BRISCOE RANCH

Operated by ROSETTA RESOURCES OPERATING LP (P-5 728883) in the CATARINA, SW. (OLMOS) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 64991District 01Field 16340500CondensateGasSaveExport
Value, all time
$88 k
Jan 1993 – Apr 2016
Value, last 12 filed months
$397
at the published price for each month
Months reported
280
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 213 leases and 214 wells, and the rule below applies to all of them.

Discovered
1973-12-28
as the register files it
Field class
Oil and gas
the register's own label
Between wells
1,200 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 80 acres.

The Commission's schedule remark for this field reads: OPTIONAL 80 ACRE UNIT MAX DIAG 4000

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition28 bbl$1,004
GasProduction41,957 Mcf$87,229
Total$88,233

19,279 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 28.2636, -99.7855. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

28.26356, -99.78553 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
5,210 ft
1 wells filed one
Completion to plug
40.3 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 5,210 ft.

Completions filed
Nov 1975
1 of 1 wells
Plug dates filed
Feb 2016
1 of 1 wells

Last completion to plug: a median of 40.3 years across the 1 well that filed both dates, with the middle half between 40.3 years and 40.3 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-12730875115,210 ftNov 1975Feb 2016Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (280)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

280 months

Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 201615026.472.06$397
Jan 20160027.352.36$0
Dec 20150032.362.00$0
Nov 20150038.792.17$0
Oct 20150043.552.43$0
Sep 20150042.992.76$0
Aug 20150040.162.87$0
Jul 20150048.152.95$0
Jun 20150056.152.88$0
May 20150055.212.96$0
Apr 20150049.822.71$0
Mar 20150042.892.93$0
Feb 20150044.662.98$0
Jan 20150043.433.10$0
Dec 20140054.693.59$0
Nov 20140070.464.25$0
Oct 20140078.303.90$0
Sep 20140086.164.05$0
Aug 20140089.394.04$0
Jul 20140096.564.18$0
Jun 20140098.164.74$0
May 20140094.734.73$0
Apr 20140095.944.81$0
Mar 20140095.895.06$0
Feb 20140097.406.19$0
Jan 20140090.404.86$0
Dec 20130091.824.35$0
Nov 20130088.853.74$0
Oct 20130097.423.78$0
Sep 201300104.113.72$0
Aug 201300104.253.52$0
Jul 20130475102.523.72$1,766
Jun 2013039194.403.93$1,538
May 2013029994.834.15$1,241
Apr 2013016593.964.28$707
Mar 2013022693.623.91$884
Feb 2013019191.233.42$653
Jan 2013025791.603.42$879
Dec 2012018586.773.42$633
Nov 2012039886.953.62$1,443
Oct 2012027589.383.40$935
Sep 2012017894.672.92$519
Aug 2012029292.662.91$849
Jul 2012028985.133.02$873
Jun 2012428879.822.52$1,045
May 2012031191.612.49$774
Apr 20120302101.652.00$603
Mar 20120304105.052.22$676
Feb 20120104101.102.57$267
Jan 201207598.092.73$205
Dec 2011012896.873.24$415
Nov 201104895.723.31$159
Oct 2011012684.983.65$460
Sep 201129483.623.99$542
Aug 2011013883.404.15$573
Jul 201102794.144.52$122
Jun 201109192.904.64$422
May 2011011198.134.40$489
Apr 20110119105.964.33$516
Mar 2011010296.364.06$414
Feb 201105085.644.18$209
Jan 201102486.504.59$110
Dec 201001985.734.35$83
Nov 201002080.843.80$76
Oct 201004578.103.51$158
Sep 2010018072.633.98$716
Aug 201001073.684.42$44
Jul 201001172.554.74$52
Jun 201009970.364.91$486
May 201006671.124.24$280
Apr 201002881.694.12$115
Mar 201002478.394.39$105
Feb 201001773.585.44$93
Jan 201001374.365.96$78
Dec 200902171.445.48$115
Nov 20090074.593.75$0
Oct 20090072.544.11$0
Sep 200903965.543.06$120
Aug 200902367.423.22$74
Jul 2009013161.133.46$454
Jun 200904866.163.90$187
May 200905754.743.93$224
Apr 200909746.773.59$348
Mar 200908342.144.06$337
Feb 200906032.814.63$278
Jan 2009010235.865.37$548
Dec 200808837.105.98$526
Nov 200809355.496.86$638
Oct 2008012575.246.92$865
Sep 20080150101.767.88$1,182
Aug 20080140114.228.48$1,188
Jul 20080122131.0811.39$1,390
Jun 2008081131.3313.03$1,056
May 2008034123.1711.57$394
Apr 2008029110.3110.45$303
Mar 2008019101.909.66$184
Feb 200804192.538.77$360
Jan 200802890.388.21$230
Dec 200704288.337.30$307
Nov 200705691.677.29$408
Oct 2007010182.856.92$699
Sep 200708875.846.24$549
Aug 200706569.066.39$415
Jul 200706770.906.39$428
Jun 200705362.007.55$400
May 200703958.747.85$306
Apr 200705159.617.81$398
Mar 200705356.927.30$387
Feb 200707955.108.22$649
Jan 200707250.306.73$484
Dec 200608956.656.92$616
Nov 200605254.207.62$396
Oct 200607154.906.01$427
Sep 200604160.085.04$207
Aug 200605968.717.34$433
Jul 200606069.376.34$381
Jun 200606766.286.38$428
May 200606966.016.42$443
Apr 200607164.397.36$523
Mar 200606856.707.08$482
Feb 200606757.597.75$519
Jan 200604860.598.93$429
Dec 200505054.9413.42$671
Nov 200506954.6910.59$731
Oct 200507958.3413.80$1,090
Sep 200506961.4512.08$833
Aug 200505861.519.80$568
Jul 200508555.697.84$667
Jun 200504252.337.38$310
May 200507045.226.65$466
Apr 200506149.207.36$449
Mar 200505750.377.15$408
Feb 200506745.226.31$423
Jan 200509743.166.32$613
Dec 2004013039.866.75$878
Nov 200405945.286.33$373
Oct 200407549.706.52$489
Sep 200405843.245.28$306
Aug 200409942.375.55$550
Jul 200401838.286.08$110
Jun 200403436.106.43$219
May 20040637.486.49$39
Apr 200401534.475.86$88
Mar 20040234.365.53$11
Feb 20040132.455.51$6
Jan 200401032.036.30$63
Dec 200302130.266.30$132
Nov 20030028.804.60$0
Oct 200301528.174.76$71
Sep 200302026.314.75$95
Aug 200306329.765.13$323
Jul 200309029.415.17$465
Jun 2003010128.565.98$604
May 200309826.595.97$585
Apr 2003011026.675.41$595
Mar 200309831.146.10$597
Feb 200306733.487.93$531
Jan 200306730.315.58$374
Dec 200205426.914.85$262
Nov 200203524.664.14$145
Oct 200207226.464.23$305
Sep 200205627.443.64$204
Aug 200206225.963.16$196
Jul 200208324.583.06$254
Jun 2002011923.733.34$397
May 2002012124.663.58$434
Apr 200201423.653.51$49
Mar 20020022.003.10$0
Feb 20020018.222.38$0
Jan 20020017.172.38$0
Dec 2001011016.932.36$260
Nov 200101318.072.41$31
Oct 200103219.782.53$81
Sep 200108524.262.25$191
Aug 200109624.873.05$293
Jul 200108023.933.20$256
Jun 200107924.563.82$302
May 200108325.524.31$358
Apr 200107224.685.34$384
Mar 200107824.545.38$419
Feb 20010027.755.77$0
Jan 20010027.478.40$0
Dec 20000626.889.12$55
Nov 20000632.215.66$34
Oct 20000331.235.15$15
Sep 200005631.875.19$290
Aug 200001629.644.54$73
Jul 200006828.534.09$278
Jun 200007829.304.40$343
May 200006927.263.68$254
Apr 200006224.513.12$193
Mar 200006228.422.86$177
Feb 200006527.622.73$177
Jan 200005325.272.48$131
Dec 199905724.282.42$138
Nov 199906023.192.43$146
Oct 199907420.982.80$207
Sep 199907421.752.62$194
Aug 199906019.262.88$173
Jul 199907417.892.37$176
Jun 199905315.942.36$125
May 199908915.792.32$207
Apr 199906715.102.21$148
Mar 199906212.471.84$114
Feb 19990609.981.82$109
Jan 199907310.381.90$139
Dec 199801109.201.77$195
Nov 1998014510.892.19$317
Oct 1998020412.421.97$402
Sep 1998026312.592.08$548
Aug 1998027811.301.91$530
Jul 1998031811.742.24$711
Jun 1998030511.242.24$682
May 1998035912.622.21$792
Apr 1998032813.042.51$822
Mar 1998037212.802.31$859
Feb 1998026613.952.30$612
Jan 1998026114.702.15$562
Dec 1997022116.322.41$533
Nov 1997022018.193.09$679
Oct 1997026319.253.15$828
Sep 1997026017.742.95$768
Aug 1997034217.862.55$874
Jul 1997033217.582.25$746
Jun 1997048617.242.26$1,097
May 1997062218.972.31$1,436
Apr 1997060617.882.08$1,262
Mar 1997061918.951.94$1,200
Feb 1997051620.492.21$1,138
Jan 1997049623.483.54$1,756
Dec 1996059523.32$0
Nov 1996062021.97$0
Oct 1996058723.31$0
Sep 1996058122.22$0
Aug 1996077620.26$0
Jul 1996089519.55$0
Jun 1996073218.73$0
May 1996065119.43$0
Apr 1996026921.51$0
Mar 1996021019.38$0
Feb 1996018116.98$0
Jan 1996019317.07$0
Dec 1995020817.19$0
Nov 1995020416.00$0
Oct 1995019915.43$0
Sep 1995020116.18$0
Aug 1995021715.92$0
Jul 1995021515.24$0
Jun 1995021516.41$0
May 1995021217.56$0
Apr 1995018217.73$0
Mar 1995022116.44$0
Feb 1995021316.58$0
Jan 1995029615.92$0
Dec 1994035615.03$0
Nov 1994038015.90$0
Oct 1994034415.58$0
Sep 1994043015.29$0
Aug 1994037116.13$0
Jul 1994037517.56$0
Jun 1994036717.09$0
May 1994038815.88$0
Apr 1994032914.14$0
Mar 1994032012.46$0
Feb 1994031512.50$0
Jan 1994033512.66$0
Dec 1993036412.33$0
Nov 1993040014.49$0
Oct 1993045115.85$0
Sep 1993068615.03$0
Aug 1993050815.66$0
Jul 1993051915.46$0
Jun 1993056016.79$0
May 1993057717.68$0
Apr 1993058718.05$0
Mar 1993150818.14$18
Feb 1993143417.90$18
Jan 1993550216.93$85

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Feb 2016 — as filed, then multipliedworked
Condensate            15 bbl  × $ 26.47 =       $397
Gas                    0 Mcf  × $  2.06 =         $0

────────────────────────────────────────────────────
Month total                                     $397

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 01/G/64991 is the state's own key, not one this site invented.