HATLEY

Operated by BROOKSTON ENERGY, INC. (P-5 97353) in the WOODLAWN, SW. (COTTON VALLEY) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 221944District 06Field 985704002 tax incentive programmesCondensateGasSaveExport
Value, all time
$2.1 M
May 2006 – May 2026
Value, last 12 filed months
$31 k
at the published price for each month
Months reported
241
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 68 leases and 68 wells, and the rule below applies to all of them.

Discovered
1977-10-20
as the register files it
Field class
Gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2014-11-13.

The Commission's schedule remark for this field reads: ADOPTED, BUT REMAINS SUSPENDED.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112006-11-30169631
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition1,300 bbl$87,617
GasProduction339,980 Mcf$2,051,123
Total$2,138,739

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.5442, -94.5004. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.54415, -94.50042 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
10,600 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 10,600 ft.

Completions filed
Nov 2014
1 of 1 wells

1 well

42-20333424110,600 ftNov 2014

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (241)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

241 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 2026010163.503.75$379
Jan 202603,81059.138.00$30,472
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 2022900101.587.54$9,142
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 20170047.933.21$0
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170849.413.42$27
Dec 20160048.763.72$0
Nov 2016024642.492.64$651
Oct 2016060446.193.09$1,867
Sep 2016022341.553.10$691
Aug 2016038841.442.92$1,135
Jul 201601841.622.92$53
Jun 2016011445.352.69$306
May 2016033042.521.99$657
Apr 2016033536.561.99$667
Mar 2016049433.011.79$886
Feb 2016071826.472.06$1,482
Jan 2016041727.352.36$986
Dec 2015073832.362.00$1,477
Nov 201551,19138.792.17$2,775
Oct 201531,15543.552.43$2,933
Sep 2015057242.992.76$1,578
Aug 2015029740.162.87$853
Jul 2015046548.152.95$1,369
Jun 2015058056.152.88$1,672
May 20151151,06655.212.96$9,500
Apr 201551,92049.822.71$5,446
Mar 201501,99942.892.93$5,866
Feb 201501,93644.662.98$5,762
Jan 201501,81943.433.10$5,640
Dec 20141522,59454.693.59$17,629
Nov 201412,07770.464.25$8,902
Oct 2014092778.303.90$3,616
Sep 201401,16586.164.05$4,713
Aug 201401,08589.394.04$4,378
Jul 201401,16896.564.18$4,882
Jun 201401,10398.164.74$5,225
May 201401,18894.734.73$5,615
Apr 201401,12695.944.81$5,415
Mar 201401,22995.895.06$6,215
Feb 201411,01097.406.19$6,351
Jan 201401,21890.404.86$5,920
Dec 201311,07991.824.35$4,790
Nov 2013191988.853.74$3,524
Oct 2013065797.423.78$2,483
Sep 20130868104.113.72$3,227
Aug 20130992104.253.52$3,494
Jul 201301,166102.523.72$4,335
Jun 201301,15694.403.93$4,547
May 201311,18394.834.15$5,003
Apr 201301,11193.964.28$4,758
Mar 201301,16093.623.91$4,539
Feb 201311,08391.233.42$3,795
Jan 2013285991.603.42$3,121
Dec 20121161,11886.773.42$13,889
Nov 201211,03586.953.62$3,839
Oct 201211,24289.383.40$4,312
Sep 201211,15294.672.92$3,457
Aug 201211,24392.662.91$3,708
Jul 201211,24585.133.02$3,846
Jun 201201,24779.822.52$3,141
May 201211,28591.612.49$3,289
Apr 201211,252101.652.00$2,602
Mar 201211,369105.052.22$3,147
Feb 201211,308101.102.57$3,463
Jan 201201,08298.092.73$2,958
Dec 2011085196.873.24$2,757
Nov 2011051095.723.31$1,689
Oct 2011059984.983.65$2,185
Sep 201101,21083.623.99$4,823
Aug 201101,35183.404.15$5,606
Jul 201101,32094.144.52$5,963
Jun 2011084492.904.64$3,916
May 2011059498.134.40$2,616
Apr 20110652105.964.33$2,825
Mar 201101,06396.364.06$4,313
Feb 201101,11485.644.18$4,657
Jan 201101,26286.504.59$5,791
Dec 20101031,21085.734.35$14,091
Nov 201001,26080.843.80$4,782
Oct 201001,31678.103.51$4,618
Sep 201001,25472.633.98$4,990
Aug 201001,36873.684.42$6,046
Jul 201001,12672.554.74$5,333
Jun 201001,56470.364.91$7,680
May 2010111,16871.124.24$5,729
Apr 201001,63581.694.12$6,741
Mar 201001,71278.394.39$7,513
Feb 201001,57373.585.44$8,561
Jan 201002,05074.365.96$12,226
Dec 200901,31571.445.48$7,211
Nov 200901,78574.593.75$6,696
Oct 200901,95172.544.11$8,019
Sep 2009131,65165.543.06$5,912
Aug 200901,99767.423.22$6,427
Jul 200901,79061.133.46$6,201
Jun 200901,80466.163.90$7,027
May 200902,06654.743.93$8,111
Apr 200901,88346.773.59$6,755
Mar 200902,38642.144.06$9,685
Feb 200901,47132.814.63$6,815
Jan 20091652,25235.865.37$18,012
Dec 200862,34437.105.98$14,233
Nov 200802,51255.496.86$17,233
Oct 200802,25875.246.92$15,630
Sep 200802,079101.767.88$16,376
Aug 200822,374114.228.48$20,367
Jul 200801,471131.0811.39$16,754
Jun 200802,247131.3313.03$29,284
May 200801,961123.1711.57$22,697
Apr 200801,396110.3110.45$14,595
Mar 200813,311101.909.66$32,100
Feb 200813,31192.538.77$29,132
Jan 200813,45890.388.21$28,466
Dec 200703,96488.337.30$28,945
Nov 20071673,88291.677.29$43,615
Oct 200703,11882.856.92$21,583
Sep 200703,25575.846.24$20,325
Aug 200713,49869.066.39$22,414
Jul 200703,87270.906.39$24,734
Jun 200704,51062.007.55$34,044
May 200707,10358.747.85$55,732
Apr 200707,53859.617.81$58,836
Mar 20071509,97856.927.30$81,397
Feb 200708,94355.108.22$73,476
Jan 200708,49850.306.73$57,165
Dec 2006011,76656.656.92$81,402
Nov 2006013,44554.207.62$102,417
Oct 2006010,55554.906.01$63,476
Sep 20061768,86060.085.04$55,204
Aug 2006023,15968.717.34$169,985
Jul 2006032,77269.376.34$207,865
Jun 2006027,34066.286.38$174,535
May 20060066.016.42$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Feb 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $ 63.50 =         $0
Gas                  101 Mcf  × $  3.75 =       $379

────────────────────────────────────────────────────
Month total                                     $379

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/221944 is the state's own key, not one this site invented.