Operated by PRESIDIO PETROLEUM LLC (P-5 676084) in the BUFFALO WALLOW (GRANITE WASH) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 209349District 10Field 131472852 tax incentive programmesCondensateGasSaveExport
Value, all time
$2.0 M
Dec 2004 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
258
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 1,387 leases and 1,388 wells, and the rule below applies to all of them.

Discovered
1974-09-09
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2016-03-29.

The Commission's schedule remark for this field reads: 01-30-2024

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112005-11-03165379
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition3,424 bbl$217,936
GasProduction255,153 Mcf$1,736,414
Total$1,954,350

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 35.6957, -100.2866. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

35.69575, -100.28664 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
12,000 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 12,000 ft.

Completions filed
Dec 2004
1 of 1 wells

1 well

42-2113307110612,000 ftDec 2004

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (258)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

258 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 20170047.933.21$0
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170049.413.42$0
Dec 20160048.763.72$0
Nov 20161331242.492.64$5,683
Oct 20160046.193.09$0
Sep 20160041.553.10$0
Aug 2016011941.442.92$348
Jul 20160041.622.92$0
Jun 201603745.352.69$99
May 201606542.521.99$129
Apr 2016011236.561.99$223
Mar 2016010833.011.79$194
Feb 201606326.472.06$130
Jan 201609327.352.36$220
Dec 2015012432.362.00$248
Nov 2015013938.792.17$301
Oct 2015016343.552.43$396
Sep 2015017142.992.76$472
Aug 2015019440.162.87$557
Jul 2015025448.152.95$748
Jun 2015017356.152.88$499
May 2015019855.212.96$585
Apr 2015020249.822.71$547
Mar 2015010142.892.93$296
Feb 2015014744.662.98$438
Jan 2015022543.433.10$698
Dec 2014024654.693.59$883
Nov 2014018270.464.25$774
Oct 2014024878.303.90$967
Sep 2014026486.164.05$1,068
Aug 2014032689.394.04$1,315
Jul 2014028296.564.18$1,179
Jun 2014128298.164.74$1,434
May 2014034494.734.73$1,626
Apr 2014035095.944.81$1,683
Mar 2014023795.895.06$1,198
Feb 2014083197.406.19$5,146
Jan 2014037890.404.86$1,837
Dec 2013018991.824.35$823
Nov 2013123688.853.74$971
Oct 2013021097.423.78$794
Sep 20131251104.113.72$1,037
Aug 201385305104.253.52$9,936
Jul 20130301102.523.72$1,119
Jun 2013032994.403.93$1,294
May 2013033494.834.15$1,386
Apr 2013028493.964.28$1,216
Mar 2013030193.623.91$1,178
Feb 2013026091.233.42$889
Jan 2013032891.603.42$1,122
Dec 2012027386.773.42$934
Nov 2012016886.953.62$609
Oct 2012024889.383.40$843
Sep 20120994.672.92$26
Aug 2012017292.662.91$500
Jul 2012027085.133.02$816
Jun 2012034579.822.52$869
May 2012115791.612.49$482
Apr 20120383101.652.00$765
Mar 20123516105.052.22$1,462
Feb 20120529101.102.57$1,360
Jan 201219168098.092.73$20,594
Dec 2011079496.873.24$2,572
Nov 2011279595.723.31$2,824
Oct 201111,34484.983.65$4,989
Sep 201131,59083.623.99$6,588
Aug 201141,61883.404.15$7,047
Jul 201151,76994.144.52$8,462
Jun 201161,68792.904.64$8,385
May 201131,63198.134.40$7,479
Apr 201101,636105.964.33$7,089
Mar 201131,67296.364.06$7,073
Feb 201151,57085.644.18$6,991
Jan 2011101,67786.504.59$8,560
Dec 201051,58085.734.35$7,298
Nov 201031,52180.843.80$6,015
Oct 201061,68278.103.51$6,371
Sep 201041,69972.633.98$7,052
Aug 201051,77973.684.42$8,230
Jul 201031,77572.554.74$8,625
Jun 2010121,72770.364.91$9,325
May 2010121,76271.124.24$8,316
Apr 2010111,76181.694.12$8,159
Mar 2010131,89478.394.39$9,331
Feb 2010121,58073.585.44$9,482
Jan 2010111,83774.365.96$11,774
Dec 2009121,92771.445.48$11,424
Nov 2009111,90674.593.75$7,971
Oct 200981,94972.544.11$8,591
Sep 2009171,94865.543.06$7,084
Aug 200902,15767.423.22$6,942
Jul 2009172,22261.133.46$8,737
Jun 2009112,09966.163.90$8,903
May 2009101,89554.743.93$7,987
Apr 200941,73246.773.59$6,401
Mar 200931,56842.144.06$6,491
Feb 20091961,88832.814.63$15,178
Jan 200902,14435.865.37$11,515
Dec 2008187437.105.98$5,261
Nov 200831,62355.496.86$11,301
Oct 200852,21975.246.92$15,736
Sep 200822,495101.767.88$19,857
Aug 200842,780114.228.48$24,040
Jul 200862,956131.0811.39$34,454
Jun 200842,841131.3313.03$37,551
May 20081893,026123.1711.57$58,303
Apr 200842,632110.3110.45$27,958
Mar 200872,239101.909.66$22,351
Feb 2008101,49492.538.77$14,029
Jan 200841,56890.388.21$13,228
Dec 200751,38488.337.30$10,548
Nov 200731,61791.677.29$12,066
Oct 20071921,91982.856.92$29,190
Sep 200782,00975.846.24$13,151
Aug 200732,14369.066.39$13,897
Jul 200722,10270.906.39$13,569
Jun 200731,87062.007.55$14,302
May 20072251,80258.747.85$27,356
Apr 2007111,56759.617.81$12,886
Mar 2007161,68656.927.30$13,222
Feb 200721,56455.108.22$12,960
Jan 200722,00150.306.73$13,561
Dec 200651,69556.656.92$12,010
Nov 200631,48654.207.62$11,482
Oct 200681,78554.906.01$11,174
Sep 20061902,19860.085.04$22,487
Aug 200632,28368.717.34$16,963
Jul 200612,55269.376.34$16,256
Jun 20062032,71466.286.38$30,781
May 200612,89966.016.42$18,692
Apr 200623,49864.397.36$25,876
Mar 200653,88356.707.08$27,786
Feb 20062023,50357.597.75$38,785
Jan 200633,92660.598.93$35,254
Dec 200523,55254.9413.42$47,761
Nov 2005114,29554.6910.59$46,079
Oct 20052034,87158.3413.80$79,042
Sep 200544,79561.4512.08$58,165
Aug 200545,25661.519.80$51,738
Jul 20051895,30555.697.84$52,136
Jun 200505,24952.337.38$38,743
May 20052037,01945.226.65$55,864
Apr 200507,63949.207.36$56,227
Mar 20052088,07750.377.15$68,267
Feb 20051969,72845.226.31$70,265
Jan 20053818,82043.166.32$120,624
Dec 200418514,15139.866.75$102,909

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Nov 2016 — as filed, then multipliedworked
Condensate           133 bbl  × $ 42.49 =     $5,651
Gas                   12 Mcf  × $  2.64 =        $32

────────────────────────────────────────────────────
Month total                                   $5,683

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 10/G/209349 is the state's own key, not one this site invented.