BYRUM 6

Operated by BCE-MACH III LLC (P-5 40209) in the RED DEER CREEK (GRANITE WASH) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 235905District 10Field 752003002 tax incentive programmesCondensateGasSaveExport
Value, all time
$2.3 M
Mar 2008 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
219
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 157 leases and 157 wells, and the rule below applies to all of them.

Discovered
1978-03-16
as the register files it
Field class
Oil and gas
the register's own label
Between wells
467 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2008-09-09.

The Commission's schedule remark for this field reads: AND PLAT AS LONG AS THE ALLOCATION IS SUSPENDED.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112008-06-30184002
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition3,366 bbl$278,320
GasProduction345,464 Mcf$1,976,143
Total$2,254,463

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 35.7581, -100.6249. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

35.75806, -100.62495 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
10,600 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 10,600 ft.

Completions filed
Mar 2008
1 of 1 wells

1 well

42-393320592010,600 ftMar 2008

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (219)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

219 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 201863759.543.11$3,773
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 201707545.373.00$225
Jul 20170143.873.09$3
Jun 2017018642.493.09$574
May 2017024145.373.26$786
Apr 2017023847.933.21$764
Mar 2017030646.772.98$913
Feb 2017027150.452.95$800
Jan 2017259049.413.42$2,116
Dec 2016055848.763.72$2,077
Nov 201619261342.492.64$9,779
Oct 2016166446.193.09$2,098
Sep 2016261441.553.10$1,987
Aug 2016065241.442.92$1,907
Jul 2016165541.622.92$1,957
Jun 2016061445.352.69$1,649
May 2016378342.521.99$1,687
Apr 2016176236.561.99$1,554
Mar 2016181333.011.79$1,492
Feb 2016173626.472.06$1,545
Jan 2016264827.352.36$1,587
Dec 2015289932.362.00$1,864
Nov 2015194838.792.17$2,093
Oct 2015290643.552.43$2,286
Sep 2015191742.992.76$2,572
Aug 2015193640.162.87$2,729
Jul 20151991,01948.152.95$12,583
Jun 201531,07556.152.88$3,268
May 201561,10955.212.96$3,609
Apr 201511,28549.822.71$3,528
Mar 201501,71042.892.93$5,018
Feb 201511,66944.662.98$5,012
Jan 201521,89843.433.10$5,972
Dec 201431,47654.693.59$5,465
Nov 2014059470.464.25$2,526
Oct 20140178.303.90$4
Sep 201401,36186.164.05$5,506
Aug 201401,53689.394.04$6,198
Jul 201401,45596.564.18$6,081
Jun 201401,34698.164.74$6,376
May 201411,41594.734.73$6,783
Apr 201411,56995.944.81$7,641
Mar 201421,52895.895.06$7,919
Feb 201401,42297.406.19$8,805
Jan 201401,80590.404.86$8,774
Dec 201301,75191.824.35$7,625
Nov 201301,36788.853.74$5,110
Oct 20131891,97897.423.78$25,888
Sep 201301,956104.113.72$7,272
Aug 201302,176104.253.52$7,665
Jul 201302,030102.523.72$7,547
Jun 201301,94094.403.93$7,631
May 201302,00694.834.15$8,323
Apr 20131452,02493.964.28$22,292
Mar 201302,16393.623.91$8,464
Feb 201301,87191.233.42$6,399
Jan 201302,04691.603.42$6,997
Dec 201201,96386.773.42$6,714
Nov 201201,81586.953.62$6,579
Oct 201201,79489.383.40$6,099
Sep 201201,82994.672.92$5,338
Aug 201202,06492.662.91$6,002
Jul 201202,04885.133.02$6,187
Jun 201201,98779.822.52$5,005
May 20121772,10691.612.49$21,455
Apr 201202,047101.652.00$4,087
Mar 201201,968105.052.22$4,373
Feb 201201,911101.102.57$4,912
Jan 201202,13798.092.73$5,843
Dec 201102,23796.873.24$7,247
Nov 201102,19395.723.31$7,262
Oct 201102,32684.983.65$8,487
Sep 201102,32883.623.99$9,279
Aug 201102,51583.404.15$10,436
Jul 201102,60294.144.52$11,754
Jun 201102,73492.904.64$12,685
May 20111702,69898.134.40$28,566
Apr 201102,820105.964.33$12,220
Mar 20111712,90696.364.06$28,268
Feb 201102,83185.644.18$11,834
Jan 201103,16286.504.59$14,510
Dec 201003,32385.734.35$14,448
Nov 201003,31380.843.80$12,574
Oct 201003,46478.103.51$12,155
Sep 201003,55372.633.98$14,139
Aug 201003,59773.684.42$15,896
Jul 20101743,76572.554.74$30,457
Jun 201004,15670.364.91$20,408
May 201003,73771.124.24$15,827
Apr 201004,26581.694.12$17,583
Mar 201004,82878.394.39$21,189
Feb 20101524,41973.585.44$35,234
Jan 201005,26574.365.96$31,401
Dec 200905,31871.445.48$29,163
Nov 200905,48574.593.75$20,577
Oct 200905,93072.544.11$24,374
Sep 200905,96665.543.06$18,284
Aug 200906,02967.423.22$19,404
Jul 200906,19761.133.46$21,470
Jun 20091956,14066.163.90$36,817
May 200906,66754.743.93$26,173
Apr 200907,11646.773.59$25,529
Mar 200907,72142.144.06$31,340
Feb 20091945,57532.814.63$32,194
Jan 200905,83535.865.37$31,340
Dec 20081996,61737.105.98$46,934
Nov 20081786,75255.496.86$56,198
Oct 200807,79975.246.92$53,985
Sep 200808,359101.767.88$65,845
Aug 20081858,533114.228.48$93,516
Jul 200818010,688131.0811.39$145,325
Jun 200818612,065131.3313.03$181,666
May 200818715,618123.1711.57$203,800
Apr 200818923,499110.3110.45$266,527
Mar 200805,635101.909.66$54,457

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Sep 2018 — as filed, then multipliedworked
Condensate            63 bbl  × $ 59.54 =     $3,751
Gas                    7 Mcf  × $  3.11 =        $22

────────────────────────────────────────────────────
Month total                                   $3,773

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 10/G/235905 is the state's own key, not one this site invented.