JOELLEN #1-24

API 3504924769 · Garvin County, Oklahoma

ACOIL
API
3504924769
Operator
STEWART INC
County
Garvin

Completions

Oklahoma files 3 completion reports for this well. 2 carry a production test the operator filed.

Completion 1

ACOIL
Spudded
2010-01-16
Drilling finished
2010-02-02
Completed
2010-11-04
First production
2010-08-18
Total depth
5,705 ft
Operator
STEWART INC

Casing

StringSize (in)Weight (lb/ft)GradeSet (ft)Cement (sacks)
—————0

Completion 2

DIRECTIONAL HOLEACOIL
Spudded
2010-01-16
Drilling finished
2010-02-02
Completed
2010-11-04
Recompleted
2012-07-15
First production
2010-08-18
Total depth
5,705 ft
Operator
STEWART INC

Intervals

FormationProducedPerforated (ft)Treatment
1ST BROMIDEOIL5,540–5,544Acid
2ND BROMIDEOIL5,589–5,611Acid

Production tests

TestedOil (bbl/d)Gas (MCF/d)Water (bbl/d)Gravity (°API)Shut-in (psi)Choke
2010-11-05577106490—
2012-07-15100117480—

A production test is one measurement the operator made on one day and filed with Oklahoma. It is not a monthly average and it does not describe how the well produced afterwards. The choke size is shown exactly as filed: Oklahoma records it in inches on some reports and in sixty-fourths of an inch on others, and names the unit on neither. A dash is a measurement Oklahoma did not file, or one it filed outside any physically possible range.

Casing

StringSize (in)Weight (lb/ft)GradeSet (ft)Cement (sacks)
PRODUCTION5 1/215.5 & 17J-55, LT & C5,668200
SURFACE8 5/824J-55301280

Completion 3

DIRECTIONAL HOLEACOIL
Spudded
2010-01-16
Drilling finished
2010-02-02
Completed
2010-11-04
Recompleted
2014-04-01
First production
2010-08-18
Total depth
5,705 ft
Operator
STEWART INC

Interval

FormationProducedPerforated (ft)
1ST BROMIDEOIL5,522–5,527

Production test

TestedOil (bbl/d)Gas (MCF/d)Water (bbl/d)Gravity (°API)Shut-in (psi)Choke
2014-03-0717519042012/64

A production test is one measurement the operator made on one day and filed with Oklahoma. It is not a monthly average and it does not describe how the well produced afterwards. The choke size is shown exactly as filed: Oklahoma records it in inches on some reports and in sixty-fourths of an inch on others, and names the unit on neither. A dash is a measurement Oklahoma did not file, or one it filed outside any physically possible range.

Casing

StringSize (in)Weight (lb/ft)GradeSet (ft)Cement (sacks)
PRODUCTION5 1/215.5 & 17J-55, LT & C5,668200
SURFACE8 5/824J-55301280

Drilling permits

Oklahoma files 3 applications to drill this well, naming 18 target formations. A permit records what an operator asked to do, not what it did. A target formation is where the operator aimed, and the hole may have missed it, stopped short of it or never been drilled.

Filed 2009-12-02

WRADRDirectional hole
Permit API
35049247690000
Operator
RANKEN ENERGY CORPORATION
Well type
OIL
Approved
2009-12-02
Expires
2010-06-02
Proposed depth
5,738 ft
Surface casing
300 ft
Ground elevation
919 ft

Target formations

FormationExpected top (ft)
LAYTON4,850
DEESE 14,900
DEESE 2 (PHAROAH)4,950
DEESE 3 (GIBSON)5,020
DEESE 4 (HART)5,050
VIOLA5,100
BROMIDE 15,400
BROMIDE 25,550

An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.

Filed 2009-12-02

DELAMDirectional hole
Permit API
35049247690000
Operator
RANKEN ENERGY CORPORATION
Well type
OIL
Approved
2009-12-02
Expires
2010-06-02
Proposed depth
5,738 ft
Surface casing
300 ft
Ground elevation
919 ft

Target formations

FormationExpected top (ft)
LAYTON4,850
DEESE 14,900
DEESE 2 (PHAROAH)4,950
DEESE 3 (GIBSON)5,020
DEESE 4 (HART)5,050
VIOLA5,100
BROMIDE 15,400
BROMIDE 25,550

An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.

Filed 2012-08-22

WRARCDirectional hole
Permit API
35049247690002
Operator
RANKEN ENERGY CORPORATION
Well type
OIL
Approved
2012-08-22
Expires
2013-02-22
Proposed depth
5,705 ft
Surface casing
301 ft
Ground elevation
919 ft

Target formations

FormationExpected top (ft)
BROMIDE 15,400
BROMIDE 25,550

An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.

Every well in Garvin County, Oklahoma

Oklahoma state record, from OK_wells_rbdms-wells.parquet. Corpus built 2026-09-11.