GATEWAY RED OAK LLC
Miles
11
Systems
4
Counties
5
Segments
10
The Railroad Commission's inspection files, covering Aug 1 2015 to Aug 7 2026, record no inspection of this operator. That is what the files hold. It is not a statement that none took place.
The Railroad Commission's docket file published 2025-02-05 names no case against this operator. That is what the file holds. It is not a statement that none exists.
Pipeline systems
The named networks GATEWAY RED OAK LLC operates. One physical pipeline is usually filed as hundreds of segments, so a system — not a segment — is the unit worth reading.
| System | Miles | Segments | Counties |
|---|---|---|---|
| CENTER TYSON LINE | 4.3 | 3 | 1 |
| GATEWAY RED OAK PIPLINE SYSTEM | 4.2 | 5 | 2 |
| SEGUIN PIPELINE | 1.6 | 1 | 1 |
| GATEWAY RED OAK PIPELINE SYSTEM | 0.9 | 1 | 1 |