Well 19, MCDONALD, IDA, Ector County, Texas
API 13502320 — recorded on 4 leases.
Total depth
8,959 ft
Last completion
Nov 17 1990
as filed
Leases
4
1 with no page
Records
4
wellbore filings
Leases
| Lease | Well no. | Operator | Field | Schedule |
|---|---|---|---|---|
| MCDONALD, IDA | 19 | CHEVRON U. S. A. INC. | JORDAN (ELLENBURGER) | On |
| MCDONALD, IDA | 19 | CTOC ENERGY, LLC | JORDAN (WICHITA ALBANY) | On |
| MCDONALD, IDA | 19 | CTOC ENERGY, LLC | PENWELL (CLEAR FORK) | Off |
| MCDONALD, IDAno production filed | 19 | CHEVRON U. S. A. INC. | JORDAN (CONNELL SAND) | On |
The hole
- Total depth
- 8,959 ft
- Casing strings
- 9
- Deepest casing
- 8,958 ft
- Survey
- PSL
- Abstract
- not filed
- Block / section
- B-16 / 27
- Plugging records
- not filed
- Bottom hole location
- 31.66443, -102.58380
31.66443, -102.58380 · NAD83, as filed⌘ or Ctrl + scroll to zoom
Drilling permits
From the Railroad Commission's drilling permit master — the application record, not a record of drilling. A permit is an application the Commission filed and numbered; the spud date is the only field here that says a hole was started. This file carries no approval status, so none is shown.
Permits
3
First issued
Nov 14 1986
to Nov 8 1990
With a spud date
1
last Oct 13 1990
Deepest permitted
8,958 ft
as applied for
| Permit | Issued | Type | Lease | Depth | Spud |
|---|---|---|---|---|---|
| 380607 | Nov 8 1990 | Recompletion | MCDONALD, IDAno. 19 | 8,958 ft | Oct 13 1990 |
| 344367 | Mar 26 1988 | Recompletion | MCDONALD, IDAno. 19 | 6,500 ft | not filed |
| 322888 | Nov 14 1986 | Recompletion | MCDONALD, IDAno. 19 | 8,605 ft | not filed |
What the lease produced
Texas reports oil and gas by lease, never by wellbore, so this is the whole lease. Values are volume multiplied by the published monthly price, the same arithmetic the lease page shows in full.