Operated by PRESIDIO PETROLEUM LLC (P-5 676084) in the BUFFALO WALLOW (GRANITE WASH) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 251223District 10Field 131472852 tax incentive programmesCondensateGasSaveExport
Value, all time
$2.6 M
Feb 2007 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
232
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 1,387 leases and 1,388 wells, and the rule below applies to all of them.

Discovered
1974-09-09
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2016-03-29.

The Commission's schedule remark for this field reads: 01-30-2024

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112009-10-15174323
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition2,029 bbl$136,337
GasProduction444,241 Mcf$2,485,433
Total$2,621,769

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 35.6863, -100.3102. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

35.68634, -100.31024 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
11,825 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 11,825 ft.

Completions filed
Feb 2007
1 of 1 wells

1 well

42-211337705608P11,825 ftFeb 2007

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (232)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

232 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 2020046734.901.69$789
May 2020048316.921.81$877
Apr 2020046714.751.80$843
Mar 2020048330.341.86$897
Feb 2020245149.881.98$993
Jan 2020048357.252.09$1,012
Dec 20196748359.012.30$5,067
Nov 2019046755.302.75$1,285
Oct 2019048353.472.42$1,168
Sep 20190055.052.66$0
Aug 201911,58253.112.30$3,699
Jul 201901,52556.272.46$3,752
Jun 201941,53352.782.49$4,030
May 201991,61758.482.74$4,957
Apr 201901,49562.632.75$4,112
Mar 201901,63556.803.06$5,007
Feb 201901,46950.852.79$4,102
Jan 20192001,64646.033.23$14,520
Dec 201801,64046.594.19$6,864
Nov 201841,60452.934.24$7,008
Oct 201831,52961.443.40$5,380
Sep 201801,52059.543.11$4,724
Aug 201801,64059.403.07$5,029
Jul 201861,62765.142.93$5,161
Jun 201801,57160.183.08$4,834
May 201801,64065.382.90$4,757
Apr 201801,60263.842.90$4,647
Mar 201871,63061.222.79$4,971
Feb 2018161,55561.782.77$5,290
Jan 201801,57462.874.01$6,311
Dec 201721,65957.272.92$4,961
Nov 201721,65755.423.12$5,278
Oct 201701,89949.292.98$5,666
Sep 201721,66147.523.09$5,223
Aug 201711,68045.373.00$5,093
Jul 201711,92443.873.09$5,984
Jun 201701,86442.493.09$5,755
May 201711,75945.373.26$5,786
Apr 201701,57447.933.21$5,055
Mar 201701,66246.772.98$4,959
Feb 201701,49450.452.95$4,411
Jan 201701,67049.413.42$5,709
Dec 201601,56248.763.72$5,815
Nov 201601,16742.492.64$3,086
Oct 201601,22646.193.09$3,789
Sep 201601,20141.553.10$3,724
Aug 201601,24941.442.92$3,653
Jul 201601,25141.622.92$3,658
Jun 201601,19945.352.69$3,220
May 201601,26442.521.99$2,517
Apr 201601,23036.561.99$2,449
Mar 201601,28633.011.79$2,307
Feb 201601,20226.472.06$2,480
Jan 201601,30827.352.36$3,093
Dec 201501,20032.362.00$2,402
Nov 201501,18138.792.17$2,560
Oct 201511,28943.552.43$3,171
Sep 201501,26342.992.76$3,484
Aug 201511,33040.162.87$3,861
Jul 20151941,35048.152.95$13,317
Jun 201501,30156.152.88$3,751
May 201521,81555.212.96$5,475
Apr 201501,31849.822.71$3,567
Mar 201501,57642.892.93$4,625
Feb 201501,60544.662.98$4,777
Jan 201521,45843.433.10$4,608
Dec 201401,28654.693.59$4,618
Nov 201401,31370.464.25$5,583
Oct 201401,41078.303.90$5,500
Sep 201401,39686.164.05$5,647
Aug 201401,43289.394.04$5,778
Jul 201411,47296.564.18$6,249
Jun 201401,36798.164.74$6,475
May 201401,46094.734.73$6,901
Apr 201411,43395.944.81$6,987
Mar 201401,43695.895.06$7,262
Feb 201401,36997.406.19$8,477
Jan 201421,49290.404.86$7,433
Dec 201301,43891.824.35$6,262
Nov 201301,53388.853.74$5,731
Oct 201301,60797.423.78$6,073
Sep 201301,549104.113.72$5,759
Aug 201301,632104.253.52$5,749
Jul 20131971,635102.523.72$26,275
Jun 201301,59094.403.93$6,254
May 201311,60894.834.15$6,767
Apr 201311,60193.964.28$6,950
Mar 201311,61593.623.91$6,413
Feb 201301,36991.233.42$4,682
Jan 201301,66991.603.42$5,708
Dec 201201,65086.773.42$5,643
Nov 201201,69386.953.62$6,137
Oct 201211,68589.383.40$5,818
Sep 20121171,66194.672.92$15,924
Aug 201211,77992.662.91$5,266
Jul 201251,83585.133.02$5,969
Jun 201221,80379.822.52$4,701
May 201221,82691.612.49$4,727
Apr 201201,805101.652.00$3,604
Mar 201231,775105.052.22$4,259
Feb 201201,586101.102.57$4,076
Jan 201201,83698.092.73$5,020
Dec 201101,83496.873.24$5,942
Nov 201101,80795.723.31$5,983
Oct 20111712,00284.983.65$21,836
Sep 201102,26383.623.99$9,020
Aug 201101,60283.404.15$6,647
Jul 201101,92494.144.52$8,691
Jun 201101,95992.904.64$9,090
May 201102,17898.134.40$9,594
Apr 201102,349105.964.33$10,179
Mar 201101,52496.364.06$6,183
Feb 201101,72685.644.18$7,215
Jan 201102,21686.504.59$10,169
Dec 201002,21285.734.35$9,617
Nov 201002,11580.843.80$8,027
Oct 201002,36478.103.51$8,295
Sep 201002,44472.633.98$9,726
Aug 20101532,49273.684.42$22,286
Jul 201002,56672.554.74$12,154
Jun 201002,57770.364.91$12,654
May 201002,72871.124.24$11,554
Apr 201002,56481.694.12$10,571
Mar 201002,69178.394.39$11,810
Feb 201002,38573.585.44$12,980
Jan 201002,61874.365.96$15,614
Dec 200902,77071.445.48$15,190
Nov 200902,84874.593.75$10,684
Oct 200903,40172.544.11$13,979
Sep 200902,88565.543.06$8,842
Aug 200902,97967.423.22$9,588
Jul 200902,80561.133.46$9,718
Jun 200903,19766.163.90$12,452
May 200903,45754.743.93$13,571
Apr 200903,79046.773.59$13,597
Mar 200903,87842.144.06$15,741
Feb 20091833,53032.814.63$22,359
Jan 200903,57435.865.37$19,196
Dec 200803,68737.105.98$22,038
Nov 200803,80455.496.86$26,097
Oct 200804,25875.246.92$29,474
Sep 200803,960101.767.88$31,193
Aug 200804,485114.228.48$38,046
Jul 200805,090131.0811.39$57,972
Jun 200805,072131.3313.03$66,102
May 200805,388123.1711.57$62,362
Apr 200805,462110.3110.45$57,104
Mar 200805,912101.909.66$57,134
Feb 200805,83192.538.77$51,141
Jan 20081176,49490.388.21$63,862
Dec 200707,09988.337.30$51,837
Nov 200707,34691.677.29$53,565
Oct 200708,31482.856.92$57,549
Sep 200708,74575.846.24$54,605
Aug 20071779,54569.066.39$73,197
Jul 2007010,60870.906.39$67,763
Jun 200718711,49162.007.55$98,333
May 2007015,03658.747.85$117,977
Apr 200717815,83759.617.81$134,222
Mar 2007036,44056.927.30$266,084
Feb 2007017,20255.108.22$141,332

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Jun 2020 — as filed, then multipliedworked
Condensate             0 bbl  × $ 34.90 =         $0
Gas                  467 Mcf  × $  1.69 =       $789

────────────────────────────────────────────────────
Month total                                     $789

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well