WILSON, DUKE 173

Operated by UPP OPERATING, LLC (P-5 875310) in the SAWYER (CANYON) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 211995District 7CField 812673332 tax incentive programmesCondensateGasSaveExport
Value, all time
$834 k
Mar 2005 – May 2026
Value, last 12 filed months
$6 k
at the published price for each month
Months reported
255
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112006-12-20172014
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition93 bbl$6,560
GasProduction148,043 Mcf$826,984
Total$833,544

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.4402, -100.7572. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.44017, -100.75718 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
8,850 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 8,850 ft.

Completions filed
Mar 2005
1 of 1 wells

1 well

42-43537169108,850 ftMar 2005

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (255)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

255 months

May 20260250106.413.05$761
Apr 2026043898.932.87$1,257
Mar 2026027089.753.15$850
Feb 202603763.503.75$139
Jan 202605159.138.00$408
Dec 202507056.664.41$309
Nov 202507058.593.93$275
Oct 202507759.383.30$254
Sep 202508262.743.08$252
Aug 202517563.933.01$290
Jul 202529566.743.32$448
Jun 2025121566.483.13$739
May 2025726760.553.23$1,287
Apr 2025231962.363.54$1,255
Mar 2025044667.704.27$1,904
Feb 2025020170.884.34$873
Jan 2025033074.324.28$1,412
Dec 2024034068.993.12$1,061
Nov 2024132769.052.20$788
Oct 2024330971.372.28$919
Sep 2024028769.612.36$679
Aug 2024032875.632.06$677
Jul 2024036079.932.15$773
Jun 2024020378.082.63$535
May 2024037678.812.20$827
Apr 2024145084.451.66$831
Mar 2024044080.301.55$680
Feb 2024141476.091.78$815
Jan 2024046973.023.30$1,547
Dec 2023048671.262.61$1,269
Nov 2023448077.892.81$1,659
Oct 2023547885.443.09$1,903
Sep 2023042189.042.74$1,151
Aug 2023342780.522.67$1,383
Jul 2023051874.852.64$1,368
Jun 2023151268.962.26$1,225
May 2023052370.622.23$1,165
Apr 202308178.122.24$181
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230176.533.39$3
Dec 20220476.415.73$23
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 2022013115.097.98$104
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210961.302.72$24
Feb 202108657.805.55$477
Jan 202109550.412.81$267
Dec 202009544.642.68$254
Nov 202009238.772.71$249
Oct 202009536.972.48$235
Sep 202009237.091.99$183
Aug 202009539.982.39$227
Jul 202009538.371.83$173
Jun 202009234.901.69$156
May 202009516.921.81$172
Apr 202009214.751.80$166
Mar 202009530.341.86$176
Feb 202008949.881.98$176
Jan 2020015157.252.09$316
Dec 2019012559.012.30$288
Nov 201909255.302.75$253
Oct 201909553.472.42$230
Sep 201919255.052.66$300
Aug 201909553.112.30$219
Jul 2019010156.272.46$248
Jun 2019112052.782.49$352
May 2019014758.482.74$403
Apr 2019014962.632.75$410
Mar 2019115756.803.06$538
Feb 2019014450.852.79$402
Jan 2019015446.033.23$497
Dec 2018114846.594.19$666
Nov 2018214252.934.24$708
Oct 2018014761.443.40$500
Sep 2018014459.543.11$448
Aug 2018215059.403.07$579
Jul 2018216165.142.93$602
Jun 201809660.183.08$295
May 2018313065.382.90$573
Apr 2018414163.842.90$664
Mar 2018716761.222.79$894
Feb 2018017561.782.77$484
Jan 2018644962.874.01$2,177
Dec 2017064257.272.92$1,876
Nov 2017073355.423.12$2,286
Oct 2017085449.292.98$2,548
Sep 2017079447.523.09$2,451
Aug 2017078145.373.00$2,346
Jul 2017051543.873.09$1,590
Jun 2017020942.493.09$645
May 2017021445.373.26$698
Apr 2017020847.933.21$668
Mar 2017022046.772.98$656
Feb 2017021350.452.95$629
Jan 2017023349.413.42$797
Dec 2016023348.763.72$867
Nov 2016022842.492.64$603
Oct 2016022746.193.09$701
Sep 2016019941.553.10$617
Aug 2016121241.442.92$661
Jul 2016021441.622.92$626
Jun 2016037645.352.69$1,010
May 2016074042.521.99$1,473
Apr 2016072336.561.99$1,440
Mar 2016123133.011.79$447
Feb 2016028526.472.06$588
Jan 2016067427.352.36$1,594
Dec 2015166432.362.00$1,361
Nov 2015069138.792.17$1,498
Oct 2015183943.552.43$2,079
Sep 2015130342.992.76$879
Aug 2015024940.162.87$715
Jul 2015159748.152.95$1,806
Jun 2015065256.152.88$1,880
May 2015068855.212.96$2,033
Apr 2015069049.822.71$1,868
Mar 2015173142.892.93$2,188
Feb 2015077244.662.98$2,298
Jan 2015038643.433.10$1,197
Dec 2014023154.693.59$830
Nov 2014040470.464.25$1,718
Oct 2014056378.303.90$2,196
Sep 2014064586.164.05$2,609
Aug 2014068289.394.04$2,752
Jul 2014167896.564.18$2,930
Jun 2014069298.164.74$3,278
May 2014075594.734.73$3,569
Apr 2014066295.944.81$3,184
Mar 2014072195.895.06$3,646
Feb 2014056597.406.19$3,498
Jan 2014052990.404.86$2,571
Dec 2013066291.824.35$2,883
Nov 2013068088.853.74$2,542
Oct 2013066997.423.78$2,528
Sep 20130679104.113.72$2,524
Aug 20130582104.253.52$2,050
Jul 20130664102.523.72$2,469
Jun 2013066294.403.93$2,604
May 2013029094.834.15$1,203
Apr 2013048293.964.28$2,064
Mar 2013066393.623.91$2,594
Feb 2013060491.233.42$2,066
Jan 2013064691.603.42$2,209
Dec 2012251086.773.42$1,918
Nov 2012064886.953.62$2,349
Oct 2012569289.383.40$2,799
Sep 2012066794.672.92$1,947
Aug 2012069792.662.91$2,027
Jul 2012069485.133.02$2,096
Jun 2012069979.822.52$1,761
May 2012075291.612.49$1,871
Apr 20120732101.652.00$1,462
Mar 20122832105.052.22$2,059
Feb 20120563101.102.57$1,447
Jan 2012073798.092.73$2,015
Dec 2011280096.873.24$2,786
Nov 2011279595.723.31$2,824
Oct 2011685384.983.65$3,622
Sep 2011086783.623.99$3,456
Aug 2011099283.404.15$4,116
Jul 2011178994.144.52$3,658
Jun 2011080092.904.64$3,712
May 2011072798.134.40$3,202
Apr 20110634105.964.33$2,747
Mar 2011058596.364.06$2,374
Feb 2011154085.644.18$2,343
Jan 2011036286.504.59$1,661
Dec 2010060185.734.35$2,613
Nov 2010048580.843.80$1,841
Oct 2010071578.103.51$2,509
Sep 2010256772.633.98$2,402
Aug 2010070473.684.42$3,111
Jul 2010045072.554.74$2,131
Jun 2010036470.364.91$1,787
May 2010078371.124.24$3,316
Apr 2010076581.694.12$3,154
Mar 2010074978.394.39$3,287
Feb 2010098273.585.44$5,344
Jan 2010085074.365.96$5,069
Dec 2009075071.445.48$4,113
Nov 200901,22474.593.75$4,592
Oct 20090072.544.11$0
Sep 20090065.543.06$0
Aug 2009079967.423.22$2,572
Jul 2009055461.133.46$1,919
Jun 2009087766.163.90$3,416
May 2009082454.743.93$3,235
Apr 2009089746.773.59$3,218
Mar 2009094642.144.06$3,840
Feb 2009092732.814.63$4,295
Jan 2009093635.865.37$5,027
Dec 200801,01437.105.98$6,061
Nov 200801,01655.496.86$6,970
Oct 200801,02175.246.92$7,067
Sep 200801,072101.767.88$8,444
Aug 200801,055114.228.48$8,950
Jul 200801,153131.0811.39$13,132
Jun 200801,034131.3313.03$13,476
May 200801,179123.1711.57$13,646
Apr 200801,147110.3110.45$11,992
Mar 200801,086101.909.66$10,495
Feb 200801,08292.538.77$9,490
Jan 2008090090.388.21$7,385
Dec 200701,03588.337.30$7,558
Nov 200701,17791.677.29$8,582
Oct 200701,29582.856.92$8,964
Sep 200701,34375.846.24$8,386
Aug 200701,51269.066.39$9,659
Jul 200701,65670.906.39$10,578
Jun 200701,06262.007.55$8,016
May 2007040858.747.85$3,201
Apr 2007038559.617.81$3,005
Mar 2007039256.927.30$2,862
Feb 2007040455.108.22$3,319
Jan 200701,43050.306.73$9,619
Dec 200601,42156.656.92$9,831
Nov 200601,34754.207.62$10,261
Oct 200601,40354.906.01$8,437
Sep 200601,39260.085.04$7,012
Aug 200601,47968.717.34$10,856
Jul 200601,52969.376.34$9,698
Jun 200601,53366.286.38$9,786
May 200601,61066.016.42$10,344
Apr 200601,76464.397.36$12,984
Mar 200601,87556.707.08$13,280
Feb 200601,41257.597.75$10,945
Jan 200601,97760.598.93$17,661
Dec 200501,84454.9413.42$24,738
Nov 200501,84254.6910.59$19,504
Oct 200501,96558.3413.80$27,109
Sep 200502,05361.4512.08$24,798
Aug 200502,09561.519.80$20,524
Jul 200502,29755.697.84$18,017
Jun 200502,36052.337.38$17,419
May 200502,56545.226.65$17,060
Apr 200502,79849.207.36$20,595
Mar 200502,84950.377.15$20,384

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                  250 Mcf  × $  3.05 =       $761

────────────────────────────────────────────────────
Month total                                     $761

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/211995 is the state's own key, not one this site invented.