HELTON

Operated by PRESIDIO PETROLEUM LLC (P-5 676084) in the BUFFALO WALLOW (GRANITE WASH) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 216909District 10Field 131472852 tax incentive programmesCondensateGasSaveExport
Value, all time
$2.0 M
Mar 2006 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
243
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 1,387 leases and 1,388 wells, and the rule below applies to all of them.

Discovered
1974-09-09
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2016-03-29.

The Commission's schedule remark for this field reads: 01-30-2024

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112006-09-15169701
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition6,393 bbl$451,380
GasProduction265,802 Mcf$1,547,190
Total$1,998,570

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 35.6149, -100.3383. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

35.61489, -100.33825 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
13,770 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 13,770 ft.

Completions filed
Mar 2006
1 of 1 wells

1 well

42-48331996906013,770 ftMar 2006

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (243)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

243 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20184065.142.93$261
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 20170047.933.21$0
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170049.413.42$0
Dec 20160048.763.72$0
Nov 20160042.492.64$0
Oct 20160046.193.09$0
Sep 20160041.553.10$0
Aug 20160041.442.92$0
Jul 20160041.622.92$0
Jun 20160045.352.69$0
May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 20160026.472.06$0
Jan 20160027.352.36$0
Dec 20150032.362.00$0
Nov 20150038.792.17$0
Oct 20150043.552.43$0
Sep 20150042.992.76$0
Aug 20150040.162.87$0
Jul 20150048.152.95$0
Jun 20150056.152.88$0
May 20150055.212.96$0
Apr 20150049.822.71$0
Mar 20150042.892.93$0
Feb 20150044.662.98$0
Jan 20158143.433.10$351
Dec 20140054.693.59$0
Nov 201412070.464.25$846
Oct 20140078.303.90$0
Sep 2014017386.164.05$700
Aug 20140989.394.04$36
Jul 2014203296.564.18$2,065
Jun 2014014598.164.74$687
May 20143217294.734.73$3,844
Apr 20146497895.944.81$10,843
Mar 2014311,31495.895.06$9,617
Feb 2014072397.406.19$4,477
Jan 2014044690.404.86$2,168
Dec 2013048091.824.35$2,090
Nov 20132953488.853.74$4,573
Oct 20133464197.423.78$5,735
Sep 201335831104.113.72$6,733
Aug 20130875104.253.52$3,082
Jul 2013371,427102.523.72$9,098
Jun 2013201,52694.403.93$7,890
May 2013241,14494.834.15$7,022
Apr 2013731,32893.964.28$12,546
Mar 2013651,67093.623.91$12,620
Feb 2013391,54391.233.42$8,835
Jan 2013661,91691.603.42$12,598
Dec 2012581,93686.773.42$11,654
Nov 2012232,06186.953.62$9,471
Oct 2012592,04089.383.40$12,209
Sep 201202394.672.92$67
Aug 2012351,89292.662.91$8,745
Jul 2012152,30585.133.02$8,240
Jun 2012482,14279.822.52$9,227
May 2012442,28491.612.49$9,714
Apr 2012182,349101.652.00$6,520
Mar 2012872,658105.052.22$15,046
Feb 2012332,752101.102.57$10,410
Jan 2012352,17698.092.73$9,383
Dec 2011322,31396.873.24$10,593
Nov 2011512,13795.723.31$11,958
Oct 2011532,18884.983.65$12,487
Sep 2011292,16983.623.99$11,070
Aug 2011141,81183.404.15$8,682
Jul 2011181,84394.144.52$10,020
Jun 2011272,04392.904.64$11,988
May 2011362,46598.134.40$14,391
Apr 201101,557105.964.33$6,747
Mar 2011441,89196.364.06$11,912
Feb 2011451,67985.644.18$10,872
Jan 2011272,42086.504.59$13,440
Dec 2010452,30185.734.35$13,862
Nov 2010462,10780.843.80$11,715
Oct 2010251,35478.103.51$6,704
Sep 2010136972.633.98$1,541
Aug 2010762773.684.42$3,287
Jul 20101052872.554.74$3,226
Jun 20101174970.364.91$4,452
May 20101183971.124.24$4,336
Apr 2010196281.694.12$4,048
Mar 20101897378.394.39$5,681
Feb 2010974773.585.44$4,728
Jan 20101189774.365.96$6,168
Dec 200981,07671.445.48$6,472
Nov 2009769674.593.75$3,133
Oct 2009874072.544.11$3,622
Sep 2009893165.543.06$3,378
Aug 2009695667.423.22$3,481
Jul 2009656761.133.46$2,331
Jun 2009654366.163.90$2,512
May 2009972054.743.93$3,319
Apr 2009858946.773.59$2,487
Mar 2009563042.144.06$2,768
Feb 2009636432.814.63$1,883
Jan 2009324835.865.37$1,440
Dec 200844737.105.98$429
Nov 2008238355.496.86$2,739
Oct 2008436775.246.92$2,841
Sep 20083255101.767.88$2,314
Aug 20083382114.228.48$3,583
Jul 20085376131.0811.39$4,938
Jun 20080411131.3313.03$5,356
May 20081301123.1711.57$3,607
Apr 20082329110.3110.45$3,660
Mar 20087381101.909.66$4,395
Feb 2008590492.538.77$8,391
Jan 20081181290.388.21$7,657
Dec 200791,86888.337.30$14,435
Nov 2007141,33291.677.29$10,996
Oct 200781,61382.856.92$11,828
Sep 200782,07675.846.24$13,570
Aug 200792,06569.066.39$13,813
Jul 2007452,78770.906.39$20,994
Jun 2007762,85962.007.55$26,293
May 20071332,61058.747.85$28,291
Apr 200712,57859.617.81$20,181
Mar 20071384,17356.927.30$38,326
Feb 20071153,72155.108.22$36,908
Jan 2007724,58150.306.73$34,437
Dec 2006846,08956.656.92$46,885
Nov 20062366,72454.207.62$64,011
Oct 20063249,22954.906.01$73,289
Sep 20063139,30660.085.04$65,681
Aug 200642511,11068.717.34$110,748
Jul 200652413,46569.376.34$121,755
Jun 200639117,26466.286.38$136,127
May 200678333,03266.016.42$263,916
Apr 200685234,72164.397.36$310,424
Mar 2006879656.707.08$5,613

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Jul 2018 — as filed, then multipliedworked
Condensate             4 bbl  × $ 65.14 =       $261
Gas                    0 Mcf  × $  2.93 =         $0

────────────────────────────────────────────────────
Month total                                     $261

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 10/G/216909 is the state's own key, not one this site invented.