24$0
Jun 1995165116.41$2,708
May 19950117.56$0
Apr 19950117.73$0
Mar 1995183116.44$3,009
Feb 19950116.58$0
Jan 1995148115.92$2,356
Dec 19940115.03$0
Nov 1994148115.90$2,353
Oct 19940115.58$0
Sep 1994144115.29$2,202
Aug 1994146116.13$2,355
Jul 19940117.56$0
Jun 1994147117.09$2,512
May 19940115.88$0
Apr 1994146114.14$2,064
Mar 1994147112.46$1,832
Feb 19940112.50$0
Jan 1994146112.66$1,848
Dec 19930112.33$0
Nov 1993150114.49$2,174
Oct 1993159115.85$2,520
Sep 19930115.03$0
Aug 1993145115.66$2,271
Jul 1993148115.46$2,288
Jun 19930116.79$0
May 1993146117.68$2,581
Apr 1993153118.05$2,762
Mar 19930118.14$0
Feb 1993149117.90$2,667
Jan 1993155116.93$2,624

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Jul 2006 — as filed, then multipliedworked
Oil                  174 bbl  × $ 69.37 =    $12,070
Casinghead gas         0 Mcf  × $  6.34 =         $0

────────────────────────────────────────────────────
Month total                                  $12,070

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 8A/O/11882 is the state's own key, not one this site invented.