CULLERS #3
API 3511923852 · Payne County, Oklahoma
Completion
Oklahoma files 1 completion report for this well. One carries a production test the operator filed.
Completion 1
STRAIGHT HOLEACOILInterval
| Formation | Produced | Perforated (ft) | Treatment |
|---|---|---|---|
| MISSISSIPPI LIME | OIL | 3,838–3,906 | Frac |
Production test
| Tested | Oil (bbl/d) | Gas (MCF/d) | Water (bbl/d) | Gravity (°API) | Shut-in (psi) | Choke |
|---|---|---|---|---|---|---|
| 2012-01-16 | 1 | 0 | 10 | — | 100 | — |
A production test is one measurement the operator made on one day and filed with Oklahoma. It is not a monthly average and it does not describe how the well produced afterwards. The choke size is shown exactly as filed: Oklahoma records it in inches on some reports and in sixty-fourths of an inch on others, and names the unit on neither. A dash is a measurement Oklahoma did not file, or one it filed outside any physically possible range.
Casing
| String | Size (in) | Weight (lb/ft) | Grade | Set (ft) | Cement (sacks) |
|---|---|---|---|---|---|
| PRODUCTION | 5 1/2 | — | — | 4,170 | 225 |
| SURFACE | 8 5/8 | — | — | 315 | 200 |
Drilling permits
Oklahoma files 2 applications to drill this well, naming 20 target formations. A permit records what an operator asked to do, not what it did. A target formation is where the operator aimed, and the hole may have missed it, stopped short of it or never been drilled.
Filed 2011-01-04
WRADRStraight holeTarget formations
| Formation | Expected top (ft) |
|---|---|
| TONKAWA | 1,900 |
| OSAGE LAYTON /MISSOURIAN/ | 2,250 |
| LAYTON | 2,630 |
| CLEVELAND | 3,200 |
| OSWEGO | 3,230 |
| RED FORK | 3,570 |
| MISSISSIPPI LM | 3,800 |
| MISENER | 3,930 |
| VIOLA | 3,980 |
| WILCOX | 4,040 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Filed 2011-01-04
WRAAMStraight holeTarget formations
| Formation | Expected top (ft) |
|---|---|
| TONKAWA | 1,900 |
| OSAGE LAYTON /MISSOURIAN/ | 2,250 |
| LAYTON | 2,630 |
| CLEVELAND | 3,200 |
| BIG LIME-OSWEGO | 3,230 |
| RED FORK | 3,570 |
| MISSISSIPPI LM | 3,800 |
| MISENER | 3,930 |
| VIOLA | 3,980 |
| WILCOX | 4,040 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Every well in Payne County, Oklahoma
Oklahoma state record, from OK_wells_rbdms-wells.parquet. Corpus built 2026-09-11.