CHANDLER #2-8H
API 3506920136 · Johnston County, Oklahoma
Completion
Oklahoma files 1 completion report for this well. One carries a production test the operator filed.
Completion 2
HORIZONTAL HOLEACOILInterval
| Formation | Produced | Perforated (ft) | Treatment |
|---|---|---|---|
| WOODFORD | OIL | 11,027–15,939 | Acid, Frac |
Production test
| Tested | Oil (bbl/d) | Gas (MCF/d) | Water (bbl/d) | Gravity (°API) | Shut-in (psi) | Choke |
|---|---|---|---|---|---|---|
| 2013-09-13 | 897 | 3,196 | 884 | 46 | 2,100 | 38/64 |
A production test is one measurement the operator made on one day and filed with Oklahoma. It is not a monthly average and it does not describe how the well produced afterwards. The choke size is shown exactly as filed: Oklahoma records it in inches on some reports and in sixty-fourths of an inch on others, and names the unit on neither. A dash is a measurement Oklahoma did not file, or one it filed outside any physically possible range.
Casing
| String | Size (in) | Weight (lb/ft) | Grade | Set (ft) | Cement (sacks) |
|---|---|---|---|---|---|
| PRODUCTION | 5 1/2 | 20.23 | P-110 | 16,054 | 1,725 |
| CONDUCTOR | 16 | 97 | J-55 | 86 | 17 |
| SURFACE | 9 5/8 | 36 | J-55 | 1,212 | 490 |
Drilling permits
Oklahoma files 3 applications to drill this well, naming 12 target formations. A permit records what an operator asked to do, not what it did. A target formation is where the operator aimed, and the hole may have missed it, stopped short of it or never been drilled.
Filed 2012-05-08
WRADRHorizontal holeTarget formations
| Formation | Expected top (ft) |
|---|---|
| CANEY | 9,936 |
| SYCAMORE | 10,526 |
| WOODFORD | 10,846 |
| HUNTON | 11,251 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Filed 2012-05-08
WRAAMHorizontal holeTarget formations
| Formation | Expected top (ft) |
|---|---|
| CANEY | 9,936 |
| SYCAMORE | 10,526 |
| WOODFORD | 10,846 |
| HUNTON | 11,251 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Filed 2013-01-15
WRADRHorizontal holeTarget formations
| Formation | Expected top (ft) |
|---|---|
| CANEY | 9,936 |
| SYCAMORE | 10,526 |
| WOODFORD | 10,846 |
| HUNTON | 11,251 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Location
34.216865, -96.910333
Every well in Johnston County, Oklahoma