HUTCHINGS

Operated by SCOUT ENERGY MANAGEMENT LLC (P-5 760218) in the OZONA (CANYON SAND) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 99257District 7CField 67995200NGPA filingCondensateGasSaveExport
Value, all time
$256 k
Jan 1993 – May 2026
Value, last 12 filed months
$8 k
at the published price for each month
Months reported
401
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 2,312 leases and 2,323 wells, and the rule below applies to all of them.

Discovered
1962-02-23
as the register files it
Field class
Oil and gas
the register's own label
Between wells
600 ft
minimum
From a lease line
660 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2006-09-12.

The Commission's schedule remark for this field reads: ZONE TO BE SET UP IN OZONA (CANYON SAND, OIL).

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition24 bbl$1,669
GasProduction78,138 Mcf$254,588
Total$256,256

18,535 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.4820, -101.4820. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.48199, -101.48200 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
7,272 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,272 ft.

Completions filed
Mar 1982
1 of 1 wells

1 well

42-1053390120357,272 ftMar 1982

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (401)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

401 months

May 2026086106.413.05$262
Apr 2026116198.932.87$561
Mar 202632489.753.15$345
Feb 202605463.503.75$203
Jan 202615959.138.00$531
Dec 202515956.664.41$317
Nov 202515858.593.93$286
Oct 2025346459.383.30$1,712
Sep 2025262062.743.08$2,033
Aug 2025120563.933.01$682
Jul 202507266.743.32$239
Jun 2025114166.483.13$508
May 2025114160.553.23$516
Apr 2025113562.363.54$541
Mar 2025213067.704.27$690
Feb 2025213770.884.34$736
Jan 20250074.324.28$0
Dec 2024014868.993.12$462
Nov 2024011769.052.20$257
Oct 202408371.372.28$189
Sep 202407169.612.36$168
Aug 202405975.632.06$122
Jul 202406579.932.15$140
Jun 202407578.082.63$198
May 2024012578.812.20$275
Apr 2024013284.451.66$219
Mar 2024012880.301.55$198
Feb 2024011276.091.78$200
Jan 2024411773.023.30$678
Dec 2023012071.262.61$313
Nov 2023012777.892.81$357
Oct 2023010785.443.09$330
Sep 202309089.042.74$246
Aug 202308680.522.67$230
Jul 202309474.852.64$248
Jun 2023010468.962.26$235
May 2023011870.622.23$263
Apr 2023010478.122.24$233
Mar 2023011872.852.39$282
Feb 2023010675.112.47$261
Jan 2023011576.533.39$390
Dec 2022011676.415.73$665
Nov 2022011385.005.65$638
Oct 2022011387.185.86$663
Sep 2022014384.888.16$1,167
Aug 202204994.529.13$447
Jul 2022099101.587.54$747
Jun 20220105115.097.98$838
May 20220123109.378.43$1,037
Apr 20220125104.226.84$855
Mar 20220137108.885.08$695
Feb 2022010791.054.86$520
Jan 2022011681.844.54$526
Dec 2021012171.323.90$472
Nov 2021011877.435.24$618
Oct 2021011979.795.71$680
Sep 2021011669.865.35$621
Aug 2021011666.024.22$490
Jul 2021011370.783.98$450
Jun 2021011669.493.38$392
May 2021012063.483.02$362
Apr 2021012860.362.76$353
Mar 2021010761.302.72$291
Feb 202105857.805.55$322
Jan 2021010150.412.81$284
Dec 202009744.642.68$260
Nov 2020010438.772.71$281
Oct 2020011036.972.48$273
Sep 202009437.091.99$187
Aug 2020010439.982.39$248
Jul 2020010538.371.83$192
Jun 2020010534.901.69$177
May 2020011116.921.81$201
Apr 2020012314.751.80$222
Mar 2020012830.341.86$238
Feb 2020011749.881.98$232
Jan 2020013857.252.09$289
Dec 2019013159.012.30$302
Nov 2019013155.302.75$360
Oct 2019014153.472.42$341
Sep 2019013355.052.66$353
Aug 2019013153.112.30$302
Jul 2019014656.272.46$359
Jun 2019013752.782.49$341
May 2019013558.482.74$370
Apr 2019013462.632.75$369
Mar 2019014256.803.06$435
Feb 2019011850.852.79$329
Jan 2019013346.033.23$429
Dec 2018013446.594.19$561
Nov 2018012852.934.24$542
Oct 2018013761.443.40$466
Sep 2018015059.543.11$466
Aug 2018010259.403.07$313
Jul 2018012665.142.93$369
Jun 2018012460.183.08$382
May 2018012865.382.90$371
Apr 2018012563.842.90$363
Mar 2018012661.222.79$351
Feb 2018010361.782.77$285
Jan 2018010462.874.01$417
Dec 2017014157.272.92$412
Nov 2017012655.423.12$393
Oct 2017012649.292.98$376
Sep 2017012647.523.09$389
Aug 2017012645.373.00$379
Jul 2017012443.873.09$383
Jun 2017011742.493.09$361
May 2017012645.373.26$411
Apr 2017012347.933.21$395
Mar 2017013046.772.98$388
Feb 2017011550.452.95$340
Jan 2017013249.413.42$451
Dec 2016014548.763.72$540
Nov 2016014642.492.64$386
Oct 2016014446.193.09$445
Sep 2016015341.553.10$474
Aug 2016014441.442.92$421
Jul 2016013541.622.92$395
Jun 2016012845.352.69$344
May 2016013442.521.99$267
Apr 2016013536.561.99$269
Mar 2016013933.011.79$249
Feb 2016011926.472.06$246
Jan 2016012927.352.36$305
Dec 2015013632.362.00$272
Nov 2015013038.792.17$282
Oct 2015013643.552.43$330
Sep 2015012842.992.76$353
Aug 2015013240.162.87$379
Jul 2015014548.152.95$427
Jun 2015012556.152.88$360
May 2015015555.212.96$458
Apr 2015015349.822.71$414
Mar 2015015142.892.93$443
Feb 2015013444.662.98$399
Jan 2015016343.433.10$505
Dec 2014014554.693.59$521
Nov 2014014470.464.25$612
Oct 2014015478.303.90$601
Sep 2014016386.164.05$659
Aug 2014019289.394.04$775
Jul 2014011896.564.18$493
Jun 201409498.164.74$445
May 2014010094.734.73$473
Apr 201409895.944.81$471
Mar 2014010295.895.06$516
Feb 2014010697.406.19$656
Jan 2014015490.404.86$749
Dec 2013017091.824.35$740
Nov 2013012888.853.74$479
Oct 2013012197.423.78$457
Sep 20130117104.113.72$435
Aug 20130120104.253.52$423
Jul 20130124102.523.72$461
Jun 2013012494.403.93$488
May 2013013094.834.15$539
Apr 2013013893.964.28$591
Mar 2013014893.623.91$579
Feb 2013014891.233.42$506
Jan 2013017591.603.42$598
Dec 2012017586.773.42$599
Nov 2012014586.953.62$526
Oct 2012015789.383.40$534
Sep 2012016794.672.92$487
Aug 2012017192.662.91$497
Jul 2012014285.133.02$429
Jun 2012016279.822.52$408
May 2012017691.612.49$438
Apr 20120196101.652.00$391
Mar 20120189105.052.22$420
Feb 20120169101.102.57$434
Jan 2012015898.092.73$432
Dec 2011014296.873.24$460
Nov 2011016095.723.31$530
Oct 2011014284.983.65$518
Sep 2011011383.623.99$450
Aug 2011010983.404.15$452
Jul 2011012094.144.52$542
Jun 2011014392.904.64$664
May 2011017998.134.40$788
Apr 20110119105.964.33$516
Mar 2011015196.364.06$613
Feb 2011011385.644.18$472
Jan 2011016086.504.59$734
Dec 2010016585.734.35$717
Nov 2010014480.843.80$547
Oct 2010017678.103.51$618
Sep 2010011372.633.98$450
Aug 2010015773.684.42$694
Jul 2010011372.554.74$535
Jun 2010015270.364.91$746
May 2010013771.124.24$580
Apr 2010017681.694.12$726
Mar 2010016178.394.39$707
Feb 2010015373.585.44$833
Jan 2010017074.365.96$1,014
Dec 2009017071.445.48$932
Nov 2009017874.593.75$668
Oct 2009015272.544.11$625
Sep 2009016565.543.06$506
Aug 2009015367.423.22$492
Jul 2009016161.133.46$558
Jun 2009016066.163.90$623
May 2009017254.743.93$675
Apr 2009015646.773.59$560
Mar 2009016842.144.06$682
Feb 2009014932.814.63$690
Jan 2009016535.865.37$886
Dec 2008017137.105.98$1,022
Nov 2008016855.496.86$1,153
Oct 2008018875.246.92$1,301
Sep 20080106101.767.88$835
Aug 20080156114.228.48$1,323
Jul 20080160131.0811.39$1,822
Jun 20080145131.3313.03$1,890
May 20080150123.1711.57$1,736
Apr 20080158110.3110.45$1,652
Mar 20080167101.909.66$1,614
Feb 2008013892.538.77$1,210
Jan 2008016790.388.21$1,370
Dec 2007020388.337.30$1,482
Nov 2007014191.677.29$1,028
Oct 2007012882.856.92$886
Sep 2007012875.846.24$799
Aug 2007010369.066.39$658
Jul 2007016170.906.39$1,028
Jun 2007013162.007.55$989
May 2007019058.747.85$1,491
Apr 2007030659.617.81$2,388
Mar 2007031056.927.30$2,264
Feb 2007033555.108.22$2,752
Jan 2007016250.306.73$1,090
Dec 2006010956.656.92$754
Nov 200609254.207.62$701
Oct 2006021754.906.01$1,305
Sep 2006016560.085.04$831
Aug 2006018168.717.34$1,329
Jul 2006021469.376.34$1,357
Jun 2006026666.286.38$1,698
May 2006022466.016.42$1,439
Apr 2006024764.397.36$1,818
Mar 2006019956.707.08$1,410
Feb 2006016657.597.75$1,287
Jan 2006025660.598.93$2,287
Dec 2005020154.9413.42$2,697
Nov 2005019654.6910.59$2,075
Oct 2005019758.3413.80$2,718
Sep 2005011261.4512.08$1,353
Aug 200505561.519.80$539
Jul 2005023055.697.84$1,804
Jun 2005025352.337.38$1,867
May 2005022345.226.65$1,483
Apr 2005022849.207.36$1,678
Mar 2005017650.377.15$1,259
Feb 2005016845.226.31$1,060
Jan 2005018743.166.32$1,182
Dec 2004017839.866.75$1,202
Nov 2004020945.286.33$1,323
Oct 2004015649.706.52$1,016
Sep 200409743.245.28$513
Aug 2004013942.375.55$772
Jul 2004034538.286.08$2,099
Jun 2004034436.106.43$2,213
May 2004035637.486.49$2,312
Apr 2004035334.475.86$2,068
Mar 2004035034.365.53$1,936
Feb 2004032032.455.51$1,763
Jan 2004034032.036.30$2,142
Dec 2003020830.266.30$1,311
Nov 200309328.804.60$427
Oct 2003021228.174.76$1,009
Sep 2003015126.314.75$717
Aug 2003013329.765.13$682
Jul 2003016029.415.17$827
Jun 2003018328.565.98$1,095
May 2003039526.595.97$2,359
Apr 2003038626.675.41$2,087
Mar 2003033931.146.10$2,067
Feb 2003021333.487.93$1,688
Jan 2003029630.315.58$1,652
Dec 2002022526.914.85$1,092
Nov 2002023924.664.14$989
Oct 2002013026.464.23$550
Sep 200208427.443.64$305
Aug 200207025.963.16$221
Jul 2002010424.583.06$318
Jun 2002010623.733.34$354
May 2002014524.663.58$520
Apr 2002018923.653.51$664
Mar 2002012622.003.10$391
Feb 200206818.222.38$162
Jan 2002021117.172.38$501
Dec 2001017716.932.36$419
Nov 2001017918.072.41$431
Oct 2001017819.782.53$450
Sep 2001016124.262.25$362
Aug 2001021024.873.05$641
Jul 2001016023.933.20$512
Jun 2001017724.563.82$677
May 2001026225.524.31$1,129
Apr 2001021124.685.34$1,126
Mar 2001024224.545.38$1,301
Feb 2001021627.755.77$1,246
Jan 2001022927.478.40$1,923
Dec 2000023826.889.12$2,171
Nov 2000029132.215.66$1,646
Oct 2000024731.235.15$1,271
Sep 2000023531.875.19$1,219
Aug 2000023529.644.54$1,067
Jul 2000023928.534.09$977
Jun 2000022229.304.40$976
May 2000019927.263.68$732
Apr 2000018824.513.12$586
Mar 2000024928.422.86$712
Feb 2000030427.622.73$829
Jan 2000028825.272.48$714
Dec 1999027424.282.42$664
Nov 1999032623.192.43$793
Oct 1999035120.982.80$984
Sep 1999029221.752.62$765
Aug 1999030019.262.88$863
Jul 1999026817.892.37$636
Jun 1999037715.942.36$891
May 1999037015.792.32$859
Apr 1999030915.102.21$682
Mar 1999026012.471.84$478
Feb 199902629.981.82$476
Jan 1999029110.381.90$553
Dec 199803109.201.77$550
Nov 1998029510.892.19$645
Oct 1998029012.421.97$571
Sep 1998022912.592.08$477
Aug 1998025911.301.91$494
Jul 1998031611.742.24$707
Jun 1998028511.242.24$638
May 1998026712.622.21$589
Apr 1998025813.042.51$646
Mar 1998027712.802.31$640
Feb 1998022013.952.30$506
Jan 1998025314.702.15$545
Dec 1997025716.322.41$620
Nov 1997027318.193.09$843
Oct 1997026419.253.15$832
Sep 1997023117.742.95$683
Aug 1997024517.862.55$626
Jul 1997025717.582.25$577
Jun 1997024717.242.26$558
May 1997026618.972.31$614
Apr 1997034917.882.08$727
Mar 1997028818.951.94$558
Feb 1997028720.492.21$633
Jan 1997030723.483.54$1,087
Dec 1996033323.32$0
Nov 1996027921.97$0
Oct 1996020723.31$0
Sep 1996058822.22$0
Aug 1996033920.26$0
Jul 1996032119.55$0
Jun 1996034518.73$0
May 1996038219.43$0
Apr 1996024021.51$0
Mar 1996023519.38$0
Feb 1996024816.98$0
Jan 1996029517.07$0
Dec 1995032017.19$0
Nov 1995033316.00$0
Oct 1995033515.43$0
Sep 1995027016.18$0
Aug 1995034815.92$0
Jul 1995035115.24$0
Jun 1995029016.41$0
May 1995037017.56$0
Apr 1995029617.73$0
Mar 1995042516.44$0
Feb 1995021116.58$0
Jan 1995036515.92$0
Dec 1994046315.03$0
Nov 1994044615.90$0
Oct 1994054915.58$0
Sep 1994045415.29$0
Aug 1994049816.13$0
Jul 1994058717.56$0
Jun 1994029217.09$0
May 1994059115.88$0
Apr 1994047414.14$0
Mar 1994043012.46$0
Feb 1994044012.50$0
Jan 1994050212.66$0
Dec 1993045612.33$0
Nov 1993018814.49$0
Oct 1993041515.85$0
Sep 1993032715.03$0
Aug 1993035115.66$0
Jul 1993042415.46$0
Jun 1993051316.79$0
May 1993046917.68$0
Apr 1993040318.05$0
Mar 1993031318.14$0
Feb 1993061017.90$0
Jan 1993061416.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                   86 Mcf  × $  3.05 =       $262

────────────────────────────────────────────────────
Month total                                     $262

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/99257 is the state's own key, not one this site invented.