SW HOMER GOODWIN SAND UNIT #8-11
API 3501924077 · Carter County, Oklahoma
ACOIL
Completion
Oklahoma files 1 completion report for this well.
Completion 1
STRAIGHT HOLEACOILSpudded
1991-09-28
Drilling finished
1991-10-12
Completed
1991-10-25
First production
1991-11-03
Total depth
3,700 ft
Operator
J & J OIL COMPANY LLC
Interval
| Formation | Produced | Perforated (ft) |
|---|---|---|
| GOODWIN | TA | 3,398–3,468 |
Casing
| String | Size (in) | Weight (lb/ft) | Grade | Set (ft) | Cement (sacks) |
|---|---|---|---|---|---|
| PRODUCTION | 5 1/2 | 15.5 | K-55 | 3,698 | 300 |
| SURFACE | 8 5/8 | 23 | X-42 | 534 | 265 |
Drilling permit
Oklahoma files 1 application to drill this well, naming 2 target formations. A permit records what an operator asked to do, not what it did. A target formation is where the operator aimed, and the hole may have missed it, stopped short of it or never been drilled.
Filed 1991-09-06
WRADRPermit API
35019240770000
Operator
NOBLE ENERGY PRODUCTION INC
Well type
OIL
Approved
1991-09-06
Expires
1992-03-20
Proposed depth
4,000 ft
Surface casing
500 ft
Ground elevation
990 ft
Target formations
| Formation | Expected top (ft) |
|---|---|
| SIMS | 2,500 |
| GOODWIN | 3,300 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Location
34.466565, -97.436227
34.46657, -97.43623 · Surface location as filed with Oklahoma⌘ or Ctrl + scroll to zoom
Every well in Carter County, Oklahoma