BROWN SW 223

Operated by BRP ENERGY, LLC (P-5 41519) in the GEASLIN (WOLFCAMP) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 192657District 7CField 34300700CondensateGasSaveExport
Value, all time
$251 k
Oct 2002 – Nov 2023
Value, last 12 filed months
$0
at the published price for each month
Months reported
254
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 169 leases and 169 wells, and the rule below applies to all of them.

Discovered
1995-05-19
as the register files it
Field class
Oil and gas
the register's own label
Between wells
933 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2001-07-24.

The Commission's schedule remark for this field reads: 8000FT AS SHOWN ON THE LOG OF THE GEASLIN 198 LEASE, WELL NO. 1.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition55 bbl$3,486
GasProduction40,462 Mcf$247,816
Total$251,302

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.3556, -101.8987. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.35563, -101.89873 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
7,562 ft
1 wells filed one
Completion to plug
21.1 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,562 ft.

Completions filed
Oct 2002
1 of 1 wells
Plug dates filed
Nov 2023
1 of 1 wells

Last completion to plug: a median of 21.1 years across the 1 well that filed both dates, with the middle half between 21.1 years and 21.1 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-44330942127,562 ftOct 2002Nov 2023Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (254)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

254 months

Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202230108.885.08$327
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20192256.803.06$120
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20184460.183.08$253
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 20170047.933.21$0
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170049.413.42$0
Dec 20160048.763.72$0
Nov 20160042.492.64$0
Oct 20160046.193.09$0
Sep 20160041.553.10$0
Aug 20160041.442.92$0
Jul 20160041.622.92$0
Jun 20160045.352.69$0
May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 20160026.472.06$0
Jan 20160027.352.36$0
Dec 20150032.362.00$0
Nov 20150038.792.17$0
Oct 20151143.552.43$46
Sep 20150042.992.76$0
Aug 20150040.162.87$0
Jul 20150048.152.95$0
Jun 20150056.152.88$0
May 20150055.212.96$0
Apr 201504449.822.71$119
Mar 201506542.892.93$191
Feb 201503844.662.98$113
Jan 2015010543.433.10$326
Dec 201406154.693.59$219
Nov 201404770.464.25$200
Oct 201408178.303.90$316
Sep 201409686.164.05$388
Aug 201403489.394.04$137
Jul 201405496.564.18$226
Jun 201408998.164.74$422
May 201405894.734.73$274
Apr 201408595.944.81$409
Mar 201404395.895.06$217
Feb 201408497.406.19$520
Jan 201408490.404.86$408
Dec 201306391.824.35$274
Nov 201303488.853.74$127
Oct 201307097.423.78$265
Sep 2013045104.113.72$167
Aug 2013043104.253.52$151
Jul 201301102.523.72$4
Jun 20130094.403.93$0
May 20130194.834.15$4
Apr 20130193.964.28$4
Mar 20130293.623.91$8
Feb 20130091.233.42$0
Jan 20130091.603.42$0
Dec 201201486.773.42$48
Nov 20120586.953.62$18
Oct 201201389.383.40$44
Sep 20120594.672.92$15
Aug 20120392.662.91$9
Jul 201204585.133.02$136
Jun 201201279.822.52$30
May 201205091.612.49$124
Apr 2012080101.652.00$160
Mar 2012086105.052.22$191
Feb 2012093101.102.57$239
Jan 201209098.092.73$246
Dec 201109096.873.24$292
Nov 201109095.723.31$298
Oct 201109184.983.65$332
Sep 201108483.623.99$335
Aug 201109283.404.15$382
Jul 201109594.144.52$429
Jun 201109492.904.64$436
May 201109998.134.40$436
Apr 2011095105.964.33$412
Mar 2011010096.364.06$406
Feb 201109285.644.18$385
Jan 2011010186.504.59$463
Dec 2010010285.734.35$443
Nov 2010010180.843.80$383
Oct 2010010678.103.51$372
Sep 2010010372.633.98$410
Aug 2010010773.684.42$473
Jul 2010010972.554.74$516
Jun 2010010570.364.91$516
May 2010011171.124.24$470
Apr 2010011081.694.12$454
Mar 2010011478.394.39$500
Feb 2010010573.585.44$571
Jan 2010011574.365.96$686
Dec 2009011771.445.48$642
Nov 2009011474.593.75$428
Oct 2009012072.544.11$493
Sep 2009012065.543.06$368
Aug 2009012367.423.22$396
Jul 2009012661.133.46$437
Jun 2009012566.163.90$487
May 2009013554.743.93$530
Apr 2009013446.773.59$481
Mar 2009014242.144.06$576
Feb 2009013232.814.63$612
Jan 2009013335.865.37$714
Dec 2008014137.105.98$843
Nov 2008013555.496.86$926
Oct 2008019875.246.92$1,371
Sep 2008064101.767.88$504
Aug 20080159114.228.48$1,349
Jul 20080163131.0811.39$1,856
Jun 20080155131.3313.03$2,020
May 20080166123.1711.57$1,921
Apr 20080170110.3110.45$1,777
Mar 20080176101.909.66$1,701
Feb 2008017392.538.77$1,517
Jan 2008018590.388.21$1,518
Dec 2007018788.337.30$1,365
Nov 2007018991.677.29$1,378
Oct 2007019982.856.92$1,377
Sep 2007019875.846.24$1,236
Aug 2007021069.066.39$1,341
Jul 2007021770.906.39$1,386
Jun 2007023362.007.55$1,759
May 2007021958.747.85$1,718
Apr 2007122859.617.81$1,839
Mar 2007024456.927.30$1,782
Feb 2007023755.108.22$1,947
Jan 2007427250.306.73$2,031
Dec 2006028156.656.92$1,944
Nov 2006027054.207.62$2,057
Oct 2006129754.906.01$1,841
Sep 2006129860.085.04$1,561
Aug 20062433068.717.34$4,071
Jul 2006134569.376.34$2,258
Jun 2006031766.286.38$2,024
May 2006031466.016.42$2,017
Apr 2006133064.397.36$2,493
Mar 2006033756.707.08$2,387
Feb 2006434257.597.75$2,881
Jan 2006036360.598.93$3,243
Dec 2005038654.9413.42$5,178
Nov 2005138254.6910.59$4,099
Oct 2005040058.3413.80$5,518
Sep 2005039761.4512.08$4,795
Aug 2005043061.519.80$4,213
Jul 2005142555.697.84$3,389
Jun 2005042552.337.38$3,137
May 2005245645.226.65$3,123
Apr 2005039249.207.36$2,885
Mar 2005037950.377.15$2,712
Feb 2005014945.226.31$940
Jan 2005023543.166.32$1,486
Dec 2004030039.866.75$2,025
Nov 2004029745.286.33$1,880
Oct 2004242649.706.52$2,875
Sep 2004037643.245.28$1,987
Aug 2004042642.375.55$2,365
Jul 2004045338.286.08$2,756
Jun 2004247136.106.43$3,102
May 2004051937.486.49$3,371
Apr 2004051834.475.86$3,035
Mar 2004051934.365.53$2,870
Feb 2004052232.455.51$2,876
Jan 2004058232.036.30$3,666
Dec 2003065530.266.30$4,128
Nov 2003063528.804.60$2,918
Oct 2003068428.174.76$3,256
Sep 2003078426.314.75$3,724
Aug 2003082229.765.13$4,217
Jul 2003077729.415.17$4,018
Jun 2003085128.565.98$5,092
May 200301,04826.595.97$6,259
Apr 200301,15126.675.41$6,224
Mar 200301,29331.146.10$7,882
Feb 200301,10133.487.93$8,726
Jan 200301,43130.315.58$7,988
Dec 200202,13026.914.85$10,339
Nov 200203,13024.664.14$12,949
Oct 20020026.464.23$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Mar 2022 — as filed, then multipliedworked
Condensate             3 bbl  × $108.88 =       $327
Gas                    0 Mcf  × $  5.08 =         $0

────────────────────────────────────────────────────
Month total                                     $327

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/192657 is the state's own key, not one this site invented.