Oklahoma files 1 completion report for this well. One carries a production test the operator filed.
Completion 2
STRAIGHT HOLEPAOILIntervals
| Formation | Produced | Perforated (ft) | Treatment |
|---|---|---|---|
| BIG LIME | OIL | 4,581–4,588 | Acid |
| WOODFORD | DRY | 5,074–5,136 | Acid |
Production tests
| Tested | Oil (bbl/d) | Gas (MCF/d) | Water (bbl/d) | Gravity (°API) | Shut-in (psi) | Choke |
|---|---|---|---|---|---|---|
| 2017-09-08 | 1 | 0 | 10 | 40 | 0 | — |
| 2018-01-09 | 3 | 0 | 6 | 40 | 0 | — |
A production test is one measurement the operator made on one day and filed with Oklahoma. It is not a monthly average and it does not describe how the well produced afterwards. The choke size is shown exactly as filed: Oklahoma records it in inches on some reports and in sixty-fourths of an inch on others, and names the unit on neither. A dash is a measurement Oklahoma did not file, or one it filed outside any physically possible range.
Casing
| String | Size (in) | Weight (lb/ft) | Grade | Set (ft) | Cement (sacks) |
|---|---|---|---|---|---|
| PRODUCTION | 4.5 | — | J-55 | 5,263 | 180 |
| SURFACE | 8.625 | — | LS | 235 | 165 |
Drilling permits
Oklahoma files 3 applications to drill this well, naming 25 target formations. A permit records what an operator asked to do, not what it did. A target formation is where the operator aimed, and the hole may have missed it, stopped short of it or never been drilled.
Filed 2017-03-31
WRADRStraight holeTarget formations
| Formation | Expected top (ft) |
|---|---|
| PERRY | 3,690 |
| CHECKERBOARD | 4,480 |
| CLEVELAND | 4,550 |
| BIG LIME | 4,580 |
| OSWEGO | 4,620 |
| SKINNER | 4,900 |
| WILCOX | 5,220 |
| VIOLA | 5,280 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Filed 2017-03-31
WRAAMStraight holeTarget formations
| Formation | Expected top (ft) |
|---|---|
| PERRY | 3,690 |
| CHECKERBOARD | 4,480 |
| CLEVELAND | 4,550 |
| BIG LIME | 4,580 |
| OSWEGO | 4,620 |
| SKINNER | 4,900 |
| WILCOX | 5,220 |
| VIOLA | 5,280 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Filed 2017-03-31
WRAAMStraight holeTarget formations
| Formation | Expected top (ft) |
|---|---|
| PERRY | 3,690 |
| CHECKERBOARD | 4,480 |
| CLEVELAND | 4,550 |
| BIG LIME | 4,580 |
| OSWEGO | 4,620 |
| SKINNER | 4,900 |
| WOODFORD | 5,090 |
| WILCOX | 5,220 |
| VIOLA | 5,280 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Location
36.193633, -97.379152
Every well in Noble County, Oklahoma
Oklahoma state record, from OK_wells_rbdms-wells.parquet. Corpus built 2026-09-11.