LOCKWOOD & SHARP -B-

Operated by DENBURY ONSHORE, LLC (P-5 215343) in the THOMPSON field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 161556District 03Field 89525001CondensateGasSaveExport
Value, all time
$4.8 M
Oct 1996 – May 2016
Value, last 12 filed months
$0
at the published price for each month
Months reported
236
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 94 leases and 557 wells, and the rule below applies to all of them.

Discovered
1921-12-31
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
233 ft
minimum

A drilling unit in this field needs at least 10 acres. The field rule took effect on 2004-03-11.

The Commission's schedule remark for this field reads: BE DESIGNATED AS THE THOMPSON FIELD.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition3,614 bbl$106,377
GasProduction1,176,871 Mcf$4,691,404
Total$4,797,781

3,038 Mcf of this lease's gas, across 1 month, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 29.4544, -95.5892. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

29.45437, -95.58918 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
5,450 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 5,450 ft.

Completions filed
Apr 2023
1 of 1 wells

1 well

42-15730106485,450 ftApr 2023Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (236)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

236 months

May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 20160026.472.06$0
Jan 20160027.352.36$0
Dec 20150032.362.00$0
Nov 20150038.792.17$0
Oct 20150043.552.43$0
Sep 20150042.992.76$0
Aug 20150040.162.87$0
Jul 20150048.152.95$0
Jun 20150056.152.88$0
May 20150055.212.96$0
Apr 20150049.822.71$0
Mar 20150042.892.93$0
Feb 20150044.662.98$0
Jan 20150043.433.10$0
Dec 20140054.693.59$0
Nov 20140070.464.25$0
Oct 20140078.303.90$0
Sep 20140086.164.05$0
Aug 20140089.394.04$0
Jul 20140096.564.18$0
Jun 20140098.164.74$0
May 20140094.734.73$0
Apr 20140095.944.81$0
Mar 20140095.895.06$0
Feb 20140097.406.19$0
Jan 20140090.404.86$0
Dec 20130091.824.35$0
Nov 20130088.853.74$0
Oct 20130097.423.78$0
Sep 201300104.113.72$0
Aug 201300104.253.52$0
Jul 201300102.523.72$0
Jun 20130094.403.93$0
May 20130094.834.15$0
Apr 20130093.964.28$0
Mar 20130093.623.91$0
Feb 20130091.233.42$0
Jan 20130091.603.42$0
Dec 20120086.773.42$0
Nov 20120086.953.62$0
Oct 20120089.383.40$0
Sep 20120094.672.92$0
Aug 20120092.662.91$0
Jul 20120085.133.02$0
Jun 20120079.822.52$0
May 20120091.612.49$0
Apr 201200101.652.00$0
Mar 201200105.052.22$0
Feb 201200101.102.57$0
Jan 20120098.092.73$0
Dec 20110096.873.24$0
Nov 20110095.723.31$0
Oct 20110084.983.65$0
Sep 20110083.623.99$0
Aug 20110083.404.15$0
Jul 20110094.144.52$0
Jun 20110092.904.64$0
May 20110098.134.40$0
Apr 201100105.964.33$0
Mar 20110096.364.06$0
Feb 20110085.644.18$0
Jan 20110086.504.59$0
Dec 20100085.734.35$0
Nov 20100080.843.80$0
Oct 20100078.103.51$0
Sep 20100072.633.98$0
Aug 20100073.684.42$0
Jul 20100072.554.74$0
Jun 20100070.364.91$0
May 20100071.124.24$0
Apr 20100081.694.12$0
Mar 20100078.394.39$0
Feb 20100073.585.44$0
Jan 20100074.365.96$0
Dec 20090071.445.48$0
Nov 20090074.593.75$0
Oct 20090072.544.11$0
Sep 20090065.543.06$0
Aug 20090067.423.22$0
Jul 20090061.133.46$0
Jun 20090066.163.90$0
May 20090054.743.93$0
Apr 20090046.773.59$0
Mar 20090042.144.06$0
Feb 20090032.814.63$0
Jan 20090035.865.37$0
Dec 20080037.105.98$0
Nov 20080055.496.86$0
Oct 20080075.246.92$0
Sep 200800101.767.88$0
Aug 200800114.228.48$0
Jul 200800131.0811.39$0
Jun 200800131.3313.03$0
May 200800123.1711.57$0
Apr 200800110.3110.45$0
Mar 200800101.909.66$0
Feb 20080092.538.77$0
Jan 20080090.388.21$0
Dec 20070088.337.30$0
Nov 20070091.677.29$0
Oct 20070082.856.92$0
Sep 20070075.846.24$0
Aug 20070069.066.39$0
Jul 20070070.906.39$0
Jun 20070062.007.55$0
May 20070058.747.85$0
Apr 20070059.617.81$0
Mar 20070056.927.30$0
Feb 20070055.108.22$0
Jan 20070050.306.73$0
Dec 20060056.656.92$0
Nov 20060054.207.62$0
Oct 20060054.906.01$0
Sep 20060060.085.04$0
Aug 20060068.717.34$0
Jul 20060069.376.34$0
Jun 20060066.286.38$0
May 20060066.016.42$0
Apr 20060064.397.36$0
Mar 20060056.707.08$0
Feb 20060057.597.75$0
Jan 20060060.598.93$0
Dec 20050054.9413.42$0
Nov 20050054.6910.59$0
Oct 20050058.3413.80$0
Sep 20050061.4512.08$0
Aug 20050061.519.80$0
Jul 20050055.697.84$0
Jun 20050052.337.38$0
May 20050045.226.65$0
Apr 20050049.207.36$0
Mar 20050050.377.15$0
Feb 20050045.226.31$0
Jan 20050043.166.32$0
Dec 20040039.866.75$0
Nov 20040045.286.33$0
Oct 20041049.706.52$50
Sep 20042685743.245.28$5,653
Aug 20041856,73642.375.55$45,228
Jul 20042947,34138.286.08$55,918
Jun 20042806,89936.106.43$54,489
May 20042577,15537.486.49$56,101
Apr 20042557,34034.475.86$51,791
Mar 20042608,43634.365.53$55,586
Feb 20041254,91632.455.51$31,142
Jan 200407,05632.036.30$44,450
Dec 2003117,78730.266.30$49,404
Nov 2003548,54828.804.60$40,835
Oct 2003237,30728.174.76$35,427
Sep 20031216,31326.314.75$33,166
Aug 20031129,08129.765.13$49,916
Jul 2003727,42329.415.17$40,501
Jun 20031711,47428.565.98$69,134
May 20031312,51326.595.97$75,082
Apr 2003011,60526.675.41$62,751
Mar 200309,19231.146.10$56,035
Feb 200303,62033.487.93$28,692
Jan 200308,40130.315.58$46,895
Dec 200211,42226.914.85$6,929
Nov 200227,70424.664.14$31,920
Oct 20021121,61126.464.23$91,687
Sep 20023822,37527.443.64$82,380
Aug 200217028,35725.963.16$94,139
Jul 200226832,41424.583.06$105,831
Jun 2002931,93323.733.34$106,814
May 20021129,49324.663.58$105,974
Apr 20025626,05323.653.51$92,831
Mar 200231728,21422.003.10$94,514
Feb 200239926,31918.222.38$69,795
Jan 2002028,65717.172.38$68,080
Dec 2001028,30616.932.36$66,927
Nov 2001027,05318.072.41$65,077
Oct 2001025,51419.782.53$64,522
Sep 200102,21224.262.25$4,980
Aug 200102324.873.05$70
Jul 2001029923.933.20$956
Jun 2001029924.563.82$1,143
May 2001024,98825.524.31$107,631
Apr 2001027,84524.685.34$148,562
Mar 2001024,56124.545.38$132,051
Feb 2001025,72927.755.77$148,381
Jan 2001029,22127.478.40$245,420
Dec 2000025,43026.889.12$231,985
Nov 2000025,98832.215.66$147,040
Oct 2000021,53331.235.15$110,798
Sep 2000023,88031.875.19$123,854
Aug 2000026,72229.644.54$121,338
Jul 2000021,60928.534.09$88,375
Jun 2000026,24629.304.40$115,410
May 2000027,08827.263.68$99,677
Apr 2000026,78524.513.12$83,462
Mar 2000027,77228.422.86$79,421
Feb 2000027,09527.622.73$73,875
Jan 2000028,70825.272.48$71,210
Dec 1999028,99724.282.42$70,281
Nov 1999023,91323.192.43$58,204
Oct 1999127,75020.982.80$77,824
Sep 1999725,73221.752.62$67,541
Aug 19993821,71919.262.88$63,187
Jul 19991807,21617.892.37$20,339
Jun 19990015.942.36$0
May 19990015.792.32$0
Apr 19990015.102.21$0
Mar 19990012.471.84$0
Feb 1999009.981.82$0
Jan 19990010.381.90$0
Dec 1998009.201.77$0
Nov 19980010.892.19$0
Oct 19980012.421.97$0
Sep 19980012.592.08$0
Aug 19980011.301.91$0
Jul 19980011.742.24$0
Jun 19980011.242.24$0
May 19980012.622.21$0
Apr 19980013.042.51$0
Mar 19980012.802.31$0
Feb 19980013.952.30$0
Jan 19980014.702.15$0
Dec 19970016.322.41$0
Nov 19970018.193.09$0
Oct 19970019.253.15$0
Sep 1997010,12417.742.95$29,915
Aug 1997021,53417.862.55$55,014
Jul 1997021,82117.582.25$49,030
Jun 1997015,56917.242.26$35,142
May 19970018.972.31$0
Apr 19970017.882.08$0
Mar 19970018.951.94$0
Feb 19970020.492.21$0
Jan 19970023.483.54$0
Dec 199603,03823.32$0
Nov 19960021.97$0
Oct 19960023.31$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Oct 2004 — as filed, then multipliedworked
Condensate             1 bbl  × $ 49.70 =        $50
Gas                    0 Mcf  × $  6.52 =         $0

────────────────────────────────────────────────────
Month total                                      $50

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 03/G/161556 is the state's own key, not one this site invented.