WILLIAMS, JUANITA

Operated by BRAKA OPERATING, L.L.C. (P-5 88563) in the REB (MARBLE FALLS) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 119650District 7BField 75095500CondensateGasSaveExport
Value, all time
$50 k
Jan 1993 – Oct 2013
Value, last 12 filed months
$0
at the published price for each month
Months reported
250
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 431 leases and 525 wells, and the rule below applies to all of them.

Discovered
1982-03-12
as the register files it
Field class
Oil and gas
the register's own label
Between wells
933 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 1986-01-01.

The Commission's schedule remark for this field reads: EFF. 09-10-84 PER DOCKET #7B-82,934

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition42 bbl$576
GasProduction24,079 Mcf$49,916
Total$50,492

12,480 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.4534, -98.8187. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.45341, -98.81865 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
3,583 ft
1 wells filed one
Completion to plug
29.2 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 3,583 ft.

Completions filed
Aug 1984
1 of 1 wells
Plug dates filed
Oct 2013
1 of 1 wells

Last completion to plug: a median of 29.2 years across the 1 well that filed both dates, with the middle half between 29.2 years and 29.2 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-1333598623,583 ftAug 1984Oct 2013Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (250)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

250 months

Oct 20130097.423.78$0
Sep 201300104.113.72$0
Aug 201300104.253.52$0
Jul 201300102.523.72$0
Jun 20130094.403.93$0
May 20130094.834.15$0
Apr 20130093.964.28$0
Mar 20130093.623.91$0
Feb 20130091.233.42$0
Jan 20130091.603.42$0
Dec 20120086.773.42$0
Nov 20120086.953.62$0
Oct 20120089.383.40$0
Sep 20120094.672.92$0
Aug 20120092.662.91$0
Jul 20120085.133.02$0
Jun 20120079.822.52$0
May 20120091.612.49$0
Apr 201200101.652.00$0
Mar 201200105.052.22$0
Feb 201200101.102.57$0
Jan 20120098.092.73$0
Dec 20110096.873.24$0
Nov 20110095.723.31$0
Oct 20110084.983.65$0
Sep 20110083.623.99$0
Aug 20110083.404.15$0
Jul 20110094.144.52$0
Jun 20110092.904.64$0
May 20110098.134.40$0
Apr 201100105.964.33$0
Mar 20110096.364.06$0
Feb 20110085.644.18$0
Jan 20110086.504.59$0
Dec 20100085.734.35$0
Nov 201002980.843.80$110
Oct 201004078.103.51$140
Sep 201003172.633.98$123
Aug 201003473.684.42$150
Jul 201003172.554.74$147
Jun 201003370.364.91$162
May 201003171.124.24$131
Apr 201003381.694.12$136
Mar 201002978.394.39$127
Feb 201002373.585.44$125
Jan 201002074.365.96$119
Dec 200902571.445.48$137
Nov 200902474.593.75$90
Oct 200902972.544.11$119
Sep 200903065.543.06$92
Aug 200903167.423.22$100
Jul 200903161.133.46$107
Jun 200903666.163.90$140
May 200903754.743.93$145
Apr 200902746.773.59$97
Mar 200901542.144.06$61
Feb 20090632.814.63$28
Jan 200902235.865.37$118
Dec 200801937.105.98$114
Nov 200801555.496.86$103
Oct 200802275.246.92$152
Sep 2008028101.767.88$221
Aug 2008030114.228.48$254
Jul 2008032131.0811.39$364
Jun 2008034131.3313.03$443
May 2008038123.1711.57$440
Apr 2008036110.3110.45$376
Mar 2008026101.909.66$251
Feb 200801592.538.77$132
Jan 200801090.388.21$82
Dec 200701588.337.30$110
Nov 200703391.677.29$241
Oct 200702482.856.92$166
Sep 200702175.846.24$131
Aug 20070869.066.39$51
Jul 200702770.906.39$172
Jun 200703262.007.55$242
May 200704458.747.85$345
Apr 200703959.617.81$304
Mar 200703556.927.30$256
Feb 200701555.108.22$123
Jan 200702850.306.73$188
Dec 200603556.656.92$242
Nov 200602454.207.62$183
Oct 200604454.906.01$265
Sep 200603660.085.04$181
Aug 200603568.717.34$257
Jul 200604369.376.34$273
Jun 200601566.286.38$96
May 200602766.016.42$173
Apr 200603564.397.36$258
Mar 200605056.707.08$354
Feb 200604457.597.75$341
Jan 200605060.598.93$447
Dec 200505154.9413.42$684
Nov 200504954.6910.59$519
Oct 200506058.3413.80$828
Sep 200505461.4512.08$652
Aug 200505761.519.80$558
Jul 200502755.697.84$212
Jun 200501952.337.38$140
May 200503045.226.65$200
Apr 200503849.207.36$280
Mar 200503650.377.15$258
Feb 200503545.226.31$221
Jan 200504243.166.32$266
Dec 200404139.866.75$277
Nov 200404045.286.33$253
Oct 200404749.706.52$306
Sep 200404843.245.28$254
Aug 200405642.375.55$311
Jul 200405438.286.08$329
Jun 200404736.106.43$302
May 200404437.486.49$286
Apr 200404334.475.86$252
Mar 200404434.365.53$243
Feb 200404732.455.51$259
Jan 200402732.036.30$170
Dec 200302430.266.30$151
Nov 200302528.804.60$115
Oct 200302528.174.76$119
Sep 200302426.314.75$114
Aug 200302529.765.13$128
Jul 200303529.415.17$181
Jun 200304628.565.98$275
May 200303426.595.97$203
Apr 200302226.675.41$119
Mar 200302031.146.10$122
Feb 200301933.487.93$151
Jan 200302230.315.58$123
Dec 200202326.914.85$112
Nov 200202224.664.14$91
Oct 200202126.464.23$89
Sep 200203027.443.64$109
Aug 200203425.963.16$108
Jul 200202424.583.06$73
Jun 200202123.733.34$70
May 200201924.663.58$68
Apr 200202923.653.51$102
Mar 200202822.003.10$87
Feb 200201818.222.38$43
Jan 200201017.172.38$24
Dec 200105716.932.36$135
Nov 200104018.072.41$96
Oct 200101919.782.53$48
Sep 200104124.262.25$92
Aug 2001013424.873.05$409
Jul 2001013323.933.20$425
Jun 2001011824.563.82$451
May 2001016725.524.31$719
Apr 20010024.685.34$0
Mar 200109524.545.38$511
Feb 2001024027.755.77$1,384
Jan 2001042827.478.40$3,595
Dec 2000026626.889.12$2,427
Nov 2000018532.215.66$1,047
Oct 2000014331.235.15$736
Sep 2000012631.875.19$654
Aug 2000012729.644.54$577
Jul 200009128.534.09$372
Jun 200003629.304.40$158
May 2000011127.263.68$408
Apr 200007224.513.12$224
Mar 2000010228.422.86$292
Feb 200007527.622.73$204
Jan 200007625.272.48$189
Dec 199907924.282.42$191
Nov 199907423.192.43$180
Oct 199907320.982.80$205
Sep 199906921.752.62$181
Aug 199907319.262.88$210
Jul 199906617.892.37$157
Jun 199907615.942.36$180
May 199907115.792.32$165
Apr 199907215.102.21$159
Mar 199907412.471.84$136
Feb 19990659.981.82$118
Jan 199908210.381.90$156
Dec 199801879.201.77$332
Nov 1998040010.892.19$874
Oct 1998020012.421.97$394
Sep 1998025712.592.08$535
Aug 1998018011.301.91$343
Jul 1998018211.742.24$407
Jun 1998020211.242.24$452
May 1998018512.622.21$408
Apr 19983519013.042.51$932
Mar 1998021312.802.31$492
Feb 1998016913.952.30$389
Jan 1998018214.702.15$392
Dec 1997018416.322.41$444
Nov 1997016818.193.09$519
Oct 1997020519.253.15$646
Sep 1997020117.742.95$594
Aug 1997037517.862.55$958
Jul 1997010717.582.25$240
Jun 1997010817.242.26$244
May 1997010918.972.31$252
Apr 199703317.882.08$69
Mar 199703018.951.94$58
Feb 1997013620.492.21$300
Jan 1997029323.483.54$1,037
Dec 1996022223.32$0
Nov 1996024221.97$0
Oct 1996022923.31$0
Sep 1996023522.22$0
Aug 1996023920.26$0
Jul 1996028219.55$0
Jun 1996027718.73$0
May 1996025919.43$0
Apr 1996025121.51$0
Mar 1996031119.38$0
Feb 1996029416.98$0
Jan 1996019517.07$0
Dec 1995123017.19$17
Nov 1995025016.00$0
Oct 1995029515.43$0
Sep 1995028016.18$0
Aug 1995031515.92$0
Jul 1995027815.24$0
Jun 1995029216.41$0
May 1995029517.56$0
Apr 1995027317.73$0
Mar 1995027016.44$0
Feb 1995023416.58$0
Jan 1995027515.92$0
Dec 1994024315.03$0
Nov 1994022515.90$0
Oct 1994023915.58$0
Sep 1994024115.29$0
Aug 1994024516.13$0
Jul 1994025317.56$0
Jun 1994023817.09$0
May 1994023415.88$0
Apr 1994023914.14$0
Mar 1994024812.46$0
Feb 1994022412.50$0
Jan 1994026312.66$0
Dec 1993025412.33$0
Nov 1993024314.49$0
Oct 1993129415.85$16
Sep 1993028915.03$0
Aug 1993131815.66$16
Jul 1993028915.46$0
Jun 1993026616.79$0
May 1993128317.68$18
Apr 1993126918.05$18
Mar 1993126718.14$18
Feb 1993024017.90$0
Jan 1993125316.93$17

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Nov 2010 — as filed, then multipliedworked
Condensate             0 bbl  × $ 80.84 =         $0
Gas                   29 Mcf  × $  3.80 =       $110

────────────────────────────────────────────────────
Month total                                     $110

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7B/G/119650 is the state's own key, not one this site invented.