HOOVER A

Operated by LATIGO PETROLEUM, LLC (P-5 488260) in the PATTEN (KRIDER) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 261472District 10Field 69658200Hydrogen sulphide fieldGasSaveExport
Value, all time
$568 k
Jan 2009 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
209
no gaps in the span
Streams
1
gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 63 leases and 63 wells, and the rule below applies to all of them.

Discovered
1994-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,200 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 320 acres. The field rule took effect on 1998-01-06.

The register flags this field for hydrogen sulphide. That is a poisonous gas that occurs naturally in some formations. The flag is a property of the field as the Commission records it. It is not a measurement taken at this lease, and it is not a statement that gas is escaping anywhere.

The Commission's schedule remark for this field reads: RULE 2 AMENDED PER DOCKET 10-0205601 TO 467/1200.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
GasProduction141,146 Mcf$567,642
Total$567,642

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 36.0824, -101.3081. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

36.08238, -101.30811 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
3,269 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 3,269 ft.

Completions filed
Jan 2009
1 of 1 wells

1 well

42-1953182943,269 ftJan 2009

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (209)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

209 months

May 20260106.413.05$0
Apr 2026098.932.87$0
Mar 2026089.753.15$0
Feb 2026063.503.75$0
Jan 2026059.138.00$0
Dec 2025056.664.41$0
Nov 2025058.593.93$0
Oct 2025059.383.30$0
Sep 2025062.743.08$0
Aug 2025063.933.01$0
Jul 2025066.743.32$0
Jun 2025066.483.13$0
May 2025060.553.23$0
Apr 2025062.363.54$0
Mar 2025067.704.27$0
Feb 2025070.884.34$0
Jan 2025074.324.28$0
Dec 2024068.993.12$0
Nov 2024069.052.20$0
Oct 2024071.372.28$0
Sep 2024069.612.36$0
Aug 2024075.632.06$0
Jul 2024079.932.15$0
Jun 2024078.082.63$0
May 2024078.812.20$0
Apr 2024084.451.66$0
Mar 2024080.301.55$0
Feb 2024076.091.78$0
Jan 2024073.023.30$0
Dec 2023071.262.61$0
Nov 2023077.892.81$0
Oct 2023085.443.09$0
Sep 2023089.042.74$0
Aug 2023080.522.67$0
Jul 2023074.852.64$0
Jun 2023068.962.26$0
May 2023070.622.23$0
Apr 2023078.122.24$0
Mar 2023072.852.39$0
Feb 2023075.112.47$0
Jan 2023076.533.39$0
Dec 2022076.415.73$0
Nov 2022085.005.65$0
Oct 2022087.185.86$0
Sep 2022084.888.16$0
Aug 2022094.529.13$0
Jul 20220101.587.54$0
Jun 20220115.097.98$0
May 20220109.378.43$0
Apr 20220104.226.84$0
Mar 20220108.885.08$0
Feb 2022091.054.86$0
Jan 2022081.844.54$0
Dec 2021071.323.90$0
Nov 2021077.435.24$0
Oct 2021079.795.71$0
Sep 2021069.865.35$0
Aug 2021066.024.22$0
Jul 2021070.783.98$0
Jun 2021069.493.38$0
May 2021063.483.02$0
Apr 2021060.362.76$0
Mar 2021061.302.72$0
Feb 2021057.805.55$0
Jan 2021050.412.81$0
Dec 2020044.642.68$0
Nov 2020038.772.71$0
Oct 2020036.972.48$0
Sep 2020037.091.99$0
Aug 2020039.982.39$0
Jul 2020038.371.83$0
Jun 2020034.901.69$0
May 2020016.921.81$0
Apr 2020014.751.80$0
Mar 2020030.341.86$0
Feb 2020049.881.98$0
Jan 2020057.252.09$0
Dec 2019059.012.30$0
Nov 2019055.302.75$0
Oct 2019053.472.42$0
Sep 2019055.052.66$0
Aug 2019053.112.30$0
Jul 2019056.272.46$0
Jun 2019052.782.49$0
May 2019058.482.74$0
Apr 2019062.632.75$0
Mar 2019056.803.06$0
Feb 2019050.852.79$0
Jan 2019046.033.23$0
Dec 2018046.594.19$0
Nov 2018052.934.24$0
Oct 2018061.443.40$0
Sep 2018059.543.11$0
Aug 2018059.403.07$0
Jul 2018065.142.93$0
Jun 2018060.183.08$0
May 2018065.382.90$0
Apr 2018063.842.90$0
Mar 2018061.222.79$0
Feb 2018061.782.77$0
Jan 2018062.874.01$0
Dec 2017057.272.92$0
Nov 2017055.423.12$0
Oct 2017049.292.98$0
Sep 2017047.523.09$0
Aug 2017045.373.00$0
Jul 2017043.873.09$0
Jun 2017042.493.09$0
May 2017045.373.26$0
Apr 2017047.933.21$0
Mar 2017046.772.98$0
Feb 2017050.452.95$0
Jan 2017049.413.42$0
Dec 2016048.763.72$0
Nov 2016042.492.64$0
Oct 2016046.193.09$0
Sep 2016041.553.10$0
Aug 2016041.442.92$0
Jul 2016041.622.92$0
Jun 2016045.352.69$0
May 2016042.521.99$0
Apr 2016036.561.99$0
Mar 2016533.011.79$9
Feb 2016026.472.06$0
Jan 2016027.352.36$0
Dec 201513732.362.00$274
Nov 20159938.792.17$215
Oct 201528543.552.43$692
Sep 201543442.992.76$1,197
Aug 201524240.162.87$695
Jul 201559748.152.95$1,758
Jun 201554956.152.88$1,583
May 201568555.212.96$2,024
Apr 201561749.822.71$1,670
Mar 201564042.892.93$1,878
Feb 201564044.662.98$1,905
Jan 201573943.433.10$2,291
Dec 201458954.693.59$2,115
Nov 201470970.464.25$3,015
Oct 201471478.303.90$2,785
Sep 20141,03386.164.05$4,179
Aug 201492489.394.04$3,728
Jul 2014196.564.18$4
Jun 201418498.164.74$872
May 201459394.734.73$2,803
Apr 201462295.944.81$2,991
Mar 201487595.895.06$4,425
Feb 201488697.406.19$5,486
Jan 201495490.404.86$4,637
Dec 201376791.824.35$3,340
Nov 20131,23088.853.74$4,598
Oct 20131,83897.423.78$6,946
Sep 2013722104.113.72$2,684
Aug 2013150104.253.52$528
Jul 2013220102.523.72$818
Jun 201321094.403.93$826
May 201322094.834.15$913
Apr 20135793.964.28$244
Mar 201316193.623.91$630
Feb 201319791.233.42$674
Jan 201322591.603.42$769
Dec 201222186.773.42$756
Nov 201222986.953.62$830
Oct 201227689.383.40$938
Sep 201222094.672.92$642
Aug 201233692.662.91$977
Jul 201295585.133.02$2,885
Jun 2012079.822.52$0
May 20121,24091.612.49$3,086
Apr 20121,512101.652.00$3,019
Mar 20121,531105.052.22$3,402
Feb 20121,593101.102.57$4,094
Jan 20121,79698.092.73$4,910
Dec 20111,72596.873.24$5,589
Nov 20111,33495.723.31$4,417
Oct 20111,77984.983.65$6,491
Sep 20111,82283.623.99$7,262
Aug 20111,90483.404.15$7,900
Jul 20111,86994.144.52$8,443
Jun 20111,73592.904.64$8,050
May 20112,00098.134.40$8,810
Apr 20112,042105.964.33$8,849
Mar 20112,12296.364.06$8,610
Feb 20111,98885.644.18$8,310
Jan 20112,40986.504.59$11,054
Dec 20102,31185.734.35$10,048
Nov 20102,41180.843.80$9,151
Oct 20102,47278.103.51$8,674
Sep 20102,53872.633.98$10,100
Aug 20102,30673.684.42$10,191
Jul 20102,63972.554.74$12,500
Jun 20102,66770.364.91$13,096
May 20102,99371.124.24$12,676
Apr 20102,81881.694.12$11,618
Mar 20103,08178.394.39$13,521
Feb 20102,63673.585.44$14,346
Jan 20102,97374.365.96$17,731
Dec 20092,91771.445.48$15,996
Nov 20093,47674.593.75$13,040
Oct 20093,37872.544.11$13,884
Sep 20093,98865.543.06$12,222
Aug 20094,26967.423.22$13,740
Jul 20094,48761.133.46$15,545
Jun 20094,79266.163.90$18,665
May 20096,04154.743.93$23,715
Apr 20095,98146.773.59$21,457
Mar 20096,81242.144.06$27,650
Feb 20097,19132.814.63$33,316
Jan 20093,58135.865.37$19,234

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Mar 2016 — as filed, then multipliedworked
Gas                    5 Mcf  × $  1.79 =         $9

────────────────────────────────────────────────────
Month total                                       $9

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 10/G/261472 is the state's own key, not one this site invented.