WILSON, DUKE 187

Operated by UPP OPERATING, LLC (P-5 875310) in the SAWYER (CANYON) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 204686District 7CField 812673332 tax incentive programmesCondensateGasSaveExport
Value, all time
$3.2 M
Jul 2003 – May 2026
Value, last 12 filed months
$45 k
at the published price for each month
Months reported
275
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112005-07-12153031
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition147 bbl$11,046
GasProduction586,585 Mcf$3,174,277
Total$3,185,324

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.4267, -100.7826. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.42669, -100.78259 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
8,650 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 8,650 ft.

Completions filed
Jul 2003
1 of 1 wells

1 well

42-43536339138,650 ftJul 2003

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (275)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

275 months

May 20262980106.413.05$3,198
Apr 2026495498.932.87$3,133
Mar 2026498389.753.15$3,455
Feb 2026489763.503.75$3,618
Jan 2026093959.138.00$7,510
Dec 202561,00256.664.41$4,762
Nov 2025298358.593.93$3,977
Oct 202541,02559.383.30$3,625
Sep 2025098662.743.08$3,034
Aug 2025396063.933.01$3,086
Jul 2025196566.743.32$3,266
Jun 2025089066.483.13$2,785
May 2025192560.553.23$3,050
Apr 2025590362.363.54$3,511
Mar 2025393167.704.27$4,177
Feb 2025283470.884.34$3,762
Jan 2025290974.324.28$4,038
Dec 2024193968.993.12$3,000
Nov 2024191769.052.20$2,085
Oct 2024294171.372.28$2,290
Sep 2024392869.612.36$2,403
Aug 2024197675.632.06$2,090
Jul 2024397879.932.15$2,339
Jun 2024194978.082.63$2,578
May 2024198278.812.20$2,238
Apr 2024596684.451.66$2,025
Mar 202411,00480.301.55$1,632
Feb 2024394376.091.78$1,910
Jan 2024391673.023.30$3,240
Dec 202331,01171.262.61$2,853
Nov 2023197077.892.81$2,801
Oct 202311,01785.443.09$3,225
Sep 202301,00289.042.74$2,741
Aug 202301,03980.522.67$2,777
Jul 2023085374.852.64$2,253
Jun 2023092668.962.26$2,091
May 2023092970.622.23$2,069
Apr 2023099278.122.24$2,220
Mar 202301,04972.852.39$2,510
Feb 2023092775.112.47$2,286
Jan 2023088076.533.39$2,981
Dec 2022096076.415.73$5,500
Nov 2022091785.005.65$5,178
Oct 2022086187.185.86$5,049
Sep 2022091984.888.16$7,502
Aug 2022088894.529.13$8,105
Jul 20220940101.587.54$7,090
Jun 20220734115.097.98$5,855
May 202201,092109.378.43$9,209
Apr 202201,064104.226.84$7,275
Mar 202201,105108.885.08$5,609
Feb 2022097391.054.86$4,728
Jan 202201,07681.844.54$4,883
Dec 202101,10371.323.90$4,301
Nov 202101,08677.435.24$5,687
Oct 202101,15379.795.71$6,588
Sep 2021097669.865.35$5,223
Aug 202101,13266.024.22$4,778
Jul 202101,13770.783.98$4,528
Jun 202101,15969.493.38$3,918
May 202101,13063.483.02$3,410
Apr 202101,11860.362.76$3,084
Mar 202101,25661.302.72$3,412
Feb 2021093657.805.55$5,193
Jan 202101,12350.412.81$3,156
Dec 202001,07144.642.68$2,865
Nov 202001,06938.772.71$2,893
Oct 202001,13136.972.48$2,803
Sep 202001,11037.091.99$2,210
Aug 202001,03539.982.39$2,469
Jul 2020083638.371.83$1,526
Jun 202001,00634.901.69$1,700
May 2020075716.921.81$1,374
Apr 2020093514.751.80$1,687
Mar 202001,03830.341.86$1,927
Feb 2020096549.881.98$1,911
Jan 202001,03857.252.09$2,174
Dec 201901,01659.012.30$2,341
Nov 201901,01555.302.75$2,792
Oct 201901,02953.472.42$2,489
Sep 201901,07755.052.66$2,862
Aug 201901,00953.112.30$2,325
Jul 201901,05956.272.46$2,605
Jun 201901,03652.782.49$2,581
May 201901,06458.482.74$2,916
Apr 201901,02662.632.75$2,822
Mar 201901,05456.803.06$3,227
Feb 2019096750.852.79$2,700
Jan 201901,06246.033.23$3,428
Dec 201801,04446.594.19$4,370
Nov 2018097452.934.24$4,127
Oct 201811,19561.443.40$4,122
Sep 201801,18559.543.11$3,683
Aug 2018092759.403.07$2,843
Jul 201801,07365.142.93$3,146
Jun 201801,14460.183.08$3,520
May 201801,24265.382.90$3,603
Apr 201801,19863.842.90$3,475
Mar 201801,26061.222.79$3,511
Feb 201801,15261.782.77$3,187
Jan 201801,29262.874.01$5,180
Dec 201701,14157.272.92$3,333
Nov 2017198455.423.12$3,124
Oct 2017186649.292.98$2,633
Sep 2017189947.523.09$2,823
Aug 201711,14045.373.00$3,470
Jul 201701,04143.873.09$3,214
Jun 2017462842.493.09$2,109
May 201711,31245.373.26$4,327
Apr 201711,44247.933.21$4,679
Mar 201721,54346.772.98$4,697
Feb 2017258750.452.95$1,834
Jan 201711,10649.413.42$3,831
Dec 2016174548.763.72$2,822
Nov 2016182542.492.64$2,224
Oct 201611,37546.193.09$4,295
Sep 201601,34841.553.10$4,180
Aug 201611,39741.442.92$4,127
Jul 201601,44641.622.92$4,229
Jun 201611,33745.352.69$3,636
May 201601,38842.521.99$2,764
Apr 201601,42036.561.99$2,827
Mar 201621,55933.011.79$2,863
Feb 201601,28926.472.06$2,660
Jan 201601,31327.352.36$3,104
Dec 2015195932.362.00$1,952
Nov 201511,49038.792.17$3,268
Oct 201511,46743.552.43$3,603
Sep 201511,46342.992.76$4,079
Aug 201511,53140.162.87$4,438
Jul 201511,51348.152.95$4,504
Jun 201501,46456.152.88$4,221
May 201501,64755.212.96$4,868
Apr 201501,61049.822.71$4,358
Mar 201501,05242.892.93$3,087
Feb 201501,02244.662.98$3,042
Jan 201501,27943.433.10$3,966
Dec 201401,50054.693.59$5,387
Nov 201401,55270.464.25$6,599
Oct 201401,61778.303.90$6,308
Sep 201401,58986.164.05$6,428
Aug 201401,64789.394.04$6,646
Jul 201411,65496.564.18$7,010
Jun 201401,59598.164.74$7,555
May 201401,65294.734.73$7,808
Apr 201401,60395.944.81$7,709
Mar 201401,64795.895.06$8,329
Feb 201401,51397.406.19$9,369
Jan 201401,58290.404.86$7,690
Dec 201301,69891.824.35$7,394
Nov 201301,68988.853.74$6,314
Oct 201301,76697.423.78$6,674
Sep 201301,702104.113.72$6,328
Aug 201301,767104.253.52$6,224
Jul 201301,797102.523.72$6,681
Jun 201301,74494.403.93$6,860
May 201301,81994.834.15$7,547
Apr 201301,79393.964.28$7,679
Mar 201301,86593.623.91$7,298
Feb 201301,70291.233.42$5,821
Jan 201301,91091.603.42$6,532
Dec 201201,95686.773.42$6,690
Nov 201201,94586.953.62$7,051
Oct 201201,89289.383.40$6,432
Sep 201201,91094.672.92$5,574
Aug 201202,00992.662.91$5,842
Jul 201202,03685.133.02$6,150
Jun 201201,96779.822.52$4,955
May 201202,04491.612.49$5,086
Apr 201202,033101.652.00$4,059
Mar 201202,026105.052.22$4,502
Feb 201201,978101.102.57$5,084
Jan 201202,17198.092.73$5,936
Dec 201102,23296.873.24$7,231
Nov 201102,19895.723.31$7,278
Oct 201102,22884.983.65$8,129
Sep 201102,16683.623.99$8,633
Aug 201102,26683.404.15$9,402
Jul 201102,28194.144.52$10,304
Jun 201102,21092.904.64$10,254
May 2011442,33498.134.40$14,599
Apr 201102,248105.964.33$9,741
Mar 201102,48496.364.06$10,078
Feb 201101,72285.644.18$7,198
Jan 201102,48986.504.59$11,421
Dec 201002,18985.734.35$9,517
Nov 201002,42280.843.80$9,192
Oct 201002,59878.103.51$9,116
Sep 201002,45172.633.98$9,754
Aug 201002,56973.684.42$11,353
Jul 201002,66572.554.74$12,623
Jun 201002,44870.364.91$12,021
May 201002,41371.124.24$10,220
Apr 201002,53881.694.12$10,463
Mar 201002,73478.394.39$11,999
Feb 201002,51873.585.44$13,704
Jan 201002,74974.365.96$16,395
Dec 200902,86571.445.48$15,711
Nov 200902,80374.593.75$10,515
Oct 200902,88672.544.11$11,862
Sep 200902,83765.543.06$8,695
Aug 200902,92867.423.22$9,424
Jul 200902,96761.133.46$10,279
Jun 200902,72766.163.90$10,622
May 200902,89654.743.93$11,369
Apr 200902,83146.773.59$10,156
Mar 200902,98442.144.06$12,112
Feb 200902,75832.814.63$12,778
Jan 200903,09435.865.37$16,618
Dec 200803,16337.105.98$18,906
Nov 200803,13255.496.86$21,487
Oct 200803,14475.246.92$21,763
Sep 200803,159101.767.88$24,884
Aug 200803,356114.228.48$28,469
Jul 200803,409131.0811.39$38,827
Jun 200803,326131.3313.03$43,347
May 200803,526123.1711.57$40,811
Apr 200803,460110.3110.45$36,174
Mar 200803,439101.909.66$33,235
Feb 200803,49192.538.77$30,618
Jan 200803,89590.388.21$31,961
Dec 2007050288.337.30$3,666
Nov 200703,21691.677.29$23,450
Oct 200703,67682.856.92$25,445
Sep 200703,21475.846.24$20,069
Aug 200703,85269.066.39$24,606
Jul 200704,14470.906.39$26,472
Jun 200704,05662.007.55$30,617
May 200703,84958.747.85$30,200
Apr 200703,95859.617.81$30,893
Mar 200703,57956.927.30$26,134
Feb 200703,45155.108.22$28,353
Jan 200703,96850.306.73$26,692
Dec 200604,11556.656.92$28,469
Nov 200604,04354.207.62$30,797
Oct 200604,21454.906.01$25,342
Sep 200604,10560.085.04$20,678
Aug 200604,13968.717.34$30,380
Jul 200604,19069.376.34$26,576
Jun 200604,24066.286.38$27,068
May 200604,37266.016.42$28,090
Apr 200604,12964.397.36$30,391
Mar 200604,31756.707.08$30,577
Feb 200603,91157.597.75$30,315
Jan 200604,47960.598.93$40,012
Dec 200504,68654.9413.42$62,865
Nov 200504,77754.6910.59$50,581
Oct 200505,14958.3413.80$71,034
Sep 200505,01961.4512.08$60,625
Aug 200504,33561.519.80$42,469
Jul 200504,88455.697.84$38,308
Jun 200505,08552.337.38$37,533
May 200505,37345.226.65$35,737
Apr 200505,30649.207.36$39,055
Mar 200505,25050.377.15$37,563
Feb 200504,98045.226.31$31,433
Jan 200505,57643.166.32$35,253
Dec 200406,64139.866.75$44,834
Nov 200405,63345.286.33$35,659
Oct 200405,93449.706.52$38,661
Sep 200406,07743.245.28$32,110
Aug 200405,12042.375.55$28,419
Jul 200404,13838.286.08$25,176
Jun 200404,41236.106.43$28,382
May 200404,18337.486.49$27,167
Apr 200404,11734.475.86$24,119
Mar 200404,20434.365.53$23,249
Feb 200404,49432.455.51$24,760
Jan 200402,50332.036.30$15,768
Dec 200305,48630.266.30$34,571
Nov 200305,63428.804.60$25,889
Oct 200305,91728.174.76$28,163
Sep 200306,28826.314.75$29,864
Aug 200307,50529.765.13$38,499
Jul 200302,90529.415.17$15,021

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             2 bbl  × $106.41 =       $213
Gas                  980 Mcf  × $  3.05 =     $2,985

────────────────────────────────────────────────────
Month total                                   $3,198

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/204686 is the state's own key, not one this site invented.