SIMMONS 71

Operated by UPP OPERATING, LLC (P-5 875310) in the SAWYER (CANYON) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 202822District 7CField 812673332 tax incentive programmesCondensateGasSaveExport
Value, all time
$910 k
Jan 2004 – May 2026
Value, last 12 filed months
$77
at the published price for each month
Months reported
269
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112004-11-22156088
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition305 bbl$16,480
GasProduction132,328 Mcf$893,027
Total$909,507

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.6721, -100.7748. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.67209, -100.77483 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
7,908 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,908 ft.

Completions filed
Jan 2004
1 of 1 wells

1 well

42-4353659557,908 ftJan 2004

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (269)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

269 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260163.503.75$4
Jan 20260259.138.00$16
Dec 20250256.664.41$9
Nov 20250258.593.93$8
Oct 20250159.383.30$3
Sep 20250262.743.08$6
Aug 20250363.933.01$9
Jul 20250366.743.32$10
Jun 20250466.483.13$13
May 202501160.553.23$36
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250170.884.34$4
Jan 20250374.324.28$13
Dec 20240368.993.12$9
Nov 20240369.052.20$7
Oct 20240471.372.28$9
Sep 20240369.612.36$7
Aug 20240375.632.06$6
Jul 20240379.932.15$6
Jun 20240378.082.63$8
May 20240478.812.20$9
Apr 20240484.451.66$7
Mar 20240380.301.55$5
Feb 20240476.091.78$7
Jan 20240373.023.30$10
Dec 20230471.262.61$10
Nov 20230477.892.81$11
Oct 20230485.443.09$12
Sep 20230489.042.74$11
Aug 20230580.522.67$13
Jul 20230674.852.64$16
Jun 20230568.962.26$11
May 20230570.622.23$11
Apr 20230678.122.24$13
Mar 20230672.852.39$14
Feb 20230775.112.47$17
Jan 20230776.533.39$24
Dec 20220776.415.73$40
Nov 202201285.005.65$68
Oct 202211187.185.86$152
Sep 20220084.888.16$0
Aug 20220694.529.13$55
Jul 202288101.587.54$873
Jun 2022013115.097.98$104
May 20222027109.378.43$2,415
Apr 2022023104.226.84$157
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20213071.323.90$214
Nov 20210077.435.24$0
Oct 20212079.795.71$160
Sep 20210069.865.35$0
Aug 20218066.024.22$528
Jul 202183170.783.98$690
Jun 20210269.493.38$7
May 20211063.483.02$63
Apr 202103660.362.76$99
Mar 20212061.302.72$123
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20201144.642.68$47
Nov 20203138.772.71$119
Oct 20200036.972.48$0
Sep 20200137.091.99$2
Aug 20206939.982.39$261
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20202330.341.86$66
Feb 20200249.881.98$4
Jan 202002257.252.09$46
Dec 201902559.012.30$58
Nov 201902255.302.75$61
Oct 201902553.472.42$60
Sep 201902555.052.66$66
Aug 201902753.112.30$62
Jul 201902756.272.46$66
Jun 201902452.782.49$60
May 201902558.482.74$69
Apr 201902662.632.75$72
Mar 201902756.803.06$83
Feb 201902650.852.79$73
Jan 201902846.033.23$90
Dec 201802946.594.19$121
Nov 201802552.934.24$106
Oct 201802561.443.40$85
Sep 201802559.543.11$78
Aug 201802759.403.07$83
Jul 201812665.142.93$141
Jun 201802760.183.08$83
May 201803065.382.90$87
Apr 201813363.842.90$160
Mar 201813361.222.79$153
Feb 201802861.782.77$77
Jan 201813262.874.01$191
Dec 201703257.272.92$93
Nov 201703255.423.12$100
Oct 201703349.292.98$98
Sep 201703347.523.09$102
Aug 201703645.373.00$108
Jul 201703643.873.09$111
Jun 201703442.493.09$105
May 201703845.373.26$124
Apr 201703647.933.21$116
Mar 201703846.772.98$113
Feb 201703450.452.95$100
Jan 201704049.413.42$137
Dec 201603848.763.72$141
Nov 201603742.492.64$98
Oct 201604046.193.09$124
Sep 201604041.553.10$124
Aug 201604341.442.92$126
Jul 201604541.622.92$132
Jun 201604645.352.69$124
May 201604842.521.99$96
Apr 201614736.561.99$130
Mar 201624833.011.79$152
Feb 201684526.472.06$305
Jan 201604627.352.36$109
Dec 201524632.362.00$157
Nov 201504738.792.17$102
Oct 201505043.552.43$121
Sep 201504842.992.76$132
Aug 201504940.162.87$141
Jul 201505148.152.95$150
Jun 201505056.152.88$144
May 201504555.212.96$133
Apr 201502149.822.71$57
Mar 201504242.892.93$123
Feb 201503744.662.98$110
Jan 201504343.433.10$133
Dec 201404354.693.59$154
Nov 201404270.464.25$179
Oct 201404778.303.90$183
Sep 201404486.164.05$178
Aug 201404589.394.04$182
Jul 201404696.564.18$192
Jun 201404798.164.74$223
May 201404994.734.73$232
Apr 201405195.944.81$245
Mar 201404895.895.06$243
Feb 201404197.406.19$254
Jan 201404890.404.86$233
Dec 201304791.824.35$205
Nov 201306888.853.74$254
Oct 201304097.423.78$151
Sep 2013051104.113.72$190
Aug 2013057104.253.52$201
Jul 2013055102.523.72$204
Jun 201305394.403.93$208
May 201305994.834.15$245
Apr 201305793.964.28$244
Mar 201305993.623.91$231
Feb 201305791.233.42$195
Jan 201306191.603.42$209
Dec 201206386.773.42$215
Nov 201206086.953.62$218
Oct 201206789.383.40$228
Sep 201206694.672.92$193
Aug 201207192.662.91$206
Jul 201208785.133.02$263
Jun 201209879.822.52$247
May 2012010591.612.49$261
Apr 20120120101.652.00$240
Mar 20120200105.052.22$444
Feb 201200101.102.57$0
Jan 20120098.092.73$0
Dec 20110096.873.24$0
Nov 20110095.723.31$0
Oct 20110084.983.65$0
Sep 20110083.623.99$0
Aug 20110083.404.15$0
Jul 20110094.144.52$0
Jun 20110092.904.64$0
May 20110098.134.40$0
Apr 201100105.964.33$0
Mar 20110096.364.06$0
Feb 20110085.644.18$0
Jan 20110086.504.59$0
Dec 20100885.734.35$35
Nov 201003180.843.80$118
Oct 201004078.103.51$140
Sep 201004572.633.98$179
Aug 201003673.684.42$159
Jul 201003972.554.74$185
Jun 201007770.364.91$378
May 201009471.124.24$398
Apr 201007281.694.12$297
Mar 2010010578.394.39$461
Feb 201005773.585.44$310
Jan 2010011174.365.96$662
Dec 2009113471.445.48$806
Nov 2009123674.593.75$960
Oct 2009011072.544.11$452
Sep 2009012765.543.06$389
Aug 2009012667.423.22$406
Jul 2009015961.133.46$551
Jun 2009013866.163.90$538
May 2009029354.743.93$1,150
Apr 2009130946.773.59$1,155
Mar 2009140242.144.06$1,674
Feb 2009136832.814.63$1,738
Jan 2009035735.865.37$1,917
Dec 2008138637.105.98$2,344
Nov 2008139555.496.86$2,765
Oct 2008151975.246.92$3,668
Sep 20080220101.767.88$1,733
Aug 20081393114.228.48$3,448
Jul 20080431131.0811.39$4,909
Jun 20081432131.3313.03$5,761
May 20080425123.1711.57$4,919
Apr 20081413110.3110.45$4,428
Mar 20080361101.909.66$3,489
Feb 2008131592.538.77$2,855
Jan 2008134090.388.21$2,880
Dec 2007162988.337.30$4,681
Nov 2007359391.677.29$4,599
Oct 2007264782.856.92$4,644
Sep 2007142775.846.24$2,742
Aug 2007158769.066.39$3,819
Jul 2007161370.906.39$3,987
Jun 2007163562.007.55$4,855
May 2007381958.747.85$6,602
Apr 2007385059.617.81$6,813
Mar 2007371156.927.30$5,362
Feb 2007393755.108.22$7,864
Jan 200741,22050.306.73$8,408
Dec 200641,08156.656.92$7,705
Nov 200631,05554.207.62$8,199
Oct 2006197454.906.01$5,912
Sep 200631,00260.085.04$5,228
Aug 200601,16568.717.34$8,551
Jul 200611,24069.376.34$7,934
Jun 200621,03666.286.38$6,746
May 200601,34266.016.42$8,622
Apr 200621,50864.397.36$11,228
Mar 200661,54656.707.08$11,290
Feb 200631,52857.597.75$12,016
Jan 200631,97560.598.93$17,825
Dec 200562,07854.9413.42$28,207
Nov 200531,75254.6910.59$18,715
Oct 200522,67058.3413.80$36,951
Sep 200501,50961.4512.08$18,227
Aug 200531,93761.519.80$19,161
Jul 200502,17755.697.84$17,076
Jun 200532,17152.337.38$16,181
May 200542,37345.226.65$15,964
Apr 200502,05949.207.36$15,155
Mar 200592,38150.377.15$17,489
Feb 200502,18445.226.31$13,785
Jan 200562,64843.166.32$17,000
Dec 200462,85739.866.75$19,527
Nov 200473,01145.286.33$19,378
Oct 200402,68649.706.52$17,500
Sep 200493,96243.245.28$21,324
Aug 2004103,94642.375.55$22,327
Jul 2004134,64538.286.08$28,759
Jun 2004124,96136.106.43$32,347
May 2004155,79637.486.49$38,205
Apr 2004146,80034.475.86$40,320
Mar 2004158,31834.365.53$46,515
Feb 20041910,25432.455.51$57,112
Jan 2004012,30332.036.30$77,504

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Feb 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $ 63.50 =         $0
Gas                    1 Mcf  × $  3.75 =         $4

────────────────────────────────────────────────────
Month total                                       $4

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/202822 is the state's own key, not one this site invented.