BAILEY

Operated by ZARVONA ENERGY LLC (P-5 950523) in the OZONA, NE. (CANYON 7520) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 221931District 7CField 679985002 tax incentive programmesCondensateGasSaveExport
Value, all time
$690 k
Jul 2006 – May 2026
Value, last 12 filed months
$64
at the published price for each month
Months reported
239
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 592 leases and 641 wells, and the rule below applies to all of them.

Discovered
1966-01-17
as the register files it
Field class
Oil and gas
the register's own label
Between wells
660 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2013-10-22.

The Commission's schedule remark for this field reads: PER DOCKET 01-0299858, THIS FIELD HAS BEEN DESIGNATED AS A UFT

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112006-11-30170865
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition935 bbl$67,215
GasProduction108,634 Mcf$622,658
Total$689,874

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.8127, -100.9901. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.81272, -100.99011 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
7,909 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,909 ft.

Completions filed
Jul 2006
1 of 1 wells

1 well

42-105400061507,909 ftJul 2006

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (239)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

239 months

May 202601106.413.05$3
Apr 20260498.932.87$11
Mar 20260089.753.15$0
Feb 20260163.503.75$4
Jan 20260259.138.00$16
Dec 20250056.664.41$0
Nov 20250558.593.93$20
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250163.933.01$3
Jul 20250266.743.32$7
Jun 20250066.483.13$0
May 20250260.553.23$6
Apr 20250062.363.54$0
Mar 20250767.704.27$30
Feb 20250270.884.34$9
Jan 20250274.324.28$9
Dec 20240268.993.12$6
Nov 20240169.052.20$2
Oct 20240271.372.28$5
Sep 20240069.612.36$0
Aug 20247575.632.06$540
Jul 20240479.932.15$9
Jun 20240178.082.63$3
May 20240678.812.20$13
Apr 20240384.451.66$5
Mar 20240680.301.55$9
Feb 20240776.091.78$12
Jan 20240273.023.30$7
Dec 20230471.262.61$10
Nov 20230377.892.81$8
Oct 20230285.443.09$6
Sep 20230389.042.74$8
Aug 20230180.522.67$3
Jul 20230374.852.64$8
Jun 20230268.962.26$5
May 20230570.622.23$11
Apr 20230278.122.24$4
Mar 20230472.852.39$10
Feb 20230475.112.47$10
Jan 20230476.533.39$14
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202209101.587.54$68
Jun 202200115.097.98$0
May 202207109.378.43$59
Apr 202206104.226.84$41
Mar 202203108.885.08$15
Feb 202201491.054.86$68
Jan 20220481.844.54$18
Dec 202101471.323.90$55
Nov 202102077.435.24$105
Oct 20210579.795.71$29
Sep 202101169.865.35$59
Aug 202101266.024.22$51
Jul 20210570.783.98$20
Jun 202101369.493.38$44
May 202101963.483.02$57
Apr 20210560.362.76$14
Mar 2021262161.302.72$1,651
Feb 202102457.805.55$133
Jan 202103650.412.81$101
Dec 20200344.642.68$8
Nov 202003138.772.71$84
Oct 202004336.972.48$107
Sep 202003737.091.99$74
Aug 202002439.982.39$57
Jul 20200638.371.83$11
Jun 202002034.901.69$34
May 20200916.921.81$16
Apr 20200614.751.80$11
Mar 202001430.341.86$26
Feb 20200749.881.98$14
Jan 202001857.252.09$38
Dec 201901159.012.30$25
Nov 201901955.302.75$52
Oct 20190653.472.42$15
Sep 201904155.052.66$109
Aug 201904553.112.30$104
Jul 201904756.272.46$116
Jun 201904852.782.49$120
May 201904958.482.74$134
Apr 201905462.632.75$149
Mar 201905956.803.06$181
Feb 201904550.852.79$126
Jan 201904446.033.23$142
Dec 201805546.594.19$230
Nov 201805252.934.24$220
Oct 201806061.443.40$204
Sep 201805359.543.11$165
Aug 201805259.403.07$159
Jul 201803765.142.93$108
Jun 201805260.183.08$160
May 201806565.382.90$189
Apr 201806863.842.90$197
Mar 201807761.222.79$215
Feb 201807561.782.77$207
Jan 201808162.874.01$325
Dec 201709557.272.92$278
Nov 2017010455.423.12$324
Oct 2017011949.292.98$355
Sep 2017013547.523.09$417
Aug 2017014745.373.00$442
Jul 2017019143.873.09$590
Jun 2017021242.493.09$655
May 2017019245.373.26$627
Apr 2017022647.933.21$726
Mar 2017025546.772.98$761
Feb 2017024050.452.95$709
Jan 2017025549.413.42$872
Dec 2016026748.763.72$994
Nov 2016025242.492.64$666
Oct 2016026146.193.09$807
Sep 2016019341.553.10$598
Aug 2016019441.442.92$567
Jul 2016021541.622.92$629
Jun 2016030645.352.69$822
May 2016032442.521.99$645
Apr 2016026336.561.99$524
Mar 2016029133.011.79$522
Feb 2016033626.472.06$693
Jan 2016036627.352.36$865
Dec 20154038632.362.00$2,067
Nov 2015038538.792.17$834
Oct 2015039543.552.43$959
Sep 2015037342.992.76$1,029
Aug 2015036140.162.87$1,037
Jul 2015040248.152.95$1,184
Jun 2015040456.152.88$1,165
May 2015029355.212.96$866
Apr 2015029949.822.71$809
Mar 2015032042.892.93$939
Feb 2015032044.662.98$952
Jan 2015038243.433.10$1,184
Dec 2014041654.693.59$1,494
Nov 2014040970.464.25$1,739
Oct 20144036878.303.90$4,568
Sep 2014035086.164.05$1,416
Aug 2014134089.394.04$1,461
Jul 2014033796.564.18$1,409
Jun 2014035198.164.74$1,663
May 2014023394.734.73$1,101
Apr 2014043995.944.81$2,111
Mar 2014028695.895.06$1,446
Feb 2014031897.406.19$1,969
Jan 2014052590.404.86$2,552
Dec 2013037491.824.35$1,629
Nov 2013040588.853.74$1,514
Oct 201306497.423.78$242
Sep 20130129104.113.72$480
Aug 20130194104.253.52$683
Jul 20130166102.523.72$617
Jun 2013019394.403.93$759
May 20136228494.834.15$7,058
Apr 2013037693.964.28$1,610
Mar 2013026493.623.91$1,033
Feb 2013034591.233.42$1,180
Jan 2013036191.603.42$1,235
Dec 2012022686.773.42$773
Nov 2012022486.953.62$812
Oct 2012027789.383.40$942
Sep 2012030594.672.92$890
Aug 2012033192.662.91$963
Jul 2012037285.133.02$1,124
Jun 2012048179.822.52$1,212
May 2012049791.612.49$1,237
Apr 20120523101.652.00$1,044
Mar 20120574105.052.22$1,275
Feb 20120403101.102.57$1,036
Jan 2012055698.092.73$1,520
Dec 2011055196.873.24$1,785
Nov 2011055695.723.31$1,841
Oct 2011057384.983.65$2,091
Sep 2011056183.623.99$2,236
Aug 2011052083.404.15$2,158
Jul 2011063394.144.52$2,859
Jun 2011058692.904.64$2,719
May 2011056598.134.40$2,489
Apr 20110474105.964.33$2,054
Mar 2011063696.364.06$2,580
Feb 2011055385.644.18$2,312
Jan 2011063286.504.59$2,900
Dec 2010064885.734.35$2,817
Nov 2010058780.843.80$2,228
Oct 20104267278.103.51$5,638
Sep 2010064472.633.98$2,563
Aug 2010061173.684.42$2,700
Jul 2010058372.554.74$2,761
Jun 2010075370.364.91$3,698
May 2010054071.124.24$2,287
Apr 2010065481.694.12$2,696
Mar 2010072578.394.39$3,182
Feb 2010066573.585.44$3,619
Jan 2010073674.365.96$4,390
Dec 20092274571.445.48$5,657
Nov 2009070974.593.75$2,660
Oct 2009078472.544.11$3,222
Sep 2009071365.543.06$2,185
Aug 20098380967.423.22$8,200
Jul 2009075561.133.46$2,616
Jun 2009078266.163.90$3,046
May 2009078154.743.93$3,066
Apr 2009080846.773.59$2,899
Mar 2009090842.144.06$3,686
Feb 2009079532.814.63$3,683
Jan 2009086235.865.37$4,630
Dec 200801,00237.105.98$5,989
Nov 200801,11555.496.86$7,649
Oct 200801,24475.246.92$8,611
Sep 2008101328101.767.88$12,861
Aug 20080838114.228.48$7,109
Jul 200801,047131.0811.39$11,925
Jun 200801,062131.3313.03$13,841
May 200801,146123.1711.57$13,264
Apr 20080986110.3110.45$10,308
Mar 200801,162101.909.66$11,230
Feb 200801,12592.538.77$9,867
Jan 200801,21790.388.21$9,986
Dec 20071761,30488.337.30$25,068
Nov 200701,25491.677.29$9,144
Oct 200701,42082.856.92$9,829
Sep 200701,49975.846.24$9,360
Aug 200701,54969.066.39$9,895
Jul 200701,65470.906.39$10,566
Jun 200701,67662.007.55$12,651
May 200701,92958.747.85$15,135
Apr 200701,90759.617.81$14,885
Mar 200702,17756.927.30$15,896
Feb 20071692,21555.108.22$27,510
Jan 200702,56350.306.73$17,241
Dec 200602,83956.656.92$19,641
Nov 200603,15154.207.62$24,003
Oct 20061663,90354.906.01$32,585
Sep 200605,55860.085.04$27,997
Aug 200609,06668.717.34$66,544
Jul 200602,78869.376.34$17,684

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                    1 Mcf  × $  3.05 =         $3

────────────────────────────────────────────────────
Month total                                       $3

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/221931 is the state's own key, not one this site invented.