Operated by BULLIN, R. E. OPERATING INC. (P-5 106531) in the LEEPER (CLEARFORK, LO) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Oil lease lease 62502District 8AField 52916250Hydrogen sulphide fieldOilCasinghead gasSaveExport
Value, all time
$975 k
Jan 1993 – May 2026
Value, last 12 filed months
$30 k
at the published price for each month
Months reported
401
no gaps in the span
Streams
2
oil, casinghead gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 1 leases and 1 wells, and the rule below applies to all of them.

Discovered
1979-07-06
as the register files it
Field class
Oil
the register's own label
Between wells
no field rule filed
From a lease line
no field rule filed

The register flags this field for hydrogen sulphide. That is a poisonous gas that occurs naturally in some formations. The flag is a property of the field as the Commission records it. It is not a measurement taken at this lease, and it is not a statement that gas is escaping anywhere.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
OilDisposition27,790 bbl$930,687
Casinghead gasProduction15,990 Mcf$44,775
Total$975,461

5,370 Mcf of this lease's gas, across 37 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 33.3995, -102.3534. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

33.39947, -102.35345 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
11,960 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 11,960 ft.

Completions filed
Dec 1993
1 of 1 wells

1 well

42-21932664411,960 ftDec 1993

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (401)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

401 months

May 2026030106.413.05$91
Apr 2026843098.932.87$8,396
Mar 202603089.753.15$94
Feb 202603063.503.75$113
Jan 202603059.138.00$240
Dec 202503056.664.41$132
Nov 20251633058.593.93$9,668
Oct 202503059.383.30$99
Sep 202503062.743.08$92
Aug 202503063.933.01$90
Jul 20251563066.743.32$10,511
Jun 202503066.483.13$94
May 202503060.553.23$97
Apr 202503062.363.54$106
Mar 202503067.704.27$128
Feb 202503070.884.34$130
Jan 202503074.324.28$128
Dec 20241623068.993.12$11,270
Nov 202403069.052.20$66
Oct 202403071.372.28$68
Sep 202403069.612.36$71
Aug 202403075.632.06$62
Jul 202403079.932.15$64
Jun 202403078.082.63$79
May 20241453078.812.20$11,493
Apr 202403084.451.66$50
Mar 202403080.301.55$46
Feb 202403076.091.78$54
Jan 20241583073.023.30$11,636
Dec 202303071.262.61$78
Nov 202303077.892.81$84
Oct 202303085.443.09$93
Sep 20231743089.042.74$15,575
Aug 202303080.522.67$80
Jul 202303074.852.64$79
Jun 202303068.962.26$68
May 202303070.622.23$67
Apr 20231713078.122.24$13,426
Mar 202303072.852.39$72
Feb 202303075.112.47$74
Jan 20231673076.533.39$12,882
Dec 202203076.415.73$172
Nov 202203085.005.65$169
Oct 202203087.185.86$176
Sep 202203084.888.16$245
Aug 202203094.529.13$274
Jul 2022030101.587.54$226
Jun 2022030115.097.98$239
May 2022030109.378.43$253
Apr 2022030104.226.84$205
Mar 2022030108.885.08$152
Feb 202203091.054.86$146
Jan 202203081.844.54$136
Dec 202103071.323.90$117
Nov 202103077.435.24$157
Oct 202103079.795.71$171
Sep 202103069.865.35$161
Aug 20211763066.024.22$11,746
Jul 202103070.783.98$119
Jun 202103069.493.38$101
May 202103063.483.02$91
Apr 202103060.362.76$83
Mar 202103061.302.72$82
Feb 202103057.805.55$166
Jan 202103050.412.81$84
Dec 202003044.642.68$80
Nov 20201703038.772.71$6,672
Oct 202003036.972.48$74
Sep 202003037.091.99$60
Aug 202003039.982.39$72
Jul 202003038.371.83$55
Jun 202003034.901.69$51
May 202003016.921.81$54
Apr 202003014.751.80$54
Mar 202003030.341.86$56
Feb 202003049.881.98$59
Jan 202003057.252.09$63
Dec 201903059.012.30$69
Nov 20193373055.302.75$18,719
Oct 201903053.472.42$73
Sep 201903055.052.66$80
Aug 201903053.112.30$69
Jul 201903056.272.46$74
Jun 201903052.782.49$75
May 201903058.482.74$82
Apr 201903062.632.75$83
Mar 201903056.803.06$92
Feb 201903050.852.79$84
Jan 201903046.033.23$97
Dec 201803046.594.19$126
Nov 201803052.934.24$127
Oct 20181463061.443.40$9,072
Sep 201803059.543.11$93
Aug 201803059.403.07$92
Jul 201803065.142.93$88
Jun 201803060.183.08$92
May 201803065.382.90$87
Apr 201803063.842.90$87
Mar 20181623061.222.79$10,001
Feb 201803061.782.77$83
Jan 201803062.874.01$120
Dec 201703057.272.92$88
Nov 201703055.423.12$94
Oct 20171703049.292.98$8,469
Sep 201703047.523.09$93
Aug 201703045.373.00$90
Jul 20171693043.873.09$7,507
Jun 201703042.493.09$93
May 201703045.373.26$98
Apr 201703047.933.21$96
Mar 201703046.772.98$90
Feb 201703050.452.95$89
Jan 20171643049.413.42$8,206
Dec 201603048.763.72$112
Nov 201603042.492.64$79
Oct 201603046.193.09$93
Sep 201603041.553.10$93
Aug 201603041.442.92$88
Jul 201603041.622.92$88
Jun 20161603045.352.69$7,337
May 201603042.521.99$60
Apr 201603036.561.99$60
Mar 201603033.011.79$54
Feb 20161673026.472.06$4,482
Jan 201603027.352.36$71
Dec 201506032.362.00$120
Nov 201503038.792.17$65
Oct 201503043.552.43$73
Sep 201503042.992.76$83
Aug 201503040.162.87$86
Jul 201503048.152.95$88
Jun 201503056.152.88$86
May 201503055.212.96$89
Apr 201503049.822.71$81
Mar 20151463042.892.93$6,350
Feb 201503044.662.98$89
Jan 201503043.433.10$93
Dec 201403054.693.59$108
Nov 20141683070.464.25$11,965
Oct 201403078.303.90$117
Sep 201403086.164.05$121
Aug 201403089.394.04$121
Jul 20141643096.564.18$15,961
Jun 201403098.164.74$142
May 201403094.734.73$142
Apr 201403095.944.81$144
Mar 201403095.895.06$152
Feb 201403097.406.19$186
Jan 20141653090.404.86$15,062
Dec 201303091.824.35$131
Nov 201303088.853.74$112
Oct 201303097.423.78$113
Sep 2013030104.113.72$112
Aug 2013030104.253.52$106
Jul 201317230102.523.72$17,745
Jun 201303094.403.93$118
May 201303094.834.15$124
Apr 201303093.964.28$128
Mar 201303093.623.91$117
Feb 201303091.233.42$103
Jan 20131653091.603.42$15,217
Dec 201203086.773.42$103
Nov 201203086.953.62$109
Oct 201203089.383.40$102
Sep 201203094.672.92$88
Aug 20121693092.662.91$15,747
Jul 201203085.133.02$91
Jun 201203079.822.52$76
May 201203091.612.49$75
Apr 2012030101.652.00$60
Mar 201216730105.052.22$17,610
Feb 2012030101.102.57$77
Jan 201203098.092.73$82
Dec 201103096.873.24$97
Nov 201103095.723.31$99
Oct 201103084.983.65$109
Sep 201103083.623.99$120
Aug 20111663083.404.15$13,969
Jul 201103094.144.52$136
Jun 201103092.904.64$139
May 201103098.134.40$132
Apr 201117330105.964.33$18,461
Mar 201103096.364.06$122
Feb 201103085.644.18$125
Jan 201103086.504.59$138
Dec 201003085.734.35$130
Nov 201003080.843.80$114
Oct 20101973078.103.51$15,491
Sep 201003072.633.98$119
Aug 201003073.684.42$133
Jul 201003072.554.74$142
Jun 201003070.364.91$147
May 20101693071.124.24$12,146
Apr 201003081.694.12$124
Mar 201003078.394.39$132
Feb 201003073.585.44$163
Jan 201003074.365.96$179
Dec 200903071.445.48$165
Nov 20091503074.593.75$11,301
Oct 200903072.544.11$123
Sep 20091723065.543.06$11,365
Aug 200903067.423.22$97
Jul 200903061.133.46$104
Jun 200903066.163.90$117
May 200903054.743.93$118
Apr 200903046.773.59$108
Mar 200903042.144.06$122
Feb 20091553032.814.63$5,225
Jan 200903035.865.37$161
Dec 20081513037.105.98$5,781
Nov 200803055.496.86$206
Oct 200803075.246.92$208
Sep 2008030101.767.88$236
Aug 2008030114.228.48$254
Jul 200815730131.0811.39$20,921
Jun 2008030131.3313.03$391
May 2008030123.1711.57$347
Apr 200815530110.3110.45$17,412
Mar 2008030101.909.66$290
Feb 200803092.538.77$263
Jan 200803090.388.21$246
Dec 20071673088.337.30$14,970
Nov 200703091.677.29$219
Oct 200703082.856.92$208
Sep 20071723075.846.24$13,232
Aug 200703069.066.39$192
Jul 20071763070.906.39$12,670
Jun 200703062.007.55$226
May 200703058.747.85$235
Apr 200703059.617.81$234
Mar 20071703056.927.30$9,895
Feb 200703055.108.22$246
Jan 200703050.306.73$202
Dec 200603056.656.92$208
Nov 200603054.207.62$229
Oct 200603054.906.01$180
Sep 20061553060.085.04$9,464
Aug 200603068.717.34$220
Jul 200603069.376.34$190
Jun 20061663066.286.38$11,194
May 200603066.016.42$193
Apr 200603064.397.36$221
Mar 20061753056.707.08$10,135
Feb 200603057.597.75$233
Jan 200603060.598.93$268
Dec 20051583054.9413.42$9,083
Nov 200503054.6910.59$318
Oct 200503058.3413.80$414
Sep 200503061.4512.08$362
Aug 20051763061.519.80$11,120
Jul 200503055.697.84$235
Jun 200503052.337.38$221
May 20051503045.226.65$6,983
Apr 200503049.207.36$221
Mar 20051653050.377.15$8,526
Feb 200503045.226.31$189
Jan 200503043.166.32$190
Dec 20041763039.866.75$7,218
Nov 200403045.286.33$190
Oct 200403049.706.52$195
Sep 20041893043.245.28$8,331
Aug 20041533042.375.55$6,649
Jul 20041803038.286.08$7,073
Jun 200403036.106.43$193
May 200403037.486.49$195
Apr 200403034.475.86$176
Mar 20041793034.365.53$6,316
Feb 200403032.455.51$165
Jan 200403032.036.30$189
Dec 20031523030.266.30$4,789
Nov 200303028.804.60$138
Oct 20031493028.174.76$4,340
Sep 200303026.314.75$142
Aug 20031693029.765.13$5,183
Jul 200303029.415.17$155
Jun 200303028.565.98$179
May 20031603026.595.97$4,434
Apr 200303026.675.41$162
Mar 200303031.146.10$183
Feb 20031523033.487.93$5,327
Jan 200303030.315.58$167
Dec 20021763026.914.85$4,882
Nov 200203024.664.14$124
Oct 20021733026.464.23$4,704
Sep 200203027.443.64$109
Aug 200203025.963.16$95
Jul 20021853024.583.06$4,639
Jun 200203023.733.34$100
May 20021693024.663.58$4,275
Apr 200203023.653.51$105
Mar 200203022.003.10$93
Feb 20021713018.222.38$3,187
Jan 200203017.172.38$71
Dec 20011613016.932.36$2,797
Nov 200103018.072.41$72
Oct 20011623019.782.53$3,280
Sep 200103024.262.25$68
Aug 20011643024.873.05$4,170
Jul 200103023.933.20$96
Jun 20011763024.563.82$4,437
May 200103025.524.31$129
Apr 20011593024.685.34$4,084
Mar 20011703024.545.38$4,333
Feb 200103027.755.77$173
Jan 200103027.478.40$252
Dec 20001593026.889.12$4,548
Nov 200003032.215.66$170
Oct 20001683031.235.15$5,401
Sep 20001523031.875.19$5,000
Aug 20001823029.644.54$5,531
Jul 200003028.534.09$123
Jun 20001633029.304.40$4,908
May 200003027.263.68$110
Apr 20001683024.513.12$4,211
Mar 20001733028.422.86$5,002
Feb 200003027.622.73$82
Jan 20001783025.272.48$4,572
Dec 199903024.282.42$73
Nov 19991663023.192.43$3,923
Oct 199903020.982.80$84
Sep 19991813021.752.62$4,015
Aug 199903019.262.88$86
Jul 19991603017.892.37$2,934
Jun 199903015.942.36$71
May 19991783015.792.32$2,880
Apr 199903015.102.21$66
Mar 19991673012.471.84$2,138
Feb 1999191309.981.82$1,961
Jan 199903010.381.90$57
Dec 1998171309.201.77$1,626
Nov 199803010.892.19$66
Oct 19981783012.421.97$2,270
Sep 19981953012.592.08$2,518
Aug 199803011.301.91$57
Jul 19981633011.742.24$1,981
Jun 19981813011.242.24$2,102
May 199803012.622.21$66
Apr 19981763013.042.51$2,370
Mar 19982083012.802.31$2,732
Feb 199803013.952.30$69
Jan 19981793014.702.15$2,696
Dec 199703016.322.41$72
Nov 19971573018.193.09$2,948
Oct 19971913019.253.15$3,771
Sep 19971863017.742.95$3,388
Aug 199703017.862.55$77
Jul 19971603017.582.25$2,880
Jun 19971773017.242.26$3,119
May 19971793018.972.31$3,465
Apr 19971963017.882.08$3,567
Mar 199703018.951.94$58
Feb 19971933020.492.21$4,021
Jan 19971753023.483.54$4,215
Dec 19961493023.32$3,475
Nov 19961773021.97$3,889
Oct 199603023.31$0
Sep 19961683022.22$3,733
Aug 19961763020.26$3,566
Jul 19961783019.55$3,480
Jun 19961603018.73$2,997
May 19961793019.43$3,478
Apr 19961543021.51$3,313
Mar 19961773019.38$3,430
Feb 19961923016.98$3,260
Jan 19961903017.07$3,243
Dec 19952023017.19$3,472
Nov 19951793016.00$2,864
Oct 19951593015.43$2,453
Sep 19951826016.18$2,945
Aug 19951976015.92$3,136
Jul 19951376015.24$2,088
Jun 19953326016.41$5,448
May 19951656017.56$2,897
Apr 19951906017.73$3,369
Mar 19953656016.44$6,001
Feb 19951836016.58$3,034
Jan 19951838015.92$2,913
Dec 19943728015.03$5,591
Nov 199416212015.90$2,576
Oct 199434112015.58$5,313
Sep 199435012015.29$5,352
Aug 199417512016.13$2,823
Jul 199436847517.56$6,462
Jun 199452047517.09$8,887
May 199450247515.88$7,972
Apr 199435147514.14$4,963
Mar 199471247512.46$8,872
Feb 199452047512.50$6,500
Jan 19941,68547512.66$21,332
Dec 199339047512.33$4,809
Nov 19930014.49$0
Oct 19930015.85$0
Sep 19930015.03$0
Aug 19930015.66$0
Jul 19930015.46$0
Jun 19930016.79$0
May 19930017.68$0
Apr 19930018.05$0
Mar 19930018.14$0
Feb 19930017.90$0
Jan 19930016.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Oil                    0 bbl  × $106.41 =         $0
Casinghead gas        30 Mcf  × $  3.05 =        $91

────────────────────────────────────────────────────
Month total                                      $91

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 8A/O/62502 is the state's own key, not one this site invented.