BB #1-15
API 3511924350 · Payne County, Oklahoma
Completion
Oklahoma files 1 completion report for this well. One carries a production test the operator filed.
Completion 1
STRAIGHT HOLEPADRYInterval
| Formation | Produced | Perforated (ft) | Treatment |
|---|---|---|---|
| MISSISSIPPIAN | DRY | 4,147–4,230 | Acid, Frac |
Production test
| Tested | Oil (bbl/d) | Gas (MCF/d) | Water (bbl/d) | Gravity (°API) | Shut-in (psi) | Choke |
|---|---|---|---|---|---|---|
| 2016-10-06 | 0 | 0 | 275 | — | 0 | — |
A production test is one measurement the operator made on one day and filed with Oklahoma. It is not a monthly average and it does not describe how the well produced afterwards. The choke size is shown exactly as filed: Oklahoma records it in inches on some reports and in sixty-fourths of an inch on others, and names the unit on neither. A dash is a measurement Oklahoma did not file, or one it filed outside any physically possible range.
Casing
| String | Size (in) | Weight (lb/ft) | Grade | Set (ft) | Cement (sacks) |
|---|---|---|---|---|---|
| PRODUCTION | 5 1/2 | 17 | J-55 | 4,440 | 185 |
| CONDUCTOR | 16 | — | — | 40 | 3 |
| SURFACE | 8 5/8 | 24 | J-55 | 634 | 320 |
Drilling permits
Oklahoma files 2 applications to drill this well, naming 16 target formations. A permit records what an operator asked to do, not what it did. A target formation is where the operator aimed, and the hole may have missed it, stopped short of it or never been drilled.
Filed 2015-07-20
WRADRStraight holeTarget formations
| Formation | Expected top (ft) |
|---|---|
| LAYTON | 2,650 |
| CLEVELAND | 3,300 |
| SKINNER | 3,750 |
| RED FORK | 3,930 |
| VIOLA | 4,320 |
| SIMPSON DOLO | 4,380 |
| WILCOX 1 | 4,390 |
| WILCOX 2 | 4,500 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Filed 2015-07-20
WRAAMStraight holeTarget formations
| Formation | Expected top (ft) |
|---|---|
| TRUE LAYTON | 2,650 |
| CLEVELAND | 3,300 |
| SKINNER | 3,750 |
| RED FORK | 3,930 |
| MISSISSIPPIAN | 4,138 |
| SIMPSON DOLO | 4,380 |
| WILCOX 1 | 4,390 |
| WILCOX 2 | 4,500 |
An expected top is the depth the operator predicted before drilling, on the application it filed with Oklahoma. It is not a measurement of where the formation was found.
Every well in Payne County, Oklahoma