Well 3, SPARKS-HAISLEY-FERREE UNIT 1, San Patricio County, Texas
API 40903050 — recorded on 3 leases.
Total depth
3,925 ft
Last completion
Jul 12 1984
as filed
Leases
3
3 with no page
Records
4
wellbore filings
Leases
| Lease | Well no. | Operator | Field | Schedule |
|---|---|---|---|---|
| 04-G-015075no production filed | 1 | GRAHAM, BURDETTE | WHITE POINT, EAST (3800) | On |
| SPARKS-HAISLEY-FERREE UNIT 1no production filed | 3 | GOLDEN TREND OIL & GAS CORP. | WHITE POINT, EAST (2590) | On |
| SPARKS - HAISLEY - FERREE UNIT 1no production filed | 3 | GOLDEN TREND OIL & GAS CORP. | TAFT, SOUTH (2350) | On |
The hole
- Total depth
- 3,925 ft
- Casing strings
- 2
- Deepest casing
- 3,155 ft
- Survey
- GEORGE H. PAUL SUBD./CFPCL
- Abstract
- not filed
- Block / section
- 51
- Plugging records
- 4
- Bottom hole location
- 27.90767, -97.43676
27.90767, -97.43676 · NAD83, as filed⌘ or Ctrl + scroll to zoom
Drilling permits
From the Railroad Commission's drilling permit master — the application record, not a record of drilling. A permit is an application the Commission filed and numbered; the spud date is the only field here that says a hole was started. This file carries no approval status, so none is shown.
Permits
2
First issued
Sep 8 1977
to Jul 9 1984
With a spud date
—
none filed
Deepest permitted
3,925 ft
as applied for
| Permit | Issued | Type | Lease | Depth | Spud |
|---|---|---|---|---|---|
| 246414 | Jul 9 1984 | Recompletion | SPARKS-HAISLEY-FERREE UNIT 1no. 3 | 3,925 ft | not filed |
| 8477 | Sep 8 1977 | Other | SPARKS-HAISLEY-FERREE UNIT 1no. 3 | 3,925 ft | not filed |
What the lease produced
Texas reports oil and gas by lease, never by wellbore, so this is the whole lease. Values are volume multiplied by the published monthly price, the same arithmetic the lease page shows in full.