WHITEHEAD 1

Operated by UPP OPERATING, LLC (P-5 875310) in the SAWYER (CANYON) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 223153District 7CField 812673332 tax incentive programmesCondensateGasSaveExport
Value, all time
$1.4 M
Jul 2006 – May 2026
Value, last 12 filed months
$15 k
at the published price for each month
Months reported
239
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112007-03-22172292
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition54 bbl$5,086
GasProduction283,153 Mcf$1,433,386
Total$1,438,472

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.5177, -100.8901. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.51772, -100.89011 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
8,627 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 8,627 ft.

Completions filed
Jul 2006
1 of 1 wells

1 well

42-4353706458,627 ftJul 2006

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (239)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

239 months

May 20260462106.413.05$1,407
Apr 2026059898.932.87$1,716
Mar 2026038789.753.15$1,219
Feb 202609263.503.75$345
Jan 202609959.138.00$792
Dec 2025013456.664.41$591
Nov 2025029658.593.93$1,162
Oct 2025033859.383.30$1,117
Sep 2025043262.743.08$1,329
Aug 2025054363.933.01$1,637
Jul 2025055166.743.32$1,827
Jun 2025051166.483.13$1,599
May 2025050560.553.23$1,632
Apr 2025052762.363.54$1,867
Mar 2025055967.704.27$2,386
Feb 2025054070.884.34$2,344
Jan 2025058174.324.28$2,486
Dec 2024057368.993.12$1,789
Nov 2024057369.052.20$1,260
Oct 2024057071.372.28$1,300
Sep 2024056169.612.36$1,326
Aug 2024058175.632.06$1,199
Jul 2024059179.932.15$1,269
Jun 2024053878.082.63$1,417
May 2024056878.812.20$1,249
Apr 2024059184.451.66$981
Mar 2024062880.301.55$970
Feb 2024058476.091.78$1,042
Jan 2024062173.023.30$2,048
Dec 2023064871.262.61$1,692
Nov 2023063577.892.81$1,783
Oct 2023068585.443.09$2,115
Sep 2023063989.042.74$1,748
Aug 2023077980.522.67$2,082
Jul 2023048374.852.64$1,276
Jun 2023019568.962.26$440
May 2023045170.622.23$1,005
Apr 2023048578.122.24$1,085
Mar 2023049372.852.39$1,180
Feb 2023047575.112.47$1,171
Jan 2023067676.533.39$2,290
Dec 2022056876.415.73$3,254
Nov 2022061285.005.65$3,455
Oct 2022067087.185.86$3,929
Sep 2022070884.888.16$5,780
Aug 2022076694.529.13$6,991
Jul 20220748101.587.54$5,641
Jun 20220489115.097.98$3,901
May 20220519109.378.43$4,377
Apr 20220507104.226.84$3,467
Mar 20220639108.885.08$3,244
Feb 2022048291.054.86$2,342
Jan 2022047481.844.54$2,151
Dec 2021058071.323.90$2,261
Nov 2021063777.435.24$3,336
Oct 2021056179.795.71$3,205
Sep 2021061469.865.35$3,285
Aug 2021062866.024.22$2,651
Jul 2021063570.783.98$2,529
Jun 2021088169.493.38$2,978
May 2021059763.483.02$1,802
Apr 2021060960.362.76$1,680
Mar 2021058661.302.72$1,592
Feb 2021051457.805.55$2,852
Jan 2021047650.412.81$1,338
Dec 2020062344.642.68$1,667
Nov 2020053938.772.71$1,459
Oct 2020047536.972.48$1,177
Sep 2020045437.091.99$904
Aug 2020046839.982.39$1,116
Jul 2020046938.371.83$856
Jun 2020046134.901.69$779
May 2020049216.921.81$893
Apr 2020048814.751.80$881
Mar 2020052230.341.86$969
Feb 2020058549.881.98$1,159
Jan 2020067557.252.09$1,414
Dec 2019074659.012.30$1,719
Nov 2019069555.302.75$1,912
Oct 2019076553.472.42$1,850
Sep 2019074855.052.66$1,988
Aug 2019072153.112.30$1,661
Jul 2019072256.272.46$1,776
Jun 2019069552.782.49$1,731
May 2019071258.482.74$1,951
Apr 2019068462.632.75$1,881
Mar 2019071156.803.06$2,177
Feb 2019064450.852.79$1,798
Jan 2019072646.033.23$2,344
Dec 2018073846.594.19$3,089
Nov 2018074552.934.24$3,157
Oct 2018078561.443.40$2,667
Sep 2018070659.543.11$2,194
Aug 2018075059.403.07$2,300
Jul 2018074165.142.93$2,173
Jun 2018072260.183.08$2,222
May 2018079065.382.90$2,292
Apr 2018080263.842.90$2,326
Mar 2018085761.222.79$2,388
Feb 2018077261.782.77$2,135
Jan 2018063462.874.01$2,542
Dec 2017071457.272.92$2,086
Nov 2017083555.423.12$2,604
Oct 2017076849.292.98$2,291
Sep 2017076647.523.09$2,365
Aug 2017077445.373.00$2,325
Jul 2017081543.873.09$2,516
Jun 2017078342.493.09$2,417
May 2017085145.373.26$2,777
Apr 2017081547.933.21$2,617
Mar 2017086146.772.98$2,569
Feb 2017085350.452.95$2,519
Jan 2017065349.413.42$2,232
Dec 2016076548.763.72$2,848
Nov 2016077042.492.64$2,036
Oct 2016089146.193.09$2,753
Sep 2016056141.553.10$1,739
Aug 2016091241.442.92$2,667
Jul 2016079841.622.92$2,334
Jun 2016082145.352.69$2,205
May 2016073642.521.99$1,465
Apr 2016085236.561.99$1,696
Mar 2016090733.011.79$1,627
Feb 2016091226.472.06$1,882
Jan 2016098227.352.36$2,322
Dec 2015096032.362.00$1,921
Nov 2015067838.792.17$1,469
Oct 2015081243.552.43$1,970
Sep 2015084142.992.76$2,320
Aug 2015090440.162.87$2,597
Jul 2015081048.152.95$2,386
Jun 2015072956.152.88$2,102
May 2015090955.212.96$2,687
Apr 2015084749.822.71$2,292
Mar 2015089142.892.93$2,615
Feb 2015082544.662.98$2,455
Jan 201501,07643.433.10$3,336
Dec 201401,03254.693.59$3,706
Nov 201401,00170.464.25$4,256
Oct 201401,02578.303.90$3,998
Sep 201401,01186.164.05$4,090
Aug 201401,05989.394.04$4,273
Jul 201401,01496.564.18$4,238
Jun 201401,02298.164.74$4,841
May 201401,08994.734.73$5,147
Apr 201401,09095.944.81$5,242
Mar 2014088695.895.06$4,480
Feb 2014073097.406.19$4,520
Jan 2014085490.404.86$4,151
Dec 2013099691.824.35$4,337
Nov 2013098388.853.74$3,675
Oct 201301,02597.423.78$3,874
Sep 20130995104.113.72$3,699
Aug 201301,042104.253.52$3,671
Jul 201301,063102.523.72$3,952
Jun 2013097194.403.93$3,819
May 2013084094.834.15$3,485
Apr 201301,23593.964.28$5,289
Mar 201301,53693.623.91$6,010
Feb 201301,00391.233.42$3,430
Jan 201301,16391.603.42$3,977
Dec 2012069886.773.42$2,387
Nov 2012070586.953.62$2,556
Oct 2012074189.383.40$2,519
Sep 2012074394.672.92$2,168
Aug 2012083192.662.91$2,417
Jul 2012091585.133.02$2,764
Jun 201201,18179.822.52$2,975
May 201201,36991.612.49$3,407
Apr 201201,415101.652.00$2,825
Mar 201201,613105.052.22$3,584
Feb 201201,435101.102.57$3,688
Jan 201202,11098.092.73$5,769
Dec 201101,86596.873.24$6,042
Nov 201111,49095.723.31$5,030
Oct 201101,57084.983.65$5,728
Sep 201101,57683.623.99$6,282
Aug 201121,71083.404.15$7,262
Jul 201111,80594.144.52$8,248
Jun 201101,53092.904.64$7,099
May 201101,30498.134.40$5,744
Apr 201101,290105.964.33$5,590
Mar 201101,38896.364.06$5,632
Feb 201101,12185.644.18$4,686
Jan 201101,17486.504.59$5,387
Dec 201001,14485.734.35$4,974
Nov 201001,13980.843.80$4,323
Oct 201001,20378.103.51$4,221
Sep 201001,21372.633.98$4,827
Aug 201001,28073.684.42$5,657
Jul 201001,34872.554.74$6,385
Jun 201001,34770.364.91$6,614
May 2010071071.124.24$3,007
Apr 201001,09681.694.12$4,518
Mar 201001,15378.394.39$5,060
Feb 201001,06073.585.44$5,769
Jan 201001,19774.365.96$7,139
Dec 200901,24271.445.48$6,811
Nov 200901,23874.593.75$4,644
Oct 200901,29772.544.11$5,331
Sep 200901,32065.543.06$4,045
Aug 200901,45067.423.22$4,667
Jul 200901,41061.133.46$4,885
Jun 200901,39166.163.90$5,418
May 200901,49854.743.93$5,881
Apr 200901,43846.773.59$5,159
Mar 200901,54642.144.06$6,275
Feb 200901,58432.814.63$7,339
Jan 200902,09535.865.37$11,252
Dec 200802,18837.105.98$13,078
Nov 200802,12255.496.86$14,558
Oct 200802,22875.246.92$15,422
Sep 200802,168101.767.88$17,078
Aug 200802,299114.228.48$19,502
Jul 200802,388131.0811.39$27,198
Jun 200802,373131.3313.03$30,926
May 2008142,498123.1711.57$30,637
Apr 2008162,514110.3110.45$28,048
Mar 200802,669101.909.66$25,793
Feb 200802,59692.538.77$22,768
Jan 200802,85390.388.21$23,411
Dec 200702,96788.337.30$21,665
Nov 200702,94991.677.29$21,503
Oct 200703,16782.856.92$21,922
Sep 200703,09575.846.24$19,326
Aug 200703,44769.066.39$22,019
Jul 200703,57670.906.39$22,843
Jun 2007203,66662.007.55$28,913
May 200703,68558.747.85$28,914
Apr 200704,01059.617.81$31,299
Mar 200704,22356.927.30$30,836
Feb 200704,06255.108.22$33,373
Jan 200704,79250.306.73$32,235
Dec 200605,19856.656.92$35,962
Nov 200605,85154.207.62$44,570
Oct 200606,49554.906.01$39,060
Sep 200606,77560.085.04$34,127
Aug 200607,14168.717.34$52,414
Jul 200602,69869.376.34$17,113

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                  462 Mcf  × $  3.05 =     $1,407

────────────────────────────────────────────────────
Month total                                   $1,407

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/223153 is the state's own key, not one this site invented.