JEFFERSON PIPELINE COMPANY
Inspections and violations
What the Railroad Commission's field inspectors recorded at this operator's facilities. An inspection count tracks how much this operator runs in Texas; the rate beside it is what the inspectors found.
| Rule | What the Commission cited it for | Violations |
|---|---|---|
| SWR 3.2(a) | Access to Property | 1 |
| SWR 3.3(1) | Entrance Sign | 1 |
What the Commission did
- Notice of Violation 2
From the Commission's inspection and violation files, covering Aug 1 2015 to Aug 7 2026. The two are separate files with no key between them, so the violations here are not a subset of the 1 inspections that found this operator out of compliance — they are counted from their own file.
The Railroad Commission's docket file published 2025-02-05 names no case against this operator. That is what the file holds. It is not a statement that none exists.
Pipeline systems
The named networks JEFFERSON PIPELINE COMPANY operates. One physical pipeline is usually filed as hundreds of segments, so a system — not a segment — is the unit worth reading.
| System | Miles | Segments | Counties |
|---|---|---|---|
| ROCKY CREEK LATERAL | 7.5 | 17 | 2 |