LAUBHAN 0409 #2H
API 3508722237 · McClain County, Oklahoma
Completion
Oklahoma files 1 completion report for this well.
Completion 2
STRAIGHT HOLEACDRYCasing
| String | Size (in) | Weight (lb/ft) | Grade | Set (ft) | Cement (sacks) |
|---|---|---|---|---|---|
| SURFACE | 9 5/8 | 36 | J-55 | 1,004 | 420 |
Drilling permits
Oklahoma files 4 applications to drill this well, naming 12 target formations. A permit records what an operator asked to do, not what it did. A target formation is where the operator aimed, and the hole may have missed it, stopped short of it or never been drilled.
Filed 2019-04-29
WRADRHHMUTarget formations
| Formation | Expected top (ft) |
|---|---|
| MISSISSIPPIAN | 9,000 |
| WOODFORD | 9,142 |
| HUNTON | 9,292 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Filed 2019-04-29
WRAAMHHMUTarget formations
| Formation | Expected top (ft) |
|---|---|
| MISSISSIPPIAN | 9,000 |
| WOODFORD | 9,142 |
| HUNTON | 9,292 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Filed 2019-04-29
WRAAMHHMUTarget formations
| Formation | Expected top (ft) |
|---|---|
| MISSISSIPPIAN | 9,000 |
| WOODFORD | 9,142 |
| HUNTON | 9,292 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Application
REJAMHHMUTarget formations
| Formation | Expected top (ft) |
|---|---|
| MISSISSIPPIAN | 9,150 |
| WOODFORD | 9,250 |
| HUNTON | 9,390 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Every well in McClain County, Oklahoma