ARROYO UNIT 14-1

API 15187205170001 · Stanton County, Kansas · ARROYO field

Authorized Injection Well
API
15187205170001
Operator
BEREXCO LLC
County
Stanton
Field
ARROYO
Spudded
2019-08-01
Completed
2019-08-01
Measured depth
5,514 ft

Injection

84 monthly filings with Kansas, Jan 2019 to Dec 2025. Fluid is in barrels and gas is in MCF; the two are never added.

Well type
Authorized Injection Well
Injection zone
Morrow
Cumulative fluid injected
280,678 bbl
Cumulative gas injected
0 MCF
MonthFluid injected (bbl)Gas injected (MCF)Max pressure (psi)Days
Dec 20250000
Nov 20250000
Oct 20250000
Sep 20250000
Aug 20250000
Jul 20250000
Jun 20250000
May 20250000
Apr 20250000
Mar 20250000
Feb 20250000
Jan 20250000
Dec 20240000
Nov 20240000
Oct 20240000
Sep 20240000
Aug 20240000
Jul 20240000
Jun 20240000
May 20240000
Apr 20240000
Mar 20240000
Feb 20240000
Jan 20240000
Dec 202300—0
Nov 202300—0
Oct 202300—0
Sep 202300—0
Aug 202300—0
Jul 202300—0
Jun 202300—0
May 20237,0600025
Apr 20237,0140027
Mar 20236,9850027
Feb 20237,4650028
Jan 20237,5470031
Dec 20227,6950031
Nov 20226,7430030
Oct 20221,821006
Sep 20228,4540029
Aug 202212,1110031
Jul 20228,7790031
Jun 20225,4460027
May 202213,8630031
Apr 202213,5300030
Mar 202215,2600031
Feb 202213,2180028
Jan 202213,4900031
Dec 202114,5250031
Nov 202114,6120030
Oct 202115,1030031
Sep 202114,4190030
Aug 202115,6030031
Jul 202114,6320031
Jun 202115,5590030
May 202114,9120031
Apr 20214,8320030
Mar 202100—0
Feb 202100—0
Jan 202100—0
Dec 202000—0
Nov 202000—0
Oct 202000—0
Sep 202000—0
Aug 202000—0
Jul 202000—0
Jun 202000—0
May 202000—0
Apr 202000—0
Mar 202000—0
Feb 202000—0
Jan 202000—0
Dec 20190000
Nov 20190000
Oct 20190000
Sep 20190000
Aug 20190000
Jul 20190000
Jun 20190000
May 20190000
Apr 20190000
Mar 20190000
Feb 20190000
Jan 20190000

A dash is a month the well filed with no figure in that column.

Location

37.523561, -101.777757

37.52356, -101.77776 · Surface location as filed with Kansas

Every well in Stanton County, Kansas

Kansas state record, from KS_wells_ks_wells.parquet. Corpus built 2026-09-11.