Well 1, CLEMONS GAS UNIT NO. 1, Hidalgo County, Texas

API 21531750 — recorded on 2 leases.

No plugging record filedSave
Total depth
9,140 ft
Last completion
Dec 30 1994
as filed
Leases
2
Records
2
wellbore filings

Leases

LeaseWell no.OperatorFieldSchedule
CLEMONS GAS UNIT NO. 11MERIT ENERGY COMPANYMONTE CHRISTO (58,59 CONS.)Off
CLEMONS GAS UNIT NO. 11MERIT ENERGY COMPANYMONTE CHRISTO (56-A, N)Off

The hole

Total depth
9,140 ft
Casing strings
4
Deepest casing
9,125 ft
Survey
S.A.M. GOMEZ VALLEY FARMS S/D, LOT 75
Abstract
63
Block / section
not filed
Plugging records
not filed
Bottom hole location
26.48767, -98.30231
26.48767, -98.30231 · NAD83, as filed

Drilling permits

From the Railroad Commission's drilling permit master — the application record, not a record of drilling. A permit is an application the Commission filed and numbered; the spud date is the only field here that says a hole was started. This file carries no approval status, so none is shown.

Permits
2
First issued
Apr 13 1987
to Dec 19 1994
With a spud date
1
last Dec 19 1994
Deepest permitted
9,400 ft
as applied for
PermitIssuedTypeLeaseDepthSpud
431091Dec 19 1994RecompletionCLEMONS GAS UNITno. 19,140 ftDec 19 1994
328771Apr 13 1987DrillCLEMONSno. 19,400 ftnot filed

What the lease produced

Texas reports oil and gas by lease, never by wellbore, so this is the whole lease. Values are volume multiplied by the published monthly price, the same arithmetic the lease page shows in full.