SWIFT

Operated by BROOKSTON ENERGY, INC. (P-5 97353) in the WASKOM (COTTON VALLEY) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 227330District 06Field 953691602 tax incentive programmesCondensateGasSaveExport
Value, all time
$2.7 M
Nov 2006 – May 2026
Value, last 12 filed months
$41
at the published price for each month
Months reported
235
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 473 leases and 477 wells, and the rule below applies to all of them.

Discovered
1955-09-19
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2012-11-06.

The Commission's schedule remark for this field reads: DESIGNATED AS UFT FIELD PER DOCKET 01-0299858

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112007-07-19175776
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition7,341 bbl$560,456
GasProduction336,423 Mcf$2,089,775
Total$2,650,232

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.4667, -94.1804. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.46673, -94.18044 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
9,840 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 9,840 ft.

Completions filed
May 2007
1 of 1 wells

1 well

42-2033365199,840 ftMay 2007

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (235)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

235 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250363.933.01$9
Jul 20250466.743.32$13
Jun 20250666.483.13$19
May 202501060.553.23$32
Apr 2025040062.363.54$1,417
Mar 202502867.704.27$120
Feb 202569170.884.34$820
Jan 202502374.324.28$98
Dec 202403868.993.12$119
Nov 202402669.052.20$57
Oct 202402671.372.28$59
Sep 20241045469.612.36$7,367
Aug 202407275.632.06$149
Jul 202403279.932.15$69
Jun 20240578.082.63$13
May 202407978.812.20$174
Apr 202403084.451.66$50
Mar 202453680.301.55$457
Feb 202406776.091.78$120
Jan 20240973.023.30$30
Dec 20230571.262.61$13
Nov 202301477.892.81$39
Oct 202301485.443.09$43
Sep 202301989.042.74$52
Aug 20230880.522.67$21
Jul 2023112474.852.64$887
Jun 202302768.962.26$61
May 202302270.622.23$49
Apr 202303078.122.24$67
Mar 202301372.852.39$31
Feb 202301775.112.47$42
Jan 2023701076.533.39$5,391
Dec 202201476.415.73$80
Nov 202204085.005.65$226
Oct 202202587.185.86$147
Sep 20228984.888.16$753
Aug 202206194.529.13$557
Jul 2022012101.587.54$91
Jun 2022035115.097.98$279
May 2022071109.378.43$599
Apr 20220103104.226.84$704
Mar 2022948108.885.08$1,224
Feb 202204091.054.86$194
Jan 202203381.844.54$150
Dec 202101171.323.90$43
Nov 202101977.435.24$100
Oct 20210779.795.71$40
Sep 202102869.865.35$150
Aug 202105366.024.22$224
Jul 20211110970.783.98$1,213
Jun 202102469.493.38$81
May 202102263.483.02$66
Apr 202102360.362.76$63
Mar 202101261.302.72$33
Feb 202102257.805.55$122
Jan 20211231050.412.81$6,229
Dec 202002644.642.68$70
Nov 202002238.772.71$60
Oct 202003436.972.48$84
Sep 20200037.091.99$0
Aug 202002339.982.39$55
Jul 202003938.371.83$71
Jun 202005434.901.69$91
May 202003716.921.81$67
Apr 202004214.751.80$76
Mar 202007330.341.86$136
Feb 202009449.881.98$186
Jan 20200257.252.09$4
Dec 201991459.012.30$563
Nov 201904355.302.75$118
Oct 2019014253.472.42$343
Sep 2019018255.052.66$484
Aug 2019010853.112.30$249
Jul 201909556.272.46$234
Jun 2019013052.782.49$324
May 2019764558.482.74$4,568
Apr 201905162.632.75$140
Mar 201908256.803.06$251
Feb 2019012450.852.79$346
Jan 2019018446.033.23$594
Dec 201807546.594.19$314
Nov 2018027852.934.24$1,178
Oct 2018025261.443.40$856
Sep 2018036559.543.11$1,134
Aug 201810935659.403.07$7,566
Jul 201805465.142.93$158
Jun 201802660.183.08$80
May 201804065.382.90$116
Apr 201808763.842.90$252
Mar 201805661.222.79$156
Feb 201807561.782.77$207
Jan 201807262.874.01$289
Dec 201708757.272.92$254
Nov 201706455.423.12$200
Oct 201706549.292.98$194
Sep 201709447.523.09$290
Aug 201709845.373.00$294
Jul 201707643.873.09$235
Jun 2017012042.493.09$370
May 201709645.373.26$313
Apr 2017012047.933.21$385
Mar 20179616146.772.98$4,970
Feb 2017017950.452.95$529
Jan 2017034049.413.42$1,162
Dec 2016022548.763.72$838
Nov 2016018942.492.64$500
Oct 2016029246.193.09$902
Sep 2016020041.553.10$620
Aug 2016037741.442.92$1,102
Jul 2016052941.622.92$1,547
Jun 201617662645.352.69$9,663
May 2016035742.521.99$711
Apr 2016074236.561.99$1,477
Mar 2016053233.011.79$954
Feb 2016032226.472.06$664
Jan 2016041027.352.36$969
Dec 2015032932.362.00$658
Nov 2015027438.792.17$594
Oct 2015039143.552.43$949
Sep 2015032642.992.76$899
Aug 2015038840.162.87$1,115
Jul 2015049848.152.95$1,467
Jun 2015041856.152.88$1,205
May 2015052355.212.96$1,546
Apr 201516543349.822.71$9,392
Mar 2015029942.892.93$877
Feb 2015019944.662.98$592
Jan 2015016543.433.10$512
Dec 2014025754.693.59$923
Nov 2014037670.464.25$1,599
Oct 2014043978.303.90$1,713
Sep 2014054786.164.05$2,213
Aug 2014068889.394.04$2,776
Jul 2014067296.564.18$2,809
Jun 201401,15098.164.74$5,447
May 2014061494.734.73$2,902
Apr 2014043895.944.81$2,106
Mar 201417344095.895.06$18,814
Feb 2014090197.406.19$5,579
Jan 201401,19390.404.86$5,799
Dec 2013093791.824.35$4,080
Nov 201301,04688.853.74$3,910
Oct 201301,39097.423.78$5,253
Sep 2013154755104.113.72$18,840
Aug 20130688104.253.52$2,424
Jul 20130748102.523.72$2,781
Jun 2013096294.403.93$3,784
May 201301,25794.834.15$5,215
Apr 201301,68993.964.28$7,233
Mar 20131471,58993.623.91$19,980
Feb 201301,18391.233.42$4,046
Jan 201301,18591.603.42$4,053
Dec 201201,06686.773.42$3,646
Nov 2012098286.953.62$3,560
Oct 201201,05089.383.40$3,570
Sep 20121561,14594.672.92$18,110
Aug 201201,10992.662.91$3,225
Jul 201201,53785.133.02$4,643
Jun 201201,48279.822.52$3,733
May 201201,22791.612.49$3,053
Apr 201201,340101.652.00$2,676
Mar 20121581,090105.052.22$19,020
Feb 201201,109101.102.57$2,850
Jan 201201,27598.092.73$3,486
Dec 201101,23996.873.24$4,014
Nov 201101,28695.723.31$4,258
Oct 201101,49784.983.65$5,462
Sep 20111621,35483.623.99$18,943
Aug 201101,25883.404.15$5,220
Jul 201101,61594.144.52$7,295
Jun 201101,59192.904.64$7,382
May 20111672,03698.134.40$25,356
Apr 201101,572105.964.33$6,812
Mar 201101,41896.364.06$5,753
Feb 201101,59085.644.18$6,646
Jan 201102,09586.504.59$9,613
Dec 201002,18185.734.35$9,482
Nov 20101562,22080.843.80$21,037
Oct 201002,29778.103.51$8,060
Sep 201002,23772.633.98$8,902
Aug 201002,52273.684.42$11,146
Jul 20101782,53272.554.74$24,907
Jun 201002,50770.364.91$12,310
May 201002,73571.124.24$11,583
Apr 201003,22881.694.12$13,308
Mar 20101763,06278.394.39$27,235
Feb 201002,39573.585.44$13,034
Jan 201002,79074.365.96$16,640
Dec 200902,82271.445.48$15,475
Nov 200903,07074.593.75$11,517
Oct 20091633,65172.544.11$26,831
Sep 200903,48765.543.06$10,687
Aug 200903,70167.423.22$11,912
Jul 20091643,21261.133.46$21,153
Jun 200903,30866.163.90$12,885
May 200903,63254.743.93$14,258
Apr 20091523,51846.773.59$19,730
Mar 200903,81942.144.06$15,501
Feb 20091802,21932.814.63$16,186
Jan 200903,73335.865.37$20,050
Dec 20081583,80137.105.98$28,581
Nov 200804,13955.496.86$28,395
Oct 20081594,66075.246.92$44,220
Sep 200804,795101.767.88$37,771
Aug 20081555,507114.228.48$64,420
Jul 20081545,951131.0811.39$87,965
Jun 200806,526131.3313.03$85,051
May 20081857,355123.1711.57$107,915
Apr 20081737,086110.3110.45$93,167
Mar 20081553,592101.909.66$50,508
Feb 20081834,01092.538.77$52,103
Jan 200805,95890.388.21$48,890
Dec 20071796,37088.337.30$62,325
Nov 20073606,98591.677.29$83,934
Oct 200707,43282.856.92$51,444
Sep 20073528,02775.846.24$76,818
Aug 20073598,35669.066.39$78,170
Jul 20071799,65870.906.39$74,386
Jun 200773411,44362.007.55$131,885
May 20073688,96358.747.85$91,943
Apr 20071684,96159.617.81$48,736
Mar 2007210,69856.927.30$78,230
Feb 2007011,59055.108.22$95,223
Jan 2007915,01850.306.73$101,477
Dec 20064522,55856.656.92$158,615
Nov 20060054.207.62$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Aug 2025 — as filed, then multipliedworked
Condensate             0 bbl  × $ 63.93 =         $0
Gas                    3 Mcf  × $  3.01 =         $9

────────────────────────────────────────────────────
Month total                                       $9

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/227330 is the state's own key, not one this site invented.