DUKE WILSON 173

Operated by UPP OPERATING, LLC (P-5 875310) in the SAWYER (CANYON) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 239535District 7CField 812673332 tax incentive programmesCondensateGasSaveExport
Value, all time
$698 k
Jul 2007 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
227
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112008-10-20182596
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition7 bbl$309
GasProduction137,730 Mcf$698,016
Total$698,326

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.4355, -100.7585. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.43546, -100.75851 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
9,004 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 9,004 ft.

Completions filed
Jul 2007
1 of 1 wells

1 well

42-43538504139,004 ftJul 2007

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (227)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

227 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220394.529.13$27
Jul 202202101.587.54$15
Jun 202203115.097.98$24
May 202209109.378.43$76
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 202201091.054.86$49
Jan 202201381.844.54$59
Dec 202101471.323.90$55
Nov 202101177.435.24$58
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210770.783.98$28
Jun 20210969.493.38$30
May 20210863.483.02$24
Apr 20210760.362.76$19
Mar 202101061.302.72$27
Feb 202101157.805.55$61
Jan 20210650.412.81$17
Dec 20200744.642.68$19
Nov 20200938.772.71$24
Oct 202001336.972.48$32
Sep 202002237.091.99$44
Aug 202001839.982.39$43
Jul 202002338.371.83$42
Jun 202002234.901.69$37
May 202002916.921.81$53
Apr 202003214.751.80$58
Mar 202003630.341.86$67
Feb 202003249.881.98$63
Jan 202004257.252.09$88
Dec 201905259.012.30$120
Nov 201906455.302.75$176
Oct 201907653.472.42$184
Sep 2019010255.052.66$271
Aug 2019012153.112.30$279
Jul 2019013556.272.46$332
Jun 2019013052.782.49$324
May 2019014958.482.74$408
Apr 2019015262.632.75$418
Mar 2019017056.803.06$521
Feb 2019017450.852.79$486
Jan 2019020146.033.23$649
Dec 2018022146.594.19$925
Nov 2018023552.934.24$996
Oct 2018022661.443.40$768
Sep 2018023359.543.11$724
Aug 2018025759.403.07$788
Jul 2018027865.142.93$815
Jun 2018029060.183.08$892
May 2018032565.382.90$943
Apr 2018033563.842.90$972
Mar 2018037461.222.79$1,042
Feb 2018035761.782.77$988
Jan 2018044762.874.01$1,792
Dec 2017028257.272.92$824
Nov 2017039255.423.12$1,222
Oct 20171649.292.98$67
Sep 2017032647.523.09$1,006
Aug 2017149745.373.00$1,539
Jul 2017049243.873.09$1,519
Jun 2017155542.493.09$1,756
May 2017049145.373.26$1,602
Apr 2017042247.933.21$1,355
Mar 2017162646.772.98$1,915
Feb 2017012550.452.95$369
Jan 201713349.413.42$162
Dec 2016028248.763.72$1,050
Nov 2016036542.492.64$965
Oct 2016046046.193.09$1,422
Sep 2016073341.553.10$2,273
Aug 2016059041.442.92$1,725
Jul 2016012741.622.92$371
Jun 2016033245.352.69$892
May 2016030842.521.99$613
Apr 201602936.561.99$58
Mar 2016132833.011.79$621
Feb 2016040526.472.06$836
Jan 2016055327.352.36$1,307
Dec 2015051932.362.00$1,039
Nov 2015053038.792.17$1,149
Oct 2015052243.552.43$1,267
Sep 2015153342.992.76$1,513
Aug 2015059740.162.87$1,715
Jul 2015058648.152.95$1,726
Jun 2015060856.152.88$1,753
May 2015065155.212.96$1,924
Apr 2015082349.822.71$2,228
Mar 2015024442.892.93$716
Feb 2015043044.662.98$1,280
Jan 2015058943.433.10$1,826
Dec 2014055354.693.59$1,986
Nov 2014059370.464.25$2,521
Oct 2014059778.303.90$2,329
Sep 2014058986.164.05$2,383
Aug 2014065789.394.04$2,651
Jul 2014064796.564.18$2,704
Jun 2014062998.164.74$2,980
May 2014067194.734.73$3,172
Apr 2014070795.944.81$3,400
Mar 2014073495.895.06$3,712
Feb 2014061197.406.19$3,783
Jan 2014075790.404.86$3,680
Dec 2013075091.824.35$3,266
Nov 2013069888.853.74$2,609
Oct 2013081597.423.78$3,080
Sep 20130653104.113.72$2,428
Aug 20130777104.253.52$2,737
Jul 20130811102.523.72$3,015
Jun 2013078894.403.93$3,100
May 2013082294.834.15$3,411
Apr 2013083793.964.28$3,585
Mar 2013084293.623.91$3,295
Feb 2013077291.233.42$2,640
Jan 2013086291.603.42$2,948
Dec 2012088186.773.42$3,013
Nov 2012085486.953.62$3,096
Oct 2012089789.383.40$3,050
Sep 2012086194.672.92$2,513
Aug 2012088992.662.91$2,585
Jul 2012091085.133.02$2,749
Jun 2012089679.822.52$2,257
May 2012094891.612.49$2,359
Apr 20120894101.652.00$1,785
Mar 20120961105.052.22$2,135
Feb 20120904101.102.57$2,324
Jan 2012098098.092.73$2,679
Dec 2011097896.873.24$3,168
Nov 2011097295.723.31$3,219
Oct 201101,02584.983.65$3,740
Sep 201101,01883.623.99$4,058
Aug 201101,06583.404.15$4,419
Jul 201101,09594.144.52$4,946
Jun 201101,04692.904.64$4,853
May 201101,09898.134.40$4,836
Apr 201101,076105.964.33$4,663
Mar 201101,11596.364.06$4,524
Feb 201101,05685.644.18$4,414
Jan 201101,12186.504.59$5,144
Dec 201001,14685.734.35$4,983
Nov 201001,14180.843.80$4,330
Oct 201001,20778.103.51$4,235
Sep 201001,20472.633.98$4,791
Aug 201001,30273.684.42$5,754
Jul 201001,39572.554.74$6,607
Jun 201001,18170.364.91$5,799
May 201001,05171.124.24$4,451
Apr 201001,30481.694.12$5,376
Mar 201001,36878.394.39$6,004
Feb 201001,24473.585.44$6,770
Jan 201001,39774.365.96$8,332
Dec 200901,43471.445.48$7,864
Nov 200901,44174.593.75$5,406
Oct 200901,51572.544.11$6,227
Sep 200901,45365.543.06$4,453
Aug 200901,53567.423.22$4,940
Jul 200901,56661.133.46$5,425
Jun 200901,54866.163.90$6,029
May 200901,58954.743.93$6,238
Apr 200901,60446.773.59$5,754
Mar 200901,69842.144.06$6,892
Feb 200901,61932.814.63$7,501
Jan 200901,83735.865.37$9,867
Dec 200801,86737.105.98$11,159
Nov 200801,88355.496.86$12,918
Oct 200801,83975.246.92$12,730
Sep 200801,999101.767.88$15,746
Aug 200802,075114.228.48$17,602
Jul 200801,973131.0811.39$22,471
Jun 200802,201131.3313.03$28,685
May 200802,093123.1711.57$24,225
Apr 200801,818110.3110.45$19,007
Mar 200801,272101.909.66$12,293
Feb 200801,59392.538.77$13,972
Jan 200802,25490.388.21$18,496
Dec 200702,50188.337.30$18,262
Nov 200702,87591.677.29$20,964
Oct 200703,36882.856.92$23,313
Sep 200703,85675.846.24$24,077
Aug 200705,12669.066.39$32,745
Jul 200701,74370.906.39$11,134

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Aug 2022 — as filed, then multipliedworked
Condensate             0 bbl  × $ 94.52 =         $0
Gas                    3 Mcf  × $  9.13 =        $27

────────────────────────────────────────────────────
Month total                                      $27

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/239535 is the state's own key, not one this site invented.