KEETON

Operated by PRESIDIO PETROLEUM LLC (P-5 676084) in the BUFFALO WALLOW (GRANITE WASH) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 237454District 10Field 131472852 tax incentive programmesCondensateGasSaveExport
Value, all time
$3.0 M
Jun 2007 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
228
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 1,387 leases and 1,388 wells, and the rule below applies to all of them.

Discovered
1974-09-09
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2016-03-29.

The Commission's schedule remark for this field reads: 01-30-2024

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112008-08-18176248
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition1,922 bbl$142,439
GasProduction600,006 Mcf$2,884,464
Total$3,026,903

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 35.6843, -100.3160. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

35.68430, -100.31595 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
11,750 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 11,750 ft.

Completions filed
Jun 2007
1 of 1 wells

1 well

42-211338365626P11,750 ftJun 2007

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (228)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

228 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 2023101085.443.09$8,629
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 2021048370.783.98$1,923
Jun 2021046769.493.38$1,579
May 2021048363.483.02$1,458
Apr 2021046760.362.76$1,288
Mar 2021048361.302.72$1,312
Feb 2021043557.805.55$2,413
Jan 2021073450.412.81$2,063
Dec 202001,03144.642.68$2,758
Nov 202001,00438.772.71$2,717
Oct 202001,05136.972.48$2,605
Sep 2020296437.091.99$1,994
Aug 202001,08939.982.39$2,597
Jul 202001,04838.371.83$1,913
Jun 202001,04134.901.69$1,760
May 202001,09816.921.81$1,993
Apr 202001,06914.751.80$1,929
Mar 202021,11430.341.86$2,129
Feb 202001,17849.881.98$2,333
Jan 202001,06557.252.09$2,231
Dec 201901,17859.012.30$2,715
Nov 201901,14255.302.75$3,141
Oct 201901,19053.472.42$2,878
Sep 201901,17955.052.66$3,133
Aug 201921,21753.112.30$2,911
Jul 201921,20756.272.46$3,082
Jun 201901,23252.782.49$3,069
May 201911,30758.482.74$3,640
Apr 201921,38062.632.75$3,921
Mar 201901,41156.803.06$4,321
Feb 201901,32150.852.79$3,689
Jan 201901,46146.033.23$4,716
Dec 201801,56146.594.19$6,533
Nov 201801,40852.934.24$5,966
Oct 201801,49361.443.40$5,073
Sep 201801,42559.543.11$4,429
Aug 201801,49859.403.07$4,594
Jul 201801,47165.142.93$4,313
Jun 201801,25560.183.08$3,862
May 201811,37565.382.90$4,054
Apr 201801,40263.842.90$4,067
Mar 201801,29361.222.79$3,603
Feb 201821,16161.782.77$3,335
Jan 201831,13762.874.01$4,747
Dec 20171271,77457.272.92$12,456
Nov 201731,82955.423.12$5,870
Oct 201702,52749.292.98$7,540
Sep 201722,11747.523.09$6,631
Aug 201742,07845.373.00$6,425
Jul 201712,33943.873.09$7,265
Jun 201702,46642.493.09$7,613
May 201742,36445.373.26$7,896
Apr 201702,16447.933.21$6,950
Mar 201742,38246.772.98$7,294
Feb 201702,16850.452.95$6,401
Jan 201712,28649.413.42$7,865
Dec 201602,35548.763.72$8,767
Nov 201601,88742.492.64$4,990
Oct 20161841,97346.193.09$14,596
Sep 201601,98841.553.10$6,164
Aug 201602,06141.442.92$6,027
Jul 201602,02241.622.92$5,913
Jun 201602,10745.352.69$5,659
May 201602,11142.521.99$4,203
Apr 201602,15836.561.99$4,297
Mar 201602,32433.011.79$4,169
Feb 201602,30126.472.06$4,748
Jan 201602,30927.352.36$5,459
Dec 201502,51432.362.00$5,032
Nov 201502,47638.792.17$5,366
Oct 201542,71143.552.43$6,753
Sep 201532,64242.992.76$7,417
Aug 201522,82740.162.87$8,201
Jul 201572,90748.152.95$8,898
Jun 201522,84756.152.88$8,320
May 201533,37655.212.96$10,143
Apr 201502,84249.822.71$7,692
Mar 201503,22442.892.93$9,462
Feb 201532,84944.662.98$8,613
Jan 201502,91143.433.10$9,026
Dec 201402,97254.693.59$10,674
Nov 201402,82170.464.25$11,994
Oct 20141963,03078.303.90$27,167
Sep 201402,96386.164.05$11,987
Aug 201402,96489.394.04$11,960
Jul 201443,09696.564.18$13,326
Jun 201402,97298.164.74$14,078
May 201403,25594.734.73$15,385
Apr 201453,32595.944.81$16,470
Mar 201413,21195.895.06$16,333
Feb 201422,81197.406.19$17,601
Jan 201433,23190.404.86$15,976
Dec 201343,27991.824.35$14,646
Nov 201303,44988.853.74$12,893
Oct 201303,73897.423.78$14,127
Sep 201303,735104.113.72$13,886
Aug 201303,871104.253.52$13,636
Jul 201313,845102.523.72$14,397
Jun 201313,71094.403.93$14,687
May 201324,15094.834.15$17,408
Apr 201344,19093.964.28$18,320
Mar 201324,67593.623.91$18,480
Feb 201313,58791.233.42$12,358
Jan 201303,75391.603.42$12,835
Dec 201204,26786.773.42$14,594
Nov 20121904,35486.953.62$32,304
Oct 201214,35789.383.40$14,902
Sep 201224,44094.672.92$13,147
Aug 201215,02392.662.91$14,700
Jul 201254,71385.133.02$14,663
Jun 201234,79779.822.52$12,323
May 201234,94891.612.49$12,587
Apr 201205,417101.652.00$10,817
Mar 201234,030105.052.22$9,270
Feb 201201,854101.102.57$4,765
Jan 201202,17098.092.73$5,933
Dec 201103,32796.873.24$10,779
Nov 201101,77895.723.31$5,887
Oct 201102,69184.983.65$9,818
Sep 201101,36783.623.99$5,449
Aug 201101,96283.404.15$8,141
Jul 201105,17594.144.52$23,377
Jun 201104,77892.904.64$22,169
May 20111555,99198.134.40$41,599
Apr 201104,739105.964.33$20,535
Mar 201102,52596.364.06$10,245
Feb 201103,04385.644.18$12,720
Jan 201104,21586.504.59$19,342
Dec 201005,22385.734.35$22,708
Nov 201005,13480.843.80$19,485
Oct 201005,23178.103.51$18,355
Sep 201005,09272.633.98$20,263
Aug 201005,09373.684.42$22,508
Jul 201005,05372.554.74$23,933
Jun 20101575,12070.364.91$36,188
May 201005,41471.124.24$22,929
Apr 201004,92281.694.12$20,292
Mar 201005,89578.394.39$25,871
Feb 201006,16573.585.44$33,552
Jan 201005,91174.365.96$35,254
Dec 200904,71171.445.48$25,834
Nov 20091825,52274.593.75$34,291
Oct 200905,90872.544.11$24,283
Sep 200903,60365.543.06$11,042
Aug 200905,91467.423.22$19,034
Jul 200905,84061.133.46$20,233
Jun 200904,02566.163.90$15,677
May 200905,32854.743.93$20,916
Apr 200905,81946.773.59$20,876
Mar 200906,23442.144.06$25,304
Feb 200905,66332.814.63$26,237
Jan 20091656,02435.865.37$38,272
Dec 200806,34937.105.98$37,949
Nov 200806,39755.496.86$43,886
Oct 200806,37875.246.92$44,148
Sep 200806,444101.767.88$50,760
Aug 200806,754114.228.48$57,294
Jul 200807,316131.0811.39$83,325
Jun 200807,081131.3313.03$92,284
May 200807,538123.1711.57$87,247
Apr 200807,337110.3110.45$76,707
Mar 20081807,948101.909.66$95,152
Feb 200807,48792.538.77$65,665
Jan 200808,88390.388.21$72,892
Dec 200709,26188.337.30$67,624
Nov 200703,58691.677.29$26,148
Oct 200717710,14682.856.92$84,895
Sep 2007011,55175.846.24$72,126
Aug 2007015,24669.066.39$97,391
Jul 2007023,49070.906.39$150,053
Jun 200703,15262.007.55$23,793

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Oct 2023 — as filed, then multipliedworked
Condensate           101 bbl  × $ 85.44 =     $8,629
Gas                    0 Mcf  × $  3.09 =         $0

────────────────────────────────────────────────────
Month total                                   $8,629

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 10/G/237454 is the state's own key, not one this site invented.