PEAK-BOURASSA

Operated by PRESIDIO PETROLEUM LLC (P-5 676084) in the BUFFALO WALLOW (GRANITE WASH) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 209151District 10Field 131472852 tax incentive programmesCondensateGasSaveExport
Value, all time
$1.6 M
Sep 2004 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
261
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 1,387 leases and 1,388 wells, and the rule below applies to all of them.

Discovered
1974-09-09
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2016-03-29.

The Commission's schedule remark for this field reads: 01-30-2024

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112006-02-28164905
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition5,204 bbl$395,408
GasProduction184,909 Mcf$1,254,400
Total$1,649,808

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 35.6940, -100.2933. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

35.69398, -100.29331 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
12,090 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 12,090 ft.

Completions filed
Sep 2004
1 of 1 wells

1 well

42-2113293320712,090 ftSep 2004

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (261)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

261 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20211063.483.02$63
Apr 20215060.362.76$302
Mar 20215061.302.72$307
Feb 20215057.805.55$289
Jan 20215050.412.81$252
Dec 20205044.642.68$223
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 20170047.933.21$0
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170049.413.42$0
Dec 20160048.763.72$0
Nov 20160042.492.64$0
Oct 20160046.193.09$0
Sep 20160041.553.10$0
Aug 20160041.442.92$0
Jul 20160041.622.92$0
Jun 20160045.352.69$0
May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 20160026.472.06$0
Jan 20160027.352.36$0
Dec 20150332.362.00$6
Nov 20150038.792.17$0
Oct 20151143.552.43$46
Sep 20150042.992.76$0
Aug 20150040.162.87$0
Jul 20150048.152.95$0
Jun 2015010056.152.88$288
May 20150055.212.96$0
Apr 20150049.822.71$0
Mar 20151142.892.93$46
Feb 20150044.662.98$0
Jan 20150043.433.10$0
Dec 20140054.693.59$0
Nov 20140070.464.25$0
Oct 20140078.303.90$0
Sep 20140086.164.05$0
Aug 2014054389.394.04$2,191
Jul 2014062496.564.18$2,608
Jun 2014158398.164.74$2,860
May 2014060494.734.73$2,855
Apr 2014056095.944.81$2,693
Mar 2014060795.895.06$3,069
Feb 201439052597.406.19$41,237
Jan 2014042190.404.86$2,046
Dec 2013144091.824.35$2,008
Nov 2013146288.853.74$1,816
Oct 2013058397.423.78$2,203
Sep 20131596104.113.72$2,320
Aug 20130595104.253.52$2,096
Jul 20131563102.523.72$2,196
Jun 2013150794.403.93$2,089
May 201317747694.834.15$18,760
Apr 201339547093.964.28$39,127
Mar 2013045693.623.91$1,784
Feb 2013038991.233.42$1,330
Jan 2013044491.603.42$1,518
Dec 2012043986.773.42$1,501
Nov 2012046386.953.62$1,678
Oct 2012037089.383.40$1,258
Sep 20120094.672.92$0
Aug 2012643792.662.91$1,827
Jul 201222056285.133.02$20,426
Jun 2012017579.822.52$441
May 201209791.612.49$241
Apr 20120152101.652.00$304
Mar 20120198105.052.22$440
Feb 20120178101.102.57$458
Jan 2012521798.092.73$1,084
Dec 2011020596.873.24$664
Nov 2011023695.723.31$781
Oct 2011023484.983.65$854
Sep 2011026183.623.99$1,040
Aug 2011024583.404.15$1,017
Jul 2011027694.144.52$1,247
Jun 201111732492.904.64$12,373
May 2011034298.134.40$1,506
Apr 20110397105.964.33$1,720
Mar 2011043096.364.06$1,745
Feb 2011058085.644.18$2,424
Jan 2011030686.504.59$1,404
Dec 2010029585.734.35$1,283
Nov 2010038380.843.80$1,454
Oct 2010041978.103.51$1,470
Sep 2010043572.633.98$1,731
Aug 2010047373.684.42$2,090
Jul 2010259272.554.74$2,949
Jun 2010078270.364.91$3,840
May 2010489371.124.24$4,067
Apr 20102051,25381.694.12$21,912
Mar 20102121,22578.394.39$21,995
Feb 201020795873.585.44$20,445
Jan 201014333274.365.96$12,614
Dec 2009034071.445.48$1,864
Nov 2009036874.593.75$1,381
Oct 200918240572.544.11$14,867
Sep 2009041465.543.06$1,269
Aug 2009045767.423.22$1,471
Jul 2009050661.133.46$1,753
Jun 2009051866.163.90$2,018
May 2009061754.743.93$2,422
Apr 2009066846.773.59$2,396
Mar 2009066242.144.06$2,687
Feb 2009282732.814.63$3,897
Jan 2009441635.865.37$2,378
Dec 2008446437.105.98$2,922
Nov 2008056955.496.86$3,904
Oct 2008068875.246.92$4,762
Sep 20080837101.767.88$6,593
Aug 200821,190114.228.48$10,323
Jul 20082001,449131.0811.39$42,719
Jun 200841,647131.3313.03$21,990
May 20086854123.1711.57$10,623
Apr 20083830110.3110.45$9,008
Mar 20081951,111101.909.66$30,607
Feb 2008590192.538.77$8,365
Jan 20083481,55790.388.21$44,229
Dec 2007194888.337.30$7,011
Nov 20071911,56891.677.29$28,942
Oct 2007493282.856.92$6,783
Sep 2007090575.846.24$5,651
Aug 200701,19769.066.39$7,646
Jul 200721,67970.906.39$10,867
Jun 200751,89562.007.55$14,614
May 2007121,67258.747.85$13,824
Apr 2007399459.617.81$7,937
Mar 20071542,02056.927.30$23,516
Feb 200731,75755.108.22$14,601
Jan 200702,07950.306.73$13,985
Dec 200632,30056.656.92$16,082
Nov 20062092,44854.207.62$29,975
Oct 2006122,38954.906.01$15,026
Sep 200662,19160.085.04$11,397
Aug 200622,12668.717.34$15,742
Jul 200601,03469.376.34$6,558
Jun 2006066366.286.38$4,233
May 2006046266.016.42$2,968
Apr 20062021,03964.397.36$20,654
Mar 200601,58956.707.08$11,255
Feb 200611,80357.597.75$14,033
Jan 200602,34360.598.93$20,931
Dec 200511,84154.9413.42$24,753
Nov 20051812,74054.6910.59$38,911
Oct 200523,26658.3413.80$45,174
Sep 200513,22361.4512.08$38,992
Aug 200503,61861.519.80$35,445
Jul 200503,69455.697.84$28,974
Jun 20051923,67752.337.38$37,187
May 200504,74745.226.65$31,573
Apr 200594,95049.207.36$36,877
Mar 20052575,08450.377.15$49,321
Feb 20052275,08245.226.31$42,342
Jan 2005516,03443.166.32$40,349
Dec 20042187,59739.866.75$59,977
Nov 200409,37345.286.33$59,335
Oct 200418317,42249.706.52$122,601
Sep 2004020,51643.245.28$108,404

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2021 — as filed, then multipliedworked
Condensate             1 bbl  × $ 63.48 =        $63
Gas                    0 Mcf  × $  3.02 =         $0

────────────────────────────────────────────────────
Month total                                      $63

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 10/G/209151 is the state's own key, not one this site invented.